Weekly Traffic Control Report

September 19, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are

Friday 9/20
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Mesa Park Drive: Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Drive to Leroy Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Mesa Park Drive: Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Drive to Leroy Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Saturday 9/21
NO WORK SCHEDULED

Sunday 9/22
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Mesa Park Drive: Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Drive to Leroy Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Monday 9/23
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Mesa Park Drive: Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Drive to Leroy Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Tuesday 9/24
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Wednesday 9/25
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Thursday 9/26
Slurry Seal
Plumb Lane: Daniel Webster Drive to Arlington Avenue

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Plumb Lane: Daniel Webster Drive to Arlington Avenue
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Friday 9/27
Slurry Seal
Plumb Lane: Daniel Webster Drive to Arlington Avenue

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Plumb Lane: Daniel Webster Drive to Arlington Avenue
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

  • New traffic signal at the intersection of N Virginia and Lemmon Drive.
  • Construction is on hold until signal equipment arrives mid-November.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

Construction closures and detours for the project will continue the week of September 16. The project is expected to be complete by September 30.
Lake Street will be closed to through traffic from the Truckee River bridge to Second Street. Northbound traffic will be detoured at Mill Street to Wells Avenue to Kuenzli Street and at Liberty Street to Center Street. Southbound traffic will be detoured at Second Street to Virginia Street to Liberty Street to Sinclair Street. Businesses within the closure will be provided southbound access at 2nd Street to westbound 1st Street.
1st Street will be closed to through traffic from Center Street to Lake Street. Businesses within the closure will be provided southbound access at 2nd Street to westbound at 1st Street. Drivers will be able to access the Cal Neva parking garage using Second Street to Lover’s Lane Alley.
All detours will be marked.
This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

To learn more, please visit detours map.

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

North Hills Blvd:

  • Demolition, sidewalk and drainage work with one lane closure.
  • Two-way traffic maintained at all times.
  • Please share the road with bicyclists.
  • Between Golden Valley Rd and Beckwourth Dr:
    • Traffic is shifted using the center turn lane as a travel lane.
  • Between Beckwourth Dr and Buck Dr:
    • One lane-two way traffic with flaggers.
    • Starting Monday September 30 – northbound lane closure, only southbound traffic allowed.

Hunter Lake/Foster Dr:

  • Demolition, sidewalk and drainage work with one lane closure at intersection.
  • Two-way traffic maintained at all times.

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

Ralston St:

  • Between University Terrace and 11th St:
    • Construction is in progress through October 3, with concrete removal and replacement of sidewalk, curb/gutters, and roadway reconstruction. Traffic controls are in place along Ralston St.
  • Parking is prohibited within the Ralston St construction zones 7 am – 7 pm, Monday through Friday 8/5 thru 10/1.
  • During construction, access for trash pickup is provided on Tuesdays – place Green Waste cans out for pickup. For street parking use nearby side streets; please adhere to the “no parking” restrictions.

Ohm Place:

  • Construction is in progress.
  • Full closure of Ohm Place is in effect through the beginning of October. Traffic controls will be in place with business detours for NV Energy offices.

 

SPARKS CONSOLIDATED 19-01 – 15TH STREET, FRANKLIN WAY, HULDA COURT, AND EL RANCHO DRIVE

Starting September 16, 2019, at 7:00 a.m. through Saturday September 21, 2019:
Drivers can expect the following road and lane closures. All detours will be marked.

15th Street C Street to Prater Way:

  • Street will be closed to through traffic from C Street to Prater Way during raising utilities and striping. Northbound traffic will be detoured at C Street to 16th Street to Prater Way, or to at Victorian Avenue to Pyramid Way to Prater Way. Southbound traffic will be detoured at Prater Way to 16th Street to C Street or to Pyramid Way to Victorian Avenue. Businesses and residences within the closure will be provided southbound access from Prater Way and Northbound access from Victorian Avenue.
  • Franklin Way 15th Street C Street to Prater Way:
    Street will be closed to northbound traffic from Greg Street to Spice Island Drive during roadway removal.  Nouthbound traffic will be detoured at Spice Island Drive to Purina Way to Greg Street.

To learn more, please visit detours map.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Construction is occurring within the Midtown areas.

  • Starting September 23, 2019 construction will continue northward on the western side of Virginia St to Mary St/Center St from Plumb Ln.
  • Between Plumb Ln and Mary St/Center St:
    • Traffic will be reduced to southbound only, northbound traffic will be detoured at Regency Wy to Center St.
  • The following side streets are also under construction and closed to through traffic, local access is provided:
    • Cheney St- between Virginia St and Center St
    • Stewart St – between Virginia St and Center St
    • Caliente St – between Virginia St and Haskell St

For the most up to date information on traffic control, please visit the Virginia Street Website.  

 

For the most up to date information on traffic control, please visit the Virginia Street Website.  

See weekly traffic report archive