2023 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
**Note: This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Sunday 9/17/2023
Pavement Striping 7pm – 7am
Various Project Streets – 2nd Coat Striping
Crack Seal 7pm – 7am
Moya Boulevard: Red Rock Road to Echo Avenue
Eagle Canyon Drive: Pyramid Hwy to Calle De La Plata
David Allen Parkway: Kiley Parkway to Fortunato Loop
Vista Boulevard: Brierly Way to Wingfield Hills Drive
E Greenbrae Drive: McCarran Boulevard to Howard Drive
El Rancho Drive: Clear Acre Lane to Moorpark Court
Monday 9/18/2023
Micro-Surfacing – Slurry
Plaza Street: Virginia Street to Lake Street
Pavement Striping 7pm – 7am
Plaza Street: Virginia Street to Lake Street
Various Project Streets – 2nd Coat Striping
Crack Seal 7pm – 7am
E Greenbrae Drive: McCarran Boulevard to Howard Drive
El Rancho Drive: Clear Acre Lane to Moorpark Court
Lemmon Drive: Virginia Street to US 395
Silver Lake Road: Peppermint Drive to Sky Vista Parkway
Red Rock Road: US395 to CA/NV State Line
Tuesday 9/19/2023
Pavement Striping 7pm – 7am
Various Project Streets – 2nd Coat Striping
Crack Seal 7pm – 7am
E Greenbrae Drive: McCarran Boulevard to Howard Drive
El Rancho Drive: Clear Acre Lane to Moorpark Court
Lemmon Drive: Virginia Street to US 395
Silver Lake Road: Peppermint Drive to Sky Vista Parkway
Red Rock Road: US395 to CA/NV State Line
South Verdi Road: South Verdi Court to Bridge Street
Boomtown Garson Road: Cabela Drive to US I80
Cabela Drive: Boomtown Garson Road to South Verdi Road
Wednesday 9/20/2023
Pavement Striping 7pm – 7am
Various Project Streets – 2nd Coat Striping
Crack Seal 7pm – 7am
E Greenbrae Drive: McCarran Boulevard to Howard Drive
El Rancho Drive: Clear Acre Lane to Moorpark Court
Lemmon Drive: Virginia Street to US 395
Silver Lake Road: Peppermint Drive to Sky Vista Parkway
Red Rock Road: US395 to CA/NV State Line
South Verdi Road: South Verdi Court to Bridge Street
Boomtown Garson Road: Cabela Drive to US I80
Cabela Drive: Boomtown Garson Road to South Verdi Road
Thursday 9/21/2023
Pavement Striping 7pm – 7am
Various Project Streets – 2nd Coat Striping
Crack Seal 7pm – 7am
Lemmon Drive: Virginia Street to US 395
Silver Lake Road: Peppermint Drive to Sky Vista Parkway
Red Rock Road: US395 to CA/NV State Line
South Verdi Road: South Verdi Court to Bridge Street
Boomtown Garson Road: Cabela Drive to US I80
Cabela Drive: Boomtown Garson Road to South Verdi Road
Del Web Parkway: Somersett Parkway to Somersett Ridge Parkway
Mae Anne Avenue: Mesa Park Road to Lasalle Heights
Mesa Park Road: Mesa Park Road to US Highway 40
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Seventh Street: Robb Drive to Virginia Street
University Terrace: Vine Street to Sierra Street
Ralston Street: Fifth Street to University Terrace
4TH STREET AND WOODLAND AVENUE ROUNDABOUT INSTALLATION
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
- Construction of the eastbound travel lanes and roundabout is in progress.
- Intermittent flagging operations at this intersection could cause delays of up to 20 minutes.
- Normal construction hours are 7:00 a.m. – 5:00 p.m., Monday through Friday.
- Effective August 12th through late September work will take place on Saturdays from 7:00 a.m. to 5:00 p.m. Additionally, 24-hour operations will occur between August 28th through late September, Monday morning at 7:00 a.m. to Saturday Morning 7:00 a.m.
Mesa Park Road is closed again and will remain closed through Phase 2 of construction. This closure has been extended through late September while construction of the following occurs:
- 4th Street eastbound lanes and islands
- Southern portion of the roundabout
The project is anticipated to be completed by Fall of 2023.
For more information, visit https://www.4th-woodland-roundabout.com/
ARROWCREEK PARKWAY REHABILITATION PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Beginning Tuesday 9/19, lane reductions approaching the Arrowcreek Parkway / S. Virginia Street intersection will be in place. Expect delays.
The contractor is completing final activities including striping and signal work. Nighttime lane closures may be in place.
CALIFORNIA AVENUE RECONSTRUCTION-NEWLANDS CIRCLE TO ARLINGTON PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Paving has been completed and the contractor is completing final activities related to raising utilities, striping and landscaping.
HOLCOMB AVENUE REHABILITATION PROJECT
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881
Project reached substantial completion.
LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Work on Las Brisas Boulevard is ongoing, work on Los Altos Parkway is scheduled to start Friday, 09/15/2023. Drivers can anticpate lane closures and detours during construction. SNC will provide and maintain a minimum of one paved travel lane in each direction on Las Brisas Boulevard from Brittania Drive to McCarran Boulevard; one-way traffic from Brittania Drive to Robb Drive will be maintained throughout patching and mill and fill operations. One-way traffic will be in place on Los Altos Parkway. The project will maintain business access at all times.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- Construction completed.
- Minor punch item list work
- Lane closures on Pyramid Way and I Street the week of September 25th through 29th.
Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):
- Construction crews are working on the south side of Oddie Boulevard. Milling, roadbed modification and paving operations are expected in the next few weeks until the end of September.
- Intermittent half closures at Sullivan Lane, El Rancho Drive and Silverada Boulevard for paving the week of September 25th through 29th.
- Two-way traffic is expected to remain in place on the north side of Oddie Boulevard until approximate mid-October.
Phase 3 – east of US 395 Ramps to Sutro Street (Reno):
- Construction crews are working on the south side of Oddie Boulevard.
- Two way traffic on the north side of Oddie Boulevard.
- South side of Oddie Boulevard and Montello Street intersection is closed. Detours are in place.
Phase 4 – Sutro Street to I-80 Ramps (Reno):
- Ongoing underground work (storm drain installation and NVE relocation).
- Intermittent traffic lane shifts during construction hours.
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
Lane and shoulder closures will be in place.