2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
The contractor has completed resurfacing operations and will be finalizing striping and utility raising activities. Traffic control will vary throughout the corridor. Slow down and expect delays.
PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Monday (10/3/2022)
Utility Adjustments
– Northwood Boulevard: Tahoe Boulevard to Village Boulevard
– Incline Way: Country Club Drive to Southwood Boulevard
– Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Tuesday (10/4/2022)
No work
Wednesday (10/5/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Various project streets thermos punch list
Thursday (10/6/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Various project streets thermos punch list
Friday (10/7/2022)
No work
Note: This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871
Beginning the week of September 26th Q&D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Lane closures will be in place for this work.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- Drivers may see daily intermittent shoulder and lane closures:
- Pyramid Way – between 9:00 a.m. – 2:00 p.m.
- Sullivan Lane and Rock Boulevard – during working hours
- Rock Boulevard and 12th Street might have some intersection closures with detours
- Construction crews working on Saturdays from September 24th through November 26th
- Underground work including lighting conduits, storm drain, and install privacy wall (post and panels)
- Traffic Swap (to new pavement) north side of Oddie Boulevard
- One lane in each direction will be maintained along Oddie Boulevard
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139
Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.
Peckham Lane between South Virginia Street and Baker Lane will be closed from 9/26 to 9/30 for emergency work on the Cochran Ditch. Business access to Atlantis and Old Town Mall will be provided via. South Virginia Street.
SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
Lane and shoulder closures will be in place.
SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881
Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.
Crews will be working Friday night (September 30) starting at 4:00 p.m. through Saturday morning at 6:00 a.m. During this time, single lane closures will occur on Sparks Boulevard between Lincoln Way and I-80. Drivers can expect slow moving traffic and delays through the work zone. Use of alternative routes are encouraged.
Starting Friday at 9:00 p.m. the I-80 eastbound and westbound ramps from Sparks Boulevard will be closed. Eastbound traffic will be detoured to Vista Boulevard. The northbound ramp will remain open. All ramps will be reopened by 6:00 a.m. Saturday.
Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.
TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871
Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Lane, shoulder closures and detours will be in place. The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting spring 2023.
TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871
Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022. Lane and shoulder closures will be in place during work hours.