4TH STREET AND PRATER WAY BUS RAPID TRANSIT PROJECT
Construction is in progress.

  • Intermittent closures will occur throughout the project to facilitate punch list work.
  • Expect lane shifts and minor traffic delays.

For current traffic information Click here.

 

2018 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains temperature sensitive work and may be modified if weather conditions are unfavorable.

Saturday 9/15

Micro Surfacing
Coney Island Drive: Greg Parkway to End of Pavement
Deming Way: Spice Islands Drive to Glendale Avenue
Industrial Way: Coney Island Drive to Glendale Avenue
Kleppe Lane: Greg Street (West) to Greg Street (East)
Purina Way: Spice Islands Drive to Greg Street

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Coney Island Drive: Greg Parkway to End of Pavement
Deming Way: Spice Islands Drive to Glendale Avenue
Industrial Way: Coney Island Drive to Glendale Avenue
Kleppe Lane: Greg Street (West) to Greg Street (East)
Purina Way: Spice Islands Drive to Greg Street

 Monday 9/17

Micro Surfacing
Airway Drive: Neil Road to Longley Lane
Thomas Creek Road: Zolezzi Lane to Mt. Rose Highway

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Airway Drive: Neil Road to Longley Lane
Thomas Creek Road: Zolezzi Lane to Mt. Rose Highway
Silver Lake Drive: Red Rock Road to Bagpipe Circle
Sky Vista Boulevard: Silver Lake Road to Lear Boulevard

Tuesday 9/18

Micro Surfacing
Airway Drive: Neil Road to Longley Lane
Arrowcreek Parkway: Private Entrance to Thomas Creek Road

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Airway Drive: Neil Road to Longley Lane
Thomas Creek Road: Zolezzi Lane to Mt. Rose Highway
Silver Lake Drive: Red Rock Road to Bagpipe Circle
Sky Vista Boulevard: Silver Lake Road to Lear Boulevard
Dandini Boulevard: Sun Valley Boulevard to West Leonesio Drive
El Rancho Drive: Sullivan Lane to Moorpark Court

Wednesday 9/19

Micro Surfacing
Longley Lane: Houston Drive to Rock Boulevard
Foothill Road: Caribou Road to Virginia Street

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Longley Lane: Houston Drive to Rock Boulevard
Foothill Road: Caribou Road to Virginia Street
Coney Island Drive: Greg Parkway to End of Pavement
Deming Way: Spice Islands Drive to Glendale Avenue
Industrial Way: Coney Island Drive to Glendale Avenue
Kleppe Lane: Greg Street (West) to Greg Street (East)
Purina Way: Spice Islands Drive to Greg Street
Dandini Boulevard: Sun Valley Boulevard to West Leonesio Drive
El Rancho Drive: Sullivan Lane to Moorpark Court

Thursday 9/20

Micro Surfacing
Arlington Avenue: First Street to Sixth Street
Foothill Road: Caribou Road to Virginia Street

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Arlington Avenue: First Street to Sixth Street
Foothill Road: Caribou Road to Virginia Street
Airway Drive: Neil Road to Longley Lane
Thomas Creek Road: Zolezzi Lane to Mt. Rose Highway
Coney Island Drive: Greg Parkway to End of Pavement
Deming Way: Spice Islands Drive to Glendale Avenue
Industrial Way: Coney Island Drive to Glendale Avenue
Kleppe Lane: Greg Street (West) to Greg Street (East)
Purina Way: Spice Islands Drive to Greg Street

Friday 9/21

Micro Surfacing
Wedge Parkway: Mt. Rose Highway to Whites Creek Lane

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Wedge Parkway: Mt. Rose Highway to Whites Creek Lane
Longley Lane: Houston Drive to Rock Boulevard
Airway Drive: Neil Road to Longley Lane
Thomas Creek Road: Zolezzi Lane to Mt. Rose Highway

 

ITS PROJECT – PHASE 2A
Work will include conduit and pull box installation at the following locations:

  • N Virginia St between Comstock and 15th St – Underground work complete.
  • Wells St EB on ramp, shoulder area – Underground work complete.
  • McCarran between Greg and Nugget – Underground work complete.
  • McCarran between Prater and Baring – Night work begins week of 9/10 – 9/28; occasional shoulder closure northbound direction.

 

PYRAMID HWY & CALLE DE LA PLATA TRAFFIC SIGNAL

  • Construction begins September 10th.
  • Work hours will be from 7:00am to 3:30pm.
  • Work will commence on the shoulders of the intersection and continue through the week.
  • No lane closures at this time.

 

SOUTHEAST CONNECTOR PROJECT
From Greg St to South Meadows Pkwy and Veterans Pkwy (5.5 miles)

  • The Southeast connector is open to traffic.
  • The speed limit is 45 mph. Look for traffic signs and use caution as everyone becomes familiar with the new roadway, signalized intersections, and the multi-use path.
  • Intermittent shoulder closures and single lane closures in specific locations will occur over the next several weeks. Traffic control signs and personnel will be in place to direct traffic accordingly.

More information is available at the project website www.SouthEastConnector.com.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
The Utility Phase of the Virginia Street Bus RAPID Transit Extension Project is underway

  • Traffic control is one-way southbound from Liberty St to Wells Ave.
  •  Northbound detour will start at Wells Ave and continue to Holcomb Ave and Center St.
  •  Side streets within the midtown area are open and provide effective access to businesses and residences.
  •  Watch for arrow boards and flaggers.

For more information visit Virginia Street Website.

 

 

 