December 17, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at:

  • Rock Boulevard from Greg Street to Victorian Avenue.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent shoulder and/or lane closures on Oddie Boulevard during daytime working hours.
  • Granite construction crews are doing underground work, excavating/forming/pouring footings.
  • On Pyramid Way ( between J Street and I Street): intermittent closure of southbound lane from 9:00AM and 4:00PM.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Sparks Boulevard & Ion Drive
  • Veterans Parkway & Long Meadow Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work and construct new pedestrian ramps and sidewalks. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00AM to 3:00PM Monday through Friday.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

December 10, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at:

  • Rock Boulevard from Greg Street to Victorian Avenue.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent shoulder and/or lane closures on Oddie Boulevard during daytime working hours.
  • Granite construction crews are doing underground, excavating/forming/pouring footings.
  • NV Energy crews will continue to remove existing facilities.
  • On Pyramid Way ( between J Street and I Street): intermittent closure of southbound lane from 9:00AM and 4:00PM.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Sparks Boulevard & Ion Drive
  • Vista Boulevard & Iratcabal Drive
  • Victorian Avenue & 16th Street
  • Veterans Parkway & Long Meadow Drive
  • Mayberry Drive & Keele Drive
  • 7th Avenue & McDonald Drive
  • Valley Road & Sadlier Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work and construct new pedestrian ramps and sidewalks. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00AM to 3:00PM Monday through Friday.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

December 3, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Monday 12/6

Utility Adjustment
Red Rock Road: US395 to Moya Boulevard
Village Parkway: Cold Springs Drive to Cody Court

Tuesday 12/7

Utility Adjustment
Isidor Court: Calle De La Plata to Circuit Court
Calle De La Plata: Pyramid Highway to Isidor Court
La Posada Drive: Pyramid Highway to Omni Drive Round-a-bout
Calle De Oro: Cordoba Boulevard to Cordoba Boulevard

Wednesday 12/8

Utility Adjustment
Calle De La Plata: Pyramid Highway to Isidor Court
La Posada Drive: Pyramid Highway to 360’ E of Omni Drive Round-a-bout
Calle De Oro: Cordoba Boulevard to Cordoba Boulevard

Thursday 12/9

Utility Adjustment
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard

Friday 12/10

Utility Adjustment
E Greenbrae Drive: Howard Drive to Prater Way
Freeport Boulevard: 21st Street to Stanford Way

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at:

  • Lake Street from First Street to Second Street.
  • Rock Boulevard from Greg Street to Victorian Avenue.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work is complete. Isolated lane shifts may be in place to perform final clean up activities.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

 Phase 1: Pyramid Way to Sullivan Lane (Sparks):

Construction begins on Monday November 29, 2021.

  • Drivers may see shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • NV Energy crews will be removing existing facilities.

This week drivers can expect to see crews setting up traffic control to prepare for underground and trenching work on the shoulder.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Sparks Boulevard & Ion Drive
  • Victorian Avenue & 16th Street
  • Mayberry Drive & Keele Drive
  • 7th Avenue & McDonald Drive
  • Valley Road & Sadlier Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work and construct new pedestrian ramps and sidewalks. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 AM to 3:00 PM Monday through Friday.

Ion Drive will be temporarily closed to traffic from Sparks Boulevard to Luther Pass Court on December 8 and 9, 2021 from 9:00 AM to 5:00 PM. A detour will be provided during this closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

November 26, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 11/26

No Work

Saturday 11/27

No Work

Sunday 11/28

No Work

Monday 11/29

Utility Adjustment
Second Street: Keystone Avenue to Virginia Street
Fourth Street: West Street to Galletti Way

Tuesday 11/30

Utility Adjustment
Second Street: Keystone Avenue to Virginia Street
Fourth Street: West Street to Galletti Way

Wednesday 12/1

Utility Adjustment
Second Street: Keystone Avenue to Virginia Street
Fourth Street: West Street to Galletti Way

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Vista Boulevard & Iratcabal Drive
  • Sparks Boulevard & Ion Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 a.m. to 3:00 p.m. Monday through Friday.

Ion Drive will be temporarily closed to traffic from Sparks Boulevard to Luther Pass Court on December 2 and 3, 2021, from 9:00 a.m. to 5:00 p.m. A detour will be provided during this closure.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Lake Street from First Street to Second Street.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7:00 a.m. to 5:00 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

 Phase 1: Pyramid Way to Sullivan Lane (Sparks):

Construction begins on Monday November 29, 2021.

  • Drivers may see shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • NV Energy crews will be removing existing facilities

This week drivers can expect to see crews setting up traffic control to prepare for underground and trenching work on the shoulder.

One lane on each direction along Oddie Boulevard will be maintained.  For additional information on construction status, visit the Porject website at http://Oddiewellsproject.com

November 19, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 11/19

Utility Adjustment
Moana Lane: Plumas Street to Neil Road
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Saturday 11/20

No Work

Sunday 11/21

No Work

Monday 11/22

Utility Adjustment
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

Tuesday 11/23

Utility Adjustment
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Victorian Avenue & 16th Street
  • Veterans Parkway & Long Meadow Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 a.m. to 3:00 p.m. Monday through Friday.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Lake Street from First Street to Second Street.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7:00 a.m. to 5:00 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

 Phase 1: Pyramid Way to Sullivan Lane (Sparks):

Construction begins on Monday November 29, 2021.

  • Drivers may see shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • NV Energy crews will be removing existing facilities

This week drivers can expect to see crews setting up traffic control to prepare for underground and trenching work on the shoulder.

One lane on each direction along Oddie Boulevard will be maintained.  For additional information on construction status, visit the Porject website at http://Oddiewellsproject.com

November 12, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Monday 11/15

Utility Adjustment
Arrowcreek Parkway: Thomas Creek to private entrance
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Tuesday 11/16

Utility Adjustment
Redfield Parkway: Kietzke Lane to Virginia Street

Wednesday 11/17

Utility Adjustment
Redfield Parkway: Kietzke Lane to Virginia Street

Thursday 11/18

Utility Adjustment
Plumas Street: Ridgeview Drive to Ridgeview Drive
Moana Lane: Plumas Street to Neil Road
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Friday 11/19

Utility Adjustment
Moana Lane: Plumas Street to Neil Road
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Victorian Avenue & 16th Street
  • Veterans Parkway & Long Meadow Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 a.m. to 3:00 p.m. Monday through Friday.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will be cleaning up the job site and working on punch list items. Drivers should expect intermittent traffic control throughout the project limits.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7:00 a.m. to 5:00 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

November 5, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PHASE 3B, NORTH VIRGINIA STREET & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive. Travelers should expect shoulder closures and isolated lane closures while construction crews complete striping and pedestrian ramp work at the intersection.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following location:

  • Victorian Avenue & 16th Street

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9am to 3pm Monday through Friday.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will be cleaning up the job site and working on punch list items. Drivers should expect intermittent traffic control throughout the project limits.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 28, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PHASE 3B, NORTH VIRGINIA STREET & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Monday 11/1 – Tuesday 11/2

To complete paving activities, North Virginia Street will be closed in the southbound direction from 9:00 AM to 5:00 PM from Sunset Mountain Road to the intersection at Panther Drive. The road will remain open to northbound traffic, and a southbound detour will be provided via Golden Valley Road.

Trash pickup will continue as scheduled and access will remain open for mail deliveries.

During construction RTC RIDE bus service may be temporarily impacted within the project area.

Travel lanes will be reopened to two-way traffic after 6pm on Tuesday, November 2.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Veterans Parkway & Long Meadow Drive
  • Steamboat Parkway & Horse Ranch Road
  • Sparks Boulevard & Ion Drive
  • Victorian Avenue & 16th Street

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9am to 3pm Monday through Friday.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will be cleaning up the job site and working on punch list items. Drivers should expect intermittent traffic control throughout the project limits.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection will be open for normal operations starting October 22, 2021.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 22, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Veterans Parkway & Long Meadow Drive
  • Steamboat Parkway & Horse Ranch Road
  • Vista Boulevard & Iratcabal Drive
  • Sparks Boulevard & Ion Drive
  • Victorian Avenue & 16th Street

Travelers should expect shoulder closures at all locations while construction crews complete pole foundation and trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced in from 9am to 3pm Monday through Friday.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will be cleaning up the job site and working on punchlist items. Drivers should expect intermittent traffic control throughout the project limits.

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next Spring for pavement slurry seal, however, intersection will open  and allow normal operations by October 22, 2021. New roadway configuration, please use caution driving through intersection.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 15, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of October at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will begin utility adjustments this week within the roadway.

Drivers should expect intermittent traffic control throughout the project limits.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

Expect intermittent lane closures around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 8, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of October at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. This week the contractor will be installing roadway striping and signage.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closures around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 1, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 10/1

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Saturday 10/2

No Work

Sunday 10/3

No Work

Monday 10/4

Micro Surfacing
Panther Drive: Virginia Street to Western Road

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Tuesday 10/5

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Wednesday 10/6

Traffic Signal Loop Replacement
Moana Lane: Clover Way to Warren Way

Thursday 10/7

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Friday 10/8

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Sky Valley Drive & Mistyridge Lane
  • Virginia Street & Planetarium

Work will include roadside construction of bus stop pads and sidewalk. Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

On Tuesday, September 28, 2021 West Golden Valley Road will be closed to vehicle traffic from 9 AM to 3PM.

Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete roadway striping on Wednesday, September 29, 2021 and Thursday September 30, 2021.

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be install through the month of October at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Roadway paving will occur on Tuesday (10/5) and Wednesday (10/6) along Newport Lane. Travelers should expect delays and it is recommended to find alternative routes if possible.

On-street parking is closed during daytime working hours on Newport Lane (7 a.m. to 5 p.m. – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

Additionally, contractor will be working on Saturday (10/2) to prepare for paving next week.

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m. – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

September 24, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 9/24

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Saturday 9/25

No Work

Sunday 9/26

No Work

Monday 9/27

Chip Seal
Panther Drive: Virginia Street to Western Road

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Tuesday 9/28

Chip Seal
Panther Drive: Virginia Street to Western Road

 Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Wednesday 9/29

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Thursday 9/30

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Friday 10/1

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Sky Valley Drive & Mistyridge Lane
  • Virginia Street & Planetarium

Work will include roadside construction of bus stop pads and sidewalk. Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

On Tuesday, September 28, 2021, West Golden Valley Road will be closed to vehicle traffic from 9:00 a.m. to 3:00 p.m.

Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete roadway striping on Wednesday, September 29, 2021, and Thursday September 30, 2021.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Roadway reconstruction work will begin this week along Newport Lane and continue into the following week. Travelers should expect delays and it is recommended to find alternative routes if possible.

On-street parking is closed during daytime working hours on Newport Lane (7 a.m. to 5 p.m. – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

The contractor will be working the next two (2) Saturdays 9/25 and 10/2

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m. – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

September 17, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 9/17

Scratch Course
Panther Drive: Virginia Street to Western Road

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Saturday 9/18

No Work

Sunday 9/19

No Work

Monday 9/20

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Tuesday 9/21

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Wednesday 9/22

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Thursday 9/23

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Friday 9/24

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • 7th Street and Genoa Avenue
  • Lakeside Drive & Brinkby Avenue
  • Sky Valley Drive & Mistyridge Lane
  • Neil Road and Moana Lane
  • South Virginia Street and Meadowwood Mall
  • Double Diamond & Sandhill Road (DMV)
  • Virginia Street & Planetarium

Work will include roadside construction of bus stop pads and sidewalk. Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete sidewalk and utility work.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction begins Monday, September 20, 2021, at the intersection of North Virginia Street & Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection. Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Construction is in progress along the southside of Newport Lane.

Travelers should expect isolated lane closures and one-way flagging while construction crews complete demolition, driveway, sidewalk, storm drain, and headwall work.

Additionally, in order to complete the removal/replacement of the existing pedestrian ramps and install new storm drain along the southside of Newport Lane, access to Newport Lane from La France Lane and Collins Circle  will be closed during the day while construction activities are ongoing. To maintain resident access, a detour will be provided via Sagehen Lane and Newport Lane for the duration of the side street road closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.). Residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

September 10, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

 

Friday 9/10

Slurry Seal
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Spice Islands Drive: Greg Street to Franklin Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Prater Way: View Street to Pyramid Way
Moana Lane: US580 to Neil Road
First Street: Arlington Avenue to Sierra Street

Saturday 9/11

Slurry Seal
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard

Sunday 9/12

No Work

Monday 9/13

Slurry Seal
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
(Various project streets second coat)

Tuesday 9/14

Slurry Seal
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
(Various project streets second coat)

Wednesday 9/15

Slurry Seal
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
(Various project streets second coat)

Thursday 9/16

Slurry Seal
Battle Born Way: Galletti Way to Victorian Avenue

Striping (Night Work – 7:00PM – 7:00AM)
Battle Born Way: Galletti Way to Victorian Avenue
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
(Various project streets second coat)

Friday 9/17

Scratch Course
Panther Drive: Virginia Street to Western Road

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Saturday 9/18

Slurry Seal
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Meredeth Way & Kleppe Lane
  • 7th Street and Keystone Avenue (Near Raleys)
  • 7th Street and Genoa Avenue
  • Lakeside Drive & Brinkby Avenue
  • Sky Valley Drive & Mistyridge Lane
  • Neil Road and Moana Lane
  • South Virginia Street and Meadowwood Mall
  • Double Diamond & Sandhill Road (DMV)

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete sidewalk and utility work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Construction is in progress along the southside of Newport Lane.

Travelers should expect isolated lane closures and one-way flagging while construction crews complete demolition, driveway, and sidewalk work.

Additionally, in order to complete the removal/replacement of the exisiting pedestrian ramps and install new storm drain along the southside of Newport Lane, access to Newport Lane from La France Lane and Collins Circle  will be closed during the day while construction activies are ongoing.

To maintain resident access, a detour will be provided via Sagehen Lane and Newport Lane for the duration of the side street road closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.

 

  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking will NOT be allowed in the work zone during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

September 3, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

 

Friday 9/3

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
La Posada Drive: RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Saturday 9/4

No work

Sunday 9/5

No Work

Monday 9/6

No Work

Tuesday 9/7

Slurry Seal
Fourth Street: West Street to Galletti Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Moana Lane: US580 to Neil Road
First Street: Arlington Avenue to Sierra Street

Striping (Night Work – 7:00PM – 7:00AM)
Moana Lane: Plumas Street to Neil Road
First Street: Arlington Avenue to Sierra Street

Wednesday 9/8

Slurry Seal
Fourth Street: West Street to Galletti Way
Calle De Oro Parkway: Cordoba Boulevard to Cordoba Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Moana Lane: Plumas Street to US580

Striping (Night Work – 7:00PM – 7:00AM)
Calle De Oro Parkway: Cordoba Boulevard to Cordoba Boulevard
First Street: Arlington Avenue to Sierra Street

Thursday 9/9

Calle De Oro Parkway: Cordoba Boulevard to Cordoba Boulevard
Spice Islands Drive: Greg Street to Franklin Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Calle De Oro Parkway: Cordoba Boulevard to Cordoba Boulevard
Moana Lane: Plumas Street to US580
Prater Way: View Street to Pyramid Way

Friday 9/10

Slurry Seal
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Spice Islands Drive: Greg Street to Franklin Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Prater Way: View Street to Pyramid Way
Moana Lane: US580 to Neil Road
First Street: Arlington Avenue to Sierra Street

Saturday 9/11

Slurry Seal
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • 9th Street & Sutro Street
  • 4th Street & Morrill Avenue
  • Locust Street & Crampton Street
  • Locust Street & Capitol Hill Avenue
  • Meredeth Way & Kleppe Lane
  • 7th Street and Keystone Avenue (Near Raleys)
  • Lakeside Drive & Brinkby Avenue

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

The road re-opens to vehicle traffic starting September 3, 2021. Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete sidewalk and utility work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Construction is in progress along the southside of Newport Lane.

Travelers should expect isolated lane closures and one-way flagging while construction crews complete demolition, driveway, and sidewalk work.

Additionally, in order to complete the removal/replacement of the exisiting pedestrian ramps and install new storm drain along the southside of Newport Lane, access to Newport Lane from La France Lane and Collins Circle  will be closed during the day while construction activies are ongoing.

To maintain resident access, a detour will be provided via Sagehen Lane and Newport Lane for the duration of the side street road closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.

 

  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking will NOT be allowed in the work zone during during non-working hours (5 p.m. through 7 a.m.) starting September 7, 2021, at 5 p.m. Vehicles parked in the work zone will be towed.

 

  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

August 30, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Monday 8/30

Slurry Seal
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to E of Veterans Parkway
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Tuesday 8/31

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Wednesday 9/1

Slurry Seal (Night Work – 7:00PM – 7:00AM)
La Posada Drive: RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Thursday 9/2

Slurry Seal (Night Work – 7:00PM – 7:00AM)
La Posada Drive: 360 East of RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
La Posada Drive: RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive

Friday 9/3

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
La Posada Drive: RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Silverada Boulevard & Tybo Avenue
  • 9th Street & Sutro Street
  • 4th Street & Morrill Avenue
  • Locust Street & Crampton Street
  • Locust Street & Capitol Hill Avenue
  • Meredeth Way & Kleppe Lane

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

In order to complete roadway pulverization and paving, West Golden Valley Road remains closed to traffic from Yorkshire Drive to North Virginia Street until September 3rd, 2021.

To maintain resident access, a detour will be provided via Yorkshire Drive and Lancaster Drive for the duration of the road closure.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • North side of Lemmon Drive from North Virginia Street to US 395 southbound off-ramp
  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Construction is in progress along the southside of Newport Lane.

Thursday 9/2 and Friday 9/3
In order to complete the removal/replacement of the exisiting pedestrian ramps and install new storm drain along the southside of Newport Lane, access to Newport Lane from La France Lane and Collins Circle  will be closed during the day while construction activies are ongoing. To maintain resident access, a detour will be provided via Sagehen Lane and Newport Lane for the duration of the side street road closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

  • Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.
  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

August 20, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 8/20

Slurry Seal
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way

Slurry Seal (Night Work – 7:00PM – 7:00AM
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Second Street: Keyston Avenue to Virginia Street

Saturday 8/21

Slurry Seal
Sunshine Lane: Mill Street to Second Street
Plumas Street: Ridgeview Drive to Ridgeview Drive

Sunday 8/22

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Sunshine Lane: Mill Street to Second Street
Plumas Street: Ridgeview Drive to Ridgeview Drive
Nugget Avenue: Pyramid Way to Victorian Plaza Circle
Sixth Street: Ralston Street to Virginia Street

Monday 8/23

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way

Tuesday 8/24

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Sunshine Lane: Mill Street to Second Street
Plumas Street: Ridgeview Drive to Ridgeview Drive

Wednesday 8/25

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Thursday 8/26

Slurry Seal
McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to 444’ E of Veterans Parkway
Nugget Avenue: Pyramid Way to Victorian Plaza Circle
Sixth Street: Ralston Street to Virginia Street
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Friday 8/27

Slurry Seal
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Second Street: Keystone Avenue to Virginia Street

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Neil Road and Catalina Drive
  • Industrial Way & Greg Street
  • ElRancho Drive & Clinton Street
  • Silverada Boulevard & Tybo Avenue
  • 9th Street & Sutro Street
  • 4th Street & Morrill Avenue
  • Locust Street & Crampton Street
  • Locust Street & Capitol Hill Avenue

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

In order to complete roadway pulverization and paving, West Golden Valley Road will be completely closed to traffic from Yorkshire Drive to North Virginia Street starting Monday, August 23 extending through September 3, 2021.

To maintain resident access, a detour will be provided via Yorkshire Drive and Lancaster Drive for the duration of the road closure.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • North side of Lemmon Drive from North Virginia to US 395 southbound off-ramp
  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

August 13, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 8/13

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Steneri Way: Freeport Boulevard to Glendale Avenue

Striping (Night Work – 7:00PM – 7:00AM)
Freeport Boulevard: 21st Street to Stanford Way
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Steneri Way: Freeport Boulevard to Glendale Avenue

Saturday 8/14

No work scheduled.

Sunday 8/15

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Linda Way: Coney Island Drive to Glendale Avenue
Crane Way: 18th Street to Bridge Deck
Icehouse Avenue: end to end
Wolverine Way: Glendale Avenue to Stanford Way
International Place: Glendale Avenue to Icehouse Avenue

Monday 8/16

Chip Seal
McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Linda Way: Coney Island Drive to Glendale Avenue

Tuesday 8/17

Chip Seal
McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard
Slurry Seal
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way

Wednesday 8/18

Slurry Seal
Second Street: Keystone Avenue to Virginia Street

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Second Street: Keystone Avenue to Virginia Street
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way

Thursday 8/19

Slurry Seal
Nugget Avenue: Pyramid Way to Victorian Plaza Circle
Sixth Street: Ralston Street to Virginia Street
Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Nugget Avenue: Pyramid Way to Victorian Plaza Circle
Sixth Street: Ralston Street to Virginia Street

Friday 8/20

Slurry Seal
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Second Street: Keystone Avenue to Virginia Street

Saturday 8/21

Slurry Seal
Sunshine Lane: Mill Street to Second Street
Plumas Street: Ridgeview Drive to Ridgeview Drive

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • Neil Road and Catalina Drive
  • Industrial Way & Greg Street
  • ElRancho Drive & Clinton Street
  • Virginia Street & Planetarium
  • Silverada Boulevard & Tybo Avenue
  • 9th Street & Sutro Street
  • 4th Street & Morrill Avenue

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures, lane shifts, and one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • North side of Lemmon Drive from North Virginia to US 395 southbound off-ramp (Night Work).
  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

August 6, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Sunday 8/8

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard

Striping (Night Work – 7:00PM – 7:00AM)

Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Golden Valley Drive: Spearhead Way to Seventh Ave
Vassar Street: Virginia Street to Kietzke Lane
Coney Island Drive: Marieta Way to Stanford Way
Southern Way: Greg Street to Freeport Boulevard

Monday 8/9

Micro-Milling

McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard

Striping (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard
Coney Island Drive: Marieta Way to Stanford Way
Southern Way: Greg Street to Freeport Boulevard

 

Tuesday 8/10

Micro-Milling

McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Freeport Boulevard: 21st Street to Stanford Way

Striping (Night Work – 7:00PM – 7:00AM)

Redfield Parkway: Kietzke Lane to Virginia Street
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Wednesday 8/11

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Freeport Boulevard: 21st Street to Stanford Way

Striping (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard
Freeport Boulevard: 21st Street to Stanford Way

 

Thursday 8/12

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Crane Way: 18th Street to Bridge Deck
Icehouse Avenue: End to End
Wolverine Way: Glendale Avenue to Stanford Way
International Place: Glendale Avenue to Icehouse Avenue

Striping (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard
Crane Way: 18th Street to Bridge Deck
Icehouse Avenue: End to End
Wolverine Way: Glendale Avenue to Stanford Way
International Place: Glendale Avenue to Icehouse Avenue

Friday 8/13

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Steneri Way: Freeport Boulevard to Glendale Avenue

Striping (Night Work – 7:00PM – 7:00AM)

Freeport Boulevard: 21st Street to Stanford Way
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Steneri Way: Freeport Boulevard to Glendale Avenue

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • Neil Road and Catalina Drive
  • Industrial & Greg Street
  • ElRancho Drive & Clinton Street
  • Virginia St. & Planetarium
  • Silverada Blvd & Tybo Ave

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures, lane shifts, and one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Work on north side of Lemmon Drive from North Virginia to US 395 southbound off ramp. This portion of the contract is night work.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
  • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

This project is complete.

 

July 30, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/30

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Golden Valley Drive: Spearhead Way to Seventh Ave

Striping (Night Work – 7:00PM – 7:00AM)
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Saturday 7/31

Slurry Seal
Coney Island Drive: Marieta Way to Stanford Way
Southern Way: Greg Street to Freeport Boulevard

Monday 8/2 through Friday 8/6

No Work Scheduled

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • York Way & Pyramid Way
  • Neil Road and Catalina Drive
  • Industrial & Greg Street

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures, lane shifts, and one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Begin work on north side of Lemmon Drive from North Virginia to US 395 southbound off ramp. This portion of the contract is night work.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
  • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

Look Ahead and Reduced Speed Limit – beginning the week of August 9

Drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

  • Lane and shoulder widths will be reduced.
  • Business access will be maintained.
  • The speed limit will be reduced to 35 MPH through the work zone.
  • Temporary roadway striping will be completed in one overnight shift to minimize daytime traffic impacts.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

This project is complete.

 

July 23, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/23

Slurry Seal
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Striping
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Saturday 7/24

Slurry Seal
Mae Anne Avenue: Robb Drive to Quail Run Road

Sunday 7/25

Striping (Night Work – 7:00PM – 7:00AM)
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Monday 7/26

Slurry Seal
Redfield Parkway: Kietzke Lane to Virginia Street

Striping (Night Work – 7:00PM – 7:00AM)
Redfield Parkway: Kietzke Lane to Virginia Street
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Tuesday 7/27

Slurry Seal
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Striping (Night Work – 7:00PM – 7:00AM)
Redfield Parkway: Kietzke Lane to Virginia Street
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Wednesday 7/28

Slurry Seal
Arrowcreek Parkway: Thomas Creek to Private Entrance

Striping (Night Work – 7:00PM – 7:00AM)
Arrowcreek Parkway: Thomas Creek to Private Entrance
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Thursday 7/29

Slurry Seal
Vassar Street: Virginia Street to Kietzke Lane
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Golden Valley Drive: Spearhead Way to Seventh Ave
 
Striping (Night Work – 7:00PM – 7:00AM)
Vassar Street: Virginia Street to Kietzke Lane
Redfield Parkway: Kietzke Lane to Virginia Street

Friday 7/30

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Golden Valley Drive: Spearhead Way to Seventh Ave

Striping (Night Work – 7:00PM – 7:00AM)
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Saturday 7/31

Slurry Seal
Coney Island Drive: Marieta Way to Stanford Way
Southern Way: Greg Street to Freeport Boulevard

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • York Way & Pyramid Way
  • Neil Road and Catalina Drive

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction will begin on Golden Valley Road between North Virginia Street and Yorkshire Drive beginning July 26, 2021.

Travelers should expect isolated shoulder closures, lane shifts, and one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction in progress along Rock Boulevard. This portion of the contract is night work.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
  • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

July 16, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/16

Slurry Seal
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Striping
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Saturday 7/17

Slurry Seal
Mae Anne Avenue: Robb Drive to Quail Run Road

Sunday 7/18

Striping (Night Work – 7:00PM – 7:00AM)
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

Monday 7/19

Pavement Crack Sealing
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
McCourry Boulevard: Northwood Boulevard to SR431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal
Gentry Way: Virginia Street to Kietzke Lane
Grove Street: Wrondel Way to Kietzke Lane

Striping (Night Work – 7:00PM – 7:00AM)
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road
Gentry Way: Virginia Street to Kietzke Lane
Grove Street: Wrondel Way to Kietzke Lane

Tuesday 7/20

Slurry Seal
Airmotive Way: Villanova Street to Terminal Way
Harvard Way: Automotive Way to Market Street

Striping (Night Work – 7:00PM – 7:00AM)
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Airmotive Way: Villanova Street to Terminal Way
Harvard Way: Automotive Way to Market Street

Wednesday 7/21

Slurry Seal
Lymberry Street: Cadillac Place to Lakeside Drive
Yori Avenue: Moana Lane to Gentry Way

Striping (Night Work – 7:00PM – 7:00AM)
Mae Anne Avenue: Robb Drive to Quail Run Road
Lymberry Street: Cadillac Place to Lakeside Drive
Yori Avenue: Moana Lane to Gentry Way

Thursday 7/22

Slurry Seal
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Striping
Gentry Way: Virginia Street to Kietzke Lane
Grove Street: Wrondel Way to Kietzke Lane
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Friday 7/23

Slurry Seal
Redfield Parkway: Kietzke Lane to Virginia Street

Striping
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Saturday 7/24

Slurry Seal
Sunshine Lane: Mill Street to end

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • York Way & Pyramid Way
  • Neil Road and Catalina Drive

Work will include roadside construction of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction will begin on Golden Valley Road between North Virginia Street and Yorkshire Drive beginning July 19, 2021.

Travelers should expect shoulder closures, lane shifts, and isolated one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction in progress along Rock Boulevard.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
  • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

July 9, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/9

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Striping
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Saturday 7/10

No work is scheduled

Sunday 7/11

Striping (Night Work – 7:00PM – 7:00AM)
Red Rock Road: US 395 to Moya Boulevard

Monday 7/12

Slurry Seal
Mira Loma Drive: Longley Lane to McCarran Boulevard

Striping (Night Work – 7:00PM – 7:00AM)
Mira Loma Drive: Longley Lane to Veterans Parkway
Parr Boulevard: Virginia Street to US 395

Tuesday 7/13

Slurry Seal
Sutro Street: Kuenzli Street to McCarran Boulevard

Striping (Night Work – 7:00PM – 7:00AM)
Parr Boulevard: Virginia Street to US 395

Wednesday 7/14

Slurry Seal
Sutro Street: Kuenzli Street to McCarran Boulevard

Striping (Night Work – 7:00PM – 7:00AM)
Sutro Street: Kuenzli Street to McCarran Boulevard

Thursday 7/15

Slurry Seal
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Striping
Mira Loma Drive: Longley Lane to Veterans Parkway

Friday 7/16

Slurry Seal
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Striping
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Saturday 7/17

Slurry Seal
Mae Anne Avenue: Robb Drive to Quail Run Road

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • York Way & Pyramid Way
  • Neil Road and Catalina Drive

Work will include roadside construction of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is scheduled to begin July 11, 2021, along Rock Boulevard.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation is in progress.

Traffic control includes transition to temporary lanes along the south side of Kings Row.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

July 2, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/2

Pavement Patching
Kuenzli Street: Wells Avenue to Second Street
Fourth Street: West Street to Galletti Way

Striping (Night Work – 7:00PM – 7:00AM)
White Lake Parkway: HWY 395 to Village Parkway

Saturday, Sunday, Monday 7/3 – 5

No work is scheduled

Tuesday 7/6

Pavement Patching
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Slurry Seal
Parr Boulevard: Virginia Street to US 395

Crack Seal
Mira Loma Drive: Longley Lane to Rosehill Court
Pembroke Drive: Bullock Road to Piping Rock Drive
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway
Arrowcreek Parkway: Thomas Creek to private entrance

Wednesday 7/7

Pavement Patching
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
McCourry Boulevard: Northwood Boulevard SR 431

Slurry Seal
Parr Boulevard: Virginia Street to US 395

Crack Seal
Mira Loma Drive: Longley Lane to Rosehill Court
Pembroke Drive: Bullock Road to Piping Rock Drive
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway
Arrowcreek Parkway: Thomas Creek to private entrance

Striping (Night Work – 7:00PM – 7:00AM)
Parr Boulevard: Virginia Street to US 395

Thursday 7/8

Pavement Patching
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Crack Seal
Mira Loma Drive: Longley Lane to Rosehill Court
Pembroke Drive: Bullock Road to Piping Rock Drive
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway
Arrowcreek Parkway: Thomas Creek to private entrance

Striping
Parr Boulevard: Virginia Street to US 395
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Friday 7/9

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Striping
Seventh Avenue: Sun Valley Drive to Golden Valley Road

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada

Work will include roadside construction of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is scheduled to begin July 11, 2021.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Isolated utility improvement work is in progress.

Traffic control includes isolated lane shifts and flagger controls within the project area.

Later in the week, traffic control will transition to temporary lanes along the south side of Kings Row.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

June 25, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 6/25

Slurry Seal
Village Parkway: Cold Springs Drive to Village Center Drive

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

Saturday and Sunday 6/26 – 27

No work is scheduled

Monday 6/28

Slurry Seal
Village Parkway: Cold Springs Drive to Village Center Drive

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

Tuesday 6/29

Slurry Seal
White Lake Parkway: HWY 395 to Village Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

Wednesday 6/30

Pavement Patching
Sutro Street: Kuenzli Street to McCarran Boulevard

Slurry Seal
White Lake Parkway: HWY 395 to Village Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

Thursday 7/1

Pavement Patching
Sutro Street: Kuenzli Street to McCarran Boulevard

Slurry Seal
White Lake Parkway: HWY 395 to Village Parkway

Striping (Night Work – 7:00PM – 7:00AM)
White Lake Parkway: HWY 395 to Village Parkway

Friday 7/2

Pavement Patching
Kuenzli Street: Wells Avenue to Second Street
Fourth Street: West Street to Galletti Way

Striping (Night Work – 7:00PM – 7:00AM)
White Lake Parkway: HWY 395 to Village Parkway

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada

Work will include roadside construction of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting was awarded the construction contract.  Construction is scheduled to begin July 6, 2021.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Isolated utility improvement work is in progress.

Traffic control includes isolated lane shifts and flagger controls within the project area.

Later in the week, traffic control will transition to temporary lanes along the south side of Kings Row.

 

RENO CONSOLIDATED 21-01 – LUND LANE, YUMA LANE, ARMSTRONG LANE
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is complete and the roadways are open without restrictions.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

June 18, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Sunday 6/20

Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Grove Street: Wrondel Way to Kietzke Lane
Lymbery Street: Cadillac Place to Lakeside Drive
Gentry Way: Virginia Street to Kietzke Lane
Moana Lane: Plumas Street to Neil Road
Yori Way: Moana Lane to Gentry Way
Redfield Parkway: Kietzke Lane to Virginia Street
Plumas Street: Ridgeview Drive to 596’ S Ridgeview Drive
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

Monday 6/21

Pavement Patching
Liberty Street: Arlington Avenue to Ryland Street

Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Grove Street: Wrondel Way to Kietzke Lane
Lymbery Street: Cadillac Place to Lakeside Drive
Gentry Way: Virginia Street to Kietzke Lane
Moana Lane: Plumas Street to Neil Road
Yori Way: Moana Lane to Gentry Way
Redfield Parkway: Kietzke Lane to Virginia Street
Plumas Street: Ridgeview Drive to 596’ S Ridgeview Drive
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

Tuesday 6/22

Pavement Patching
First Street: Arlington Avenue to Sierra Street
Second Street: Keystone Avenue to Virginia Street

Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Bullock Road to Piping Rock Drive
Mira Loma Drive: Longley Lane to Rosehill Court
Damonte Ranch Parkway: I580 NB Exit Ramp to End of Pavement
Arrowcreek Parkway: Thomas Creek to Private Gate

Wednesday 6/23

Pavement Patching
Mira Loma Drive: Longley Lane to Rosehill Court
Airmotive Way: Villanova Street to Terminal Way
Harvard Way: Automotive Way to Market Street
Sunshine Lane: Mill Street to End Cul-De-Sac

Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Bullock Road to Piping Rock Drive
Mira Loma Drive: Longley Lane to Rosehill Court
Damonte Ranch Parkway: I580 NB Exit Ramp to End of Pavement
Arrowcreek Parkway: Thomas Creek to Private Gate

Thursday 6/24

Slurry Seal
Village Parkway: Cold Springs Drive to Village Center Drive

Friday 6/25

Slurry Seal
Village Parkway: Cold Springs Drive to Village Center Drive

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction of this project will begin Monday, June 14, 2021 at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 6th Avenue

Work will include roadside replacement of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting was awarded the contract.  Construction is scheduled to begin July 6, 2021.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Ongoing construction work will include isolated utility improvements followed by complete reconstruction of sidewalk and roadway.

Traffic control will include isolated lane shifts and flagger controls within project area during utility work.

 

RENO CONSOLIDATED 21-01 – LUND LANE, YUMA LANE, ARMSTRONG LANE
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane (Yuma Lane to Sunsileen Drive) and Yuma Lane (Armstrong Lane to Hunter Lake Drive) construction in progress.

Roadway closure to through traffic starting April 12 through mid-June 2021, for roadway rehabilitation.  Follow detour around construction project.  Project is expected to be completed by end of June, 2021.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Construction in progress.

Traffic Control will be in place on Packer Way.  Business access will be maintained; follow directional signage.

Paving will take place on Sunday, June 20, 2021.

 

June 10, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

WEEK 4

Sunday 6/13/2021
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard

Monday 6/14/2021
Pavement Patching
York Way: Rock Boulevard to McCarran Boulevard
Nugget Avenue: Victorian Plaza Circle (West) to Pyramid Highway
Stanford Way: Railroad Crossing to Glendale Avenue
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard

Tuesday 6/15/2021
Pavement Patching
Damonte Ranch Parkway: I580 NB Exit Ramp to End of Pavement
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
First Street: Arlington Avenue to Sierra Street
Fourth Street: West Street to Galletti
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street
Parr Boulevard: Virginia Street to US395
Second Street: Keystone Street to Virginia Street
Sixth Street: Ralston Street to Virginia Street
Sunshine Lane: Mill Street to Cul-De-Sac
Sutro Street: Second Street to McCarran Boulevard

Wednesday 6/16/2021
Pavement Patching
Redfield Parkway: Virginia Street to Kietzke Lane
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
First Street: Arlington Avenue to Sierra Street
Fourth Street: West Street to Galletti
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street
Parr Boulevard: Virginia Street to US395
Second Street: Keystone Street to Virginia Street
Sixth Street: Ralston Street to Virginia Street
Sunshine Lane: Mill Street to Cul-De-Sac
Sutro Street: Second Street to McCarran Boulevard

Thursday 6/17/2021
Pavement Patching
Moana Lane: Plumas Street to Neil Road
Lymbery Street: Cadillac Place to Lakeside Drive
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
First Street: Arlington Avenue to Sierra Street
Fourth Street: West Street to Galletti
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street
Parr Boulevard: Virginia Street to US395
Second Street: Keystone Street to Virginia Street
Sixth Street: Ralston Street to Virginia Street
Sunshine Lane: Mill Street to Cul-De-Sac
Sutro Street: Second Street to McCarran Boulevard

Friday 6/18/2021
Pavement Patching
Gentry Way: Virginia Street to Kietzke Lane
Grove Street: Wrondel Way to Kietzke Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting April 12, 2021 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Traffic Control will be in place on Packer Way starting May 17, 2021. Business access will be maintained; follow directional signage.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From 7th Avenue to Highland Ranch Parkway:

  • Construction completed.
  • Road open with no restrictions.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract and construction will begin July 6, 2021.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Construction of this project starts June 7, 2021 work will include isolated utility improvements followed by complete reconstruction of sidewalk and roadway.

  • Traffic control will include isolated lane shifts within project area during utility work.

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction of this project will begin Monday, June 14, 2021 at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 6th Avenue

Work will include roadside replacement of bus stop pads and sidewalk.

  • Traffic control will include isolated shoulder closures and lane shifts.

 

June 3, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

WEEK 2

Thursday 6/3/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E.Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

Friday 6/4/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

WEEK 3

Monday 6/7/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker LanE
Pavement Patching
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp

Tuesday 6/8/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevar
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane
Pavement Patching
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Susileen Drive: Marthiam Avenue to Meridian Lane

Wednesday 6/9/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane
Pavement Patching
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
York Way: Rock Boulevard to McCarran Boulevard
Nugget Avenue: Victorian Plaza Circle (West) to Pyramid Highway
Stanford Way: Railroad Crossing to Glendale Avenue

Thursday 6/10/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane
Pavement Patching
Isidor Court: West Calle De La Plata to Circuit Court
La Posada Drive: Pyramid Highway to Omni Drive
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Wolverine Way: Glendale Avenue to Stanford Way
Coney Island Drive: Marietta Way to Stanford Way
Spice Island Drive: Greg Street to Franklin Way
Mira Loma Drive: Longley Lane to Veterans Parkway

Friday 6/11/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane
Pavement Patching
Baring Boulevard: McCarran Boulevard to Vista Boulevard
East Greenbrae Drive: Howard Drive to Prater Way
Prater Way: View Street to Pyramid Highway

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting April 12, 2021 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Traffic Control will be in place on Packer Way starting May 17, 2021. Business access will be maintained; follow directional signage.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From 7th Avenue to Highland Ranch Parkway:

  • Construction completed.
  • Road open with no restrictions.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract and construction will begin July 6, 2021.

 

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Construction of this project starts June 7, 2021 work will include isolated utility improvements followed by complete reconstruction of sidewalk and roadway.

  • Traffic control will include isolated lane shifts within project area during utility work.

 

 

 

 

May 27, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

WEEK 2

Monday 5/31/2021
NO WORK SCHEDULED

Tuesday 6/1/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

Wednesday 6/2/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

Thursday 6/3/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E.Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

Friday 6/4/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction projec 

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Traffic Control will be in place on Packer Way starting May 17, 2021. Business access will be maintained; follow directional signage.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From 7th Avenue to Highland Ranch Parkway:

  • Construction completed: minor items and miscellaneous work
  • Road open with no restrictions.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract and construction will begin July 6, 2021.

 

 

 

 

 

May 20, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

WEEK 1

Monday 5/24/2021
NO WORK SCHEDULED

Tuesday 5/25/2021
Pavement Crack Sealing
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Panther Drive: Virginia Street to Western Road

Wednesday 5/26/2021
Pavement Crack Sealing
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Panther Drive: Virginia Street to Western Road

Pavement Patching
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)

Thursday 5/27/2021
Pavement Crack Sealing
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Panther Drive: Virginia Street to Western Road

Pavement Patching
Isidor Court: West Calle De La Plata to Circuit Court

Friday 5/28/2021
Pavement Crack Sealing
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Panther Drive: Virginia Street to Western Road

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting April 12, 2021 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Traffic Control will be in place on Packer Way starting May 17, 2021. Business access will be maintained; follow directional signage.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Construction completed: minor items and miscellaneous work.
  • Sun Valley Boulevard OPEN (north/south).
  • Minor and Intermittent lane/shoulder closures at 7th Aveune intersection.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract. Construction will begin May 30, 2021.

 

Virginia Street Bus RAPDIT Transit Extension Project
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Sierra Street to 15th Street Southbound traffic is detoured at Sierra Street for maintenance and repair work at North Virignia Roundabout.

 

 

 

 

May 14, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Full roadway closure on Wild Island Court starting 4/12 through mid-May for roadway rehabilitation. Follow detour and business access signs for access to Outback Steakhouse and Cocoanut Bowl which are open for business. Work on Packer Way will begin mid-May.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Finishing construction and miscellaneous work
  • Sun Valley Boulevard OPEN (north/south)
  • Minor and Intermittent lane closures at 7th Avenue intersection

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract and construction will begin May 30, 2021.

 

 

May 6, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Full roadway closure on Wild Island Court starting 4/12 through mid-May for roadway rehabilitation. Follow detour and business access signs for access to Outback Steakhouse and Cocoanut Bowl which are ope for business. Work on Packer Way will begin mid-May.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Finishing construction and miscellaneous work
  • Sun Valley Boulevard OPEN (north/south)
  • Intermittent lane closures at 7th Avenue intersection
  • Detours in place

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting is apparent low bidder, contract will be awarded April 23rd and construction will begin May 30, 2021.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Avenue and Mae Anne Avenue traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.

PROJECT IS SUBSTANTIALLY COMPLETE

 

April 29, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Full roadway closure on Wild Island Court starting 4/12 through mid-May for roadway rehabilitation. Follow detour and business access signs for access to Outback Steakhouse and Cocoanut Bowl which are ope for business. Work on Packer Way will begin mid-May.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Raising utilities, stripping and miscellaneous work
  • Sun Valley Blvd OPEN (north/south)
  • Intermittent lane closures at 7th Ave intersection
  • Detours in place

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting is apparent low bidder, contract will be awarded April 23rd and construction will begin May 30, 2021.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Aveue and Mae Anne Aveue traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.  The next phase of this project, restriping York at Pyramid will begin April 23rd.

 

April 22, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Full roadway closure on Wild Island Court starting 4/12 through mid-May for roadway rehabilitation. Follow detour and business access signs for access to Outback Steakhouse and Cocoanut Bowl which are ope for business. Work on Packer Way will begin mid-May.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Raising utilities, stripping and miscellaneous work
  • Sun Valley Boulevard OPEN (north/south)
  • Intermittent lane closures at 7th Aveue intersection
  • Detours in place

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting is apparent low bidder, contract will be awarded April 23rd and construction will begin May 30, 2021.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Aveue and Mae Anne Aveue traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.  The next phase of this project, restriping York at Pyramid will begin April 23rd.

 

April 16, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Ln to Sunsileen Dr & Yuma Ln – Armstrong Ln to Hunter Lake Dr.:

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Paving operations and traffic signal activation
  • Sun Valley Blvd OPEN (north/south)
  • Intermittent lane closures at 7th Ave intersection
  • Detours in place

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting is apparent low bidder, contract will be awarded April 23rd and construction will begin May 30, 2021.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Ave. and Mae Anne Ave. traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.  The next phase of this project, restriping York at Pyramid will begin April 23rd.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Arlington & Mt Rose:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Rock Blvd & Mill St.:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

April 8, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Lund Lane – Wedekind Road to Northtowne Lane:

  • Full roadway closure 3/22 to 4/9 for roadway rehabilitation. Follow detour via. El Rancho and N. McCarran for access to Northtowne Shopping Center.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Paving operations
  • Sun Valley Blvd OPEN (north/south)
  • Intermittent lane closures at 7th Ave intersection
  • Detours in place

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Ave. and Mae Anne Ave. traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.  The next phase of this project, restriping York at Pyramid will begin April 23rd.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Blvd & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Sierra St.  @ 1st St. & 2nd St..:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Virginia/Court St.:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Ralston St @ 4th St. & 2nd St.:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Arlington @ 4th & Mt Rose:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of 7th & Stoker:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

April 1, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Lund Lane – Wedekind Road to Northtowne Lane:

  • Full roadway closure 3/22 to 4/9 for roadway rehabilitation. Follow detour via. El Rancho and N. McCarran for access to Northtowne Shopping Center.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Paving operations
  • Sun Valley Boulevard OPEN (north/south)
  • 7th Ave intersection CLOSED (east side): April 5 – April 9
  • Detours in place thru 6th Avenue and 8Th Ave via Leon Drive

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Traffic signal work continues at Sharlands Avenue. and Mae Anne Avenue.  Potential shoulder and sidewalk closures will take place first week of April 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Blvd & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.
  • Traffic Signal expected to be operational on 4/1/2021

Intersection of Sierra St.  @ 1st St. & 2nd St..:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Virginia/Court St.:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Ralston St @ 4th St. & 2nd St.:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Arlington @ 4th & Mt Rose:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of 7th & Stoker:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

 

March 26, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Lund Lane – Wedekind Rd to Northtowne Lane:

  • Full roadway closure 3/22 to 4/9 for roadway rehabilitation. Follow detour via. El Rancho and N. McCarran for access to Northtowne Shopping Center.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Paving operations
  • Sun Valley Blvd OPEN (north/south)
  • 7th Ave CLOSED (east/west): March 29 – April 9
  • Detours in place

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction continues with ADA ramp work on the corners at Sharlands Ave. and Mae Anne Ave.  Potential lane and sidewalk closures will take place throughout March 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Blvd & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of 6th & Valley Rd:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Sierra St.  @ 1st St. & 2nd St..:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Virginia/Court St.:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Ralston St @ 4th St. & 2nd St.:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Arlington @ 4th & Mt Rose:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of 7th & Stoker:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

 

March 18, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Lund Lane – Wedekind Road to Northtowne Lane:

  • Full roadway closure 3/22 to 4/9 for roadway rehabilitation. Follow detour via. El Rancho and N. McCarran for access to Northtowne Shopping Center.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.
  • Pedestrian rail installation – northbound lane closure/flaggers one-lane, two-way during construction hours.

From Staci Way to 7th Avenue:

  • Intermittent lane closures and detours.
  • Traffic signal installation.
  • Median installation.
  • Intersection closure: March 29 – April 9
  • Detours in place

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction continues with ADA ramp work on the corners at Sharlands Avenue and Mae Anne Avenue  Potential lane and sidewalk closures will take place throughout March 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Boulevard & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of 6th & Valley Road:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Sierra Street  at 1st Street & 2nd Street:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Virginia/Court Street:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Ralston St at 4th Street. & 2nd Street:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Arlington at 4th & Mt Rose:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of 7th & Stoker:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

 

March 11, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.
  • Pedestrian rail installation – northbound lane closure

From Staci Way to 7th Avenue:

  • Intermitent lane closures and detours.
  • Traffic signal installation.
  • Intersection closure:
    • Southbound: March 29 & 30
    • Northbound: March 31 & April 1

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction continues with ADA ramp work on the corners at Sharlands Avenue and Mae Anne Avenue Potential lane and sidewalk closures will take place throughout March 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Boulevard & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Mill Street & Lake Street:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center Street @ 1st St. & Plaza Street:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Sierra Street  @ 1st Street & 2nd Street:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Virginia/Court Street:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Ralston St @ 4th Street & 2nd Street:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

 

March 4, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.
  • Pedestrian rail installation.

From Staci Way to 7th Avenue:

  • Intermitent lane closures and detours.
  • Traffic signal installation.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction continues with ADA ramp work on the corners at Sharlands Ave. and Mae Anne Ave.  Potential lane and sidewalk closures will take place throughout March 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Blvd & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Mill St. & Lake St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center St. @ 1st St. & Plaza St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Sierra St.  @ 1st St. & 2nd St..:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Project is complete with roadway open to traffic. For the most up to date information on the project, please visit the Virginia Street Website

 

February 25, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Construction to resume Monday March 1st.
  • Lane closures and detours in place.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin on a traffic signal at the intersection of Sharlands Avenue and Mae Anne Avenue Potential lane and sidewalk closures will take place throughout February 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Boulvard & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Mill Street & Lake Street:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center Street & 1st Street:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center Street & Plaza Street:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Project is complete with roadway open to traffic. For the most up to date information on the project, please visit the Virginia Street Website

 

February 18, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume as soon as weather permits it.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin on a traffic signal at the intersection of Sharlands Ave. and Mae Anne Ave.  Potential lane and sidewalk closures will take place throughout February 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Blvd & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Mill St. & Lake St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center St. & 1st St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center St. & Plaza St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Project is complete with roadway open to traffic. For the most up to date information on the project, please visit the Virginia Street Website

 

February 12, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume as soon as weather permits it.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Beginning February 15, 2021 construction will begin on a traffic signal at the intersection of Sharlands Ave. and Mae Anne Ave.  Potential lane and sidewalk closures will take place throughout February 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Blvd & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Mill St. & Lake St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center St. & 1st St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to traffic with isolated shoulder and street parking closures to work on final punch list work. Look for construction signage as appropriate.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

February 5, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume as soon as weather permits it.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Beginning February 8, 2021 construction will begin on a traffic signal at the intersection of Sharlands Ave. and Mae Anne Ave.  Potential lane and sidewalk closures will take place throughout February 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Blvd & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of 6th St. & Valley Rd:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to traffic with isolated shoulder and street parking closures to work on final punch list work. Look for construction signage as appropriate.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

January 28, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume as soon as weather permits it.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Beginning February 8, 2021 construction will begin on a traffic signal at the intersection of Sharlands Avenue. and Mae Anne Avenue.  Potential lane and sidewalk closures will take place throughout February 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

 Intersection of Rock Boulevard & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of 6th Street. & Valley Road:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to traffic with isolated shoulder and street parking closures to work on final punch list work. Look for construction signage as appropriate.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

January 22, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/18 – 1/22
Work on fiber optic splicing with potential shoulder closures near South Meadows on-ramp at I 580 northbound.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume by Spring 2021 weather permitting.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to traffic with isolated shoulder and street parking closures to work on final punch list work. Look for construction signage as appropriate.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

January 14, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/12 – 1/22
Work on fiber optic splicing to continue on 1/12/21 with potential shoulder closures.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume by next Spring 2021 weather permitting.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – Is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street- Open to traffic with isolated shoulder and street parking closures to work on final punch list work. Look for construction signage as appropriate.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

January 8, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/12 – 1/22
Work on fiber optic splicing to continue on 1/12/21 with potential shoulder closures.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume by next Spring 2021 weather permitting.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – Is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street- Open to traffic with isolated shoulder and street parking closures to work on final punch list work. Look for construction signage as appropriate.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

December 30, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

12/4 – 12/31
No work scheduled.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

12/28 – 12/30
Work on fiber optic splicing to resume on 12/28 with potential shoulder closures.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume by next Spring 2021 weather permitting.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to traffic with isolated shoulder and street parking closures to work on final punch list work. Look for construction signage as appropriate.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

December 23, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

12/4 – 12/31
No work scheduled.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

12/21 – 12/28
No work planned, waiting on NDOT project on I-580.
Work on fiber optic splicing to resume on 12/28 with potential shoulder closures.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume by next Spring 2021 weather permitting.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street  – open to two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

December 17, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

12/4 – 12/31
No work scheduled.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

12/21 – 12/28
No work planned, waiting on NDOT project on I-580.
Work on fiber optic splicing to resume on 12/28 with potential shoulder closures.

 

PARK LANE RAPID STATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Virginia Street eastside just south of Plumb Lane.
Construction is completed NV Energy set the transformer and provide power to the RAPID Station. All work to be completed by 12/10/20.

Please use caution in construction zones for the safety of the public and the construction workers.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  •  Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume by next Spring 2021 weather permitting.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street  – open to two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

December 4, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

11/23 – 12/4
No work scheduled.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

12/7 – 12/31
No work planned, waiting on NDOT project on I-580.

 

PARK LANE RAPID STATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is completed waiting on NV Energy to install transformer and provide power to the RAPID Station on Virginia Street eastside just south of Plumb Lane.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Project is substantially completed and Traffic Control wil be removed by December 18, 2020.
  • From now until December 18:
    • Intermittent road sections with one lane closure, two-way traffic with flaggers during construction hours.
    • Intermittent shoulder closures.

From Staci Way to 7th Avenue:

  • Winter suspension. Construction will resume by next Spring 2021 weather permitting.
    • Intermittent lane and shoulder closures with detours.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

 

For the most up to date information on traffic control, please visit the Virginia Street Website

 

November 25, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

11/23 – 12/4
No work scheduled.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

11/30 – 12/14
No work planned, waiting on NDOT project on I-580.

 

PARK LANE RAPID STATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is completed waiting on NV Energy to install transformer and provide power to the RAPID Station on Virginia Street eastside just south of Plumb Lane.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

Sun Valley Boulevard:

  • Intermittent road sections with one lane closure, two-way traffic with flaggers during construction hours.
  • Intermittent shoulder closures.

7th Avenue:

  • Utility underground and signal base work.
  • Intermittent lane and shoulder closures with detours.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to north of roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements.  Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

 

For the most up to date information on traffic control, please visit the Virginia Street Website

November 20, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

11/23 – 12/7
No work planned, waiting on NDOT project on I-580.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

11/16 – 11/30
No work planned, waiting on NDOT project on I-580.

 

PARK LANE RAPID STATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is completed waiting on NVE to install transformer and provide power to the RAPID Station on Virginia Street eastside just south of Plumb Lane.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

Sun Valley Boulevard:

    • Intermittent road sections with one lane closed, two-way traffic with flaggers during construction hours.
    • Intermittent shoulder closures.
  • 7th Ave:
    • Utility underground and signal base work.
    • Intermittent lane and shoulder closures with detours.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage and detours as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

For the most up to date information on traffic control, please visit the Virginia Street Website

November 13, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 11/16/2020
Utility Adjustments
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Tuesday 11/17/2020
Utility Adjustments
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Wednesday 11/18/2020
Utility Adjustments
West Calle De La Plata: Isidor Court to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Thursday 11/19/2020
Utility Adjustments
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Friday 11/20/2020
Utility Adjustments
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

11/16 – 11/30
No work planned, waiting on NDOT project on I-580.

 

PARK LANE RAPID STATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is completed waiting on NVE to install transformer and provide power to the RAPID Station on Virginia Street eastside just south of Plumb Lane.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

Sun Valley Boulevard:

  •  Intermittent road sections with one lane closed, two-way traffic with flaggers during construction hours.
  • Intermittent shoulder closures.

7th Ave:

  • Utility underground
  • Intermittent lane and shoulder closures with detours

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to North of Roundabout – is open to traffic with isolated and shoulder and/or lane closures to work on final project elements. Look for construction signage and detours as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

For the most up to date information on traffic control, please visit the Virginia Street Website

November 6, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 11/9/2020

Utility Adjustments
Greg Street: Mill Street to Stanford Way

Tuesday 11/10/2020

Utility Adjustments
Brierley Way: Lillard Way to Vista Boulevard
Marina Gateway Drive: Lincoln Way to East Prater Way
East Lincoln Way: McCarran Boulevard to Sparks Boulevard

Wednesday 11/11/2020

Utility Adjustments
Wedekind Road: Lund Lane to El Rancho Drive
Richard Springs Boulevard: Eagle Canyon Drive to Shelby Drive

Thursday 11/12/2020

Utility Adjustments
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Friday 11/13/2020

Utility Adjustments
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

11/9 – 11/30

No work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Project is Completed.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is completed between Evan Creek Drive and McCarran Boulevard.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along northbound Virginia Street with lane shifts.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

Sun Valley Boulevard:
• One lane closed, two-way traffic with flaggers during construction hours.
• Intermittent shoulder closures.

  • 7th Ave:
    • Utility underground
    • Intermittent lane and shoulder closures with detours

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to 8th Street – is open to traffic with isolated and shoulder and/or lane closures. Look for detour signage as appropriate.
  • 8th Street to 9th Street – is closed to southbound traffic. Southbound traffic is detoured at 9th Street to Sierra Street. Look for detour signage as appropriate.
  • 9th Street to 15th Street – traffic is reduced to one-lane in each direction. Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection – traffic is reduced to one-way northbound direction only. Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street. This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street and 9th Street at North Virginia Street – look for construction signage as appropriate or isolated lane and shoulder closures.

South Virginia Street:

  • Plumb Lane to Liberty Street – open to two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

For the most up to date information on traffic control, please visit the Virginia Street Website

October 23, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 10/23

Utility Adjustments
Sierra Street: Eleventh Street to California Avenue

Monday 10/26

Utility Adjustments
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Tuesday 10/27

Utility Adjustments
Plumas Street: Ridgeview Drive to Plumb Lane

Wednesday 10/28

Utility Adjustments
Sierra Rose Drive: Talbot Road to Kietzke Lane
Kietzke Lane: south end cul-de-sac to Virginia Street

Thursday 10/29

Utility Adjustments
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Friday 10/30
NO WORK SCHEDULED

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

10/26 – 11/2

No work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Giroux Street from E 2nd Street to Kuenzli:
Construction is substantially completed.  Expect final minor work throughout the week.

Kuenzli Street from Giroux Street to Kirman Avenue:
Construction is substantially completed.  Expect final minor work throughout the week.

Kuenzli Street/Locust Street:
Construction is substantially completed.  Expect final minor work throughout the week.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is substantially complete. Minor traffic control between Evan Creek Drive and McCarran Boulevard for punch list items to be done.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along northbound Virginia Street with lane shifts.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard  

  • One lane closed, two-way traffic with flaggers during construction hours.
  • Intermittent shoulder closures.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street

  • Maple Street to 8th Street – is open to traffic with isolated and shoulder and/or lane closures. Look for detour signage as appropriate.
  • 8th Street to 9th Street – is closed to southbound traffic. Southbound traffic is detoured at 9th Street to Sierra Street. Look for detour signage as appropriate.
  • 9th Street to 15th Street – traffic is reduced to one-lane in each direction. Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection – traffic is reduced to one-way northbound direction only. Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street. This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street and 9th Street at North Virginia Street – look for construction signage as appropriate or isolated lane or shoulder closures.

South Virginia Street

  • Plumb Lane to Liberty Street – open to two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

For the most up to date information on traffic control, please visit the Virginia Street Website

October 16 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 10/19/2020

 NO WORK SCHEDULED

Tuesday 10/20/2020

Utility Adjustments
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Booth Street: California Avenue to Riverside Drive

Wednesday 10/21/2020

Utility Adjustments
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Booth Street: California Avenue to Riverside Drive

Thursday 10/22/2020

Utility Adjustments
Plumas Street: Ridgeview Drive to Plumb Lane
Sinclair Street: Holcomb Avenue to Mill Street

Friday 10/23/2020

Utility Adjustments
Sierra Street: Eleventh Street to California Avenue

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

10/1 – 10/19: no work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is in progress and expected to be completed by 10/23.

Giroux Street from E 2nd Street to Kuenzli:
Expect lane closures for pavement slurry sealing and striping this week.

Kuenzli Street from Giroux Street to Kirman Avenue:
Expect lane closures for pavement slurry sealing and striping this week.

Kuenzli Street/Locust Street:
Expect lane closures for pavement slurry sealing and striping this week.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is substantially complete. Minor traffic control between Evan Creek Drive and McCarran Boulevard for punch list items to be done.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along northbound Virginia Street with lane shifts.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.
Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard

  • 9/28 – 10/23:
    • Southbound traffic closed between 7th Avenue and Highland Ranch Parkway
    • Detour (southbound):

 

      • Highland Ranch Parkway to Midninght Drive to Lightning Drive to Magenta Drive to 7th Avenue
    • Intermittent closures (no access) at intersections:
      • Arapaho Drive
      • Leon Drive
      • Middle Fork Drive
      • Sidehill Drive
      • Quartz Lane
      • 8th Avenue
      • Mineral Avenue
      • Staci Way
  • Highland Ranch Parkway Intersection
    • Intermittent closures, but open during peak commute periods.
    • Detour:
      • To Debussey Drive/Donatello Drive

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street within this open to traffic with isolated and intermeidan shoulder and/or lane closures. Look for detour signage as appropriate.
  • 8th Street to 9th Street: North Virginia Street within this segment is closed to southbound traffic. Southbound is detoured at 9th to Sierra Street. Look for detour signage as appropriate.
  • 9th Street to 15th Street: traffic is one-lane in each direction. Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection: traffic is reduced to one-way northbound direction only. Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street. This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street and 9th Street at North Virginia Street: Look for construction signage as appropriate or isolated lane or shoulder closures.

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with isolated shoulder and street parking closures to work on final punch list work.

For the most up to date information on traffic control, please visit the Virginia Street Website

October 8 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 10/12/2020
Micro-Surfacing
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

Tuesday 10/13/2020
Micro-Surfacing
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

Wednesday 10/14/2020
NO WORK SCHEDULED

Thursday 10/15/2020
Pavement Striping (Thermoplastic Markings)
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

Friday 10/16/2020
Pavement Striping (Thermoplastic Markings)
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is substantially complete.  There will be minor traffic impacts at the intersection of Greg Street and Spice Island Drive through September 2020.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

10/1 – 10/19: no work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is in progress and expected to be completed by 10/23.

Giroux Street from E 2nd Street to Kuenzli:
Expect lane closures for pavement slurry sealing and striping this week.

Kuenzli Street from Giroux Street to Kirman Avenue:
Expect lane closures for pavement slurry sealing and striping this week.

Kuenzli Street/Locust Street:
Expect lane closures for pavement slurry sealing and striping this week.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is anticipated to be completed and traffic control removed between Evan Creek Drive and McCarran Boulevard.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along Northbound Virginia Street with lane shifts.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.
Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard

  • 9/28 – 10/23:
    • Southbound traffic closed between 7th Avenue and Highland Ranch Parkway
    • Detour:
      • Highland Ranch Parkway to Midninght Drive to Lightning Drive to Magenta Drive to 7th Avenue
    • Intermittent closures (no access) at intersections:
      • Arapaho Drive
      • Leon Drive
      • Middle Fork Drive
      • Sidehill Drive
      • Quartz Lane
      • 8th Avenue
      • Mineral Avenue
      • Staci Way
  • Highland Ranch Parkway Intersection
    • Intermittent closures, but open during peak commute periods.
    • Detour:
      • To Debussey Drive/Donatello Drive

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street within this segment to be closed to north-south traffic during first half of week of October 12, later half of the week traffic is expected to return. Flaggers will be providing additional direction to traffic. Look for detour signage as appropriate.
  • 8th Street to 9th Street: North Virginia Street within this segment is closed to southbound traffic. This segment will be closed to northbound traffic during the first half of the week of October 12th. Flaggers will be providing additional direction to traffic. Look for detour signage as appropriate.
  • 9th Street to 15th Street: traffic is one-lane in each direction. Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection: traffic is reduced to one-way northbound direction only. Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street. This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street and 9th Street at North Virginia Street: Flaggers will be providing additional direction to the traveling public during working hours at these intersections. Look for construction signage as appropriate.

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.

For the most up to date information on traffic control, please visit the Virginia Street Website

October 2 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 10/5/2020

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

Tuesday 10/6/2020

Pavement Patching
Rio Wrangler Parkway: Veterans Parkway to Virginia Vista Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

Wednesday 10/7/2020

Pavement Patching
Rio Wrangler Parkway: Veterans Parkway to Virginia Vista Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

Thursday 10/8/2020

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

Friday 10/9/2020

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is substantially complete.  There will be minor traffic impacts at the intersection of Greg Street and Spice Island Drive through September 2020.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

10/1 – 10/19: no work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is in progress and expected to be completed by 10/23.

Giroux Street from E 2nd Street to Kuenzli:
• Expect lane closures for pavement patching and crack sealing this week.

Kuenzli Street from Giroux Street to Kirman Avenue:
• Expect lane closures for pavement patching and crack sealing this week.

Kuenzli Street/Locust Street:
• Expect lane closures for pavement patching and crack sealing this week.

Slurry sealing begins 10/5 expect delays, detours and periodic lanes closures throughout the project. Expected to be completed on 10/6.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is anticipated to be completed and traffic control removed between Evan Creek Drive and McCarran Boulevard.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along Northbound Virginia Street with lane shifts.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.
Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

Sun Valley Boulevard

9/28 – 10/23:

  • Southbound traffic closed between 7th Avenue and Highland Ranch Parkway
  • Detour:
    • Highland Ranch Parkway to Midninght Drive to Lightning Drive to Magenta Drive to 7th Ave
  • Intermittent closures (no access) at intersections:
      • Arapaho Drive
      • Leon Drive
      • Middle Fork Drive
      • Sidehill Drive
      • Quartz Lane
      • 8th Avenue
      • Mineral Avenue
      • Staci Way
  • Highland Ranch Parkway Intersection
    • Intermittent closures, but open during peak commute periods.
    • Detour:
      • To Debussey Dr/Donatello Drive

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to 9th Street: paving operations are planned for the first half of the week of October5. This will require North Virginia Street within this segment to be closed to north-south traffic. Traffic along Maple, 8th Street and 9th Street will have interim disruptions during normal working hours, flaggers will be providing direction to traffic. Look for detour signage as appropriate.
  • 9th Street to 15th Street: traffic is one-lane in each direction. Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection: traffic is reduced to one-way northbound direction only. Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street. This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street: paving operations may temporarily impact 8th Street at North Virginia Street.
  • 9th Street: paving operations may temporarily impact 9th Street at North Virginia Street. 9th Street is reduced to eastbound (one-lane) traffic between North Virginia Street and Center Street. Westbound traffic is directed to use 8th Street.

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center Street at Cheney Street: closed to buses and large trucks through the end of the month to allow for concrete curing. The street is open but reduced to one lane for through traffic. Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website

September 24 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 9/28/2020
Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

Tuesday 9/29/2020
Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

Wednesday 9/30/2020
Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

Thursday 10/1/2020
Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

Friday 10/2/2020
Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: Second Coat Paint Application

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is substantially complete.  There will be minor traffic impacts at the intersection of Greg Street and Spice Island Drive through September 2020.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

9/18 – 9/25: no work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is in progress 9/21 – 9/28

Giroux Street from E 2nd Street to Kuenzli:
• Traffic lanes have been reduced to one lane for pedestrian sidewalk improvements.

Kuenzli Street from Giroux Street to Kirman Avenue:
• Traffic lanes have been reduced to one lane for pedestrian sidewalk improvements.

Kuenzli Street/Locust Street:
• The traffic signal at Kuenzli Street and Locust Street is being removed, expect 4-way stop controls.
• Locust Street between East 2nd Street and Kuenzli Street is closed for signal removal. Please detour to Kuenzli Street and Kirman Avenue intersection.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.
Traffic controls are in place along the project. Traffic is reduced to one-lane in each direction with some flagger controls, minor delays expected.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along northbound Virginia Street with lane shifts.

Please use caution in the construction zone.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

Sun Valley Boulevard:

  • 9/28 – 10/23:
    • Southbound traffic closed between 7th Avenue and Highland Ranch Parkway
    • Detour:
      • Highland Ranch Parkway Intersection:
  • Highland Ranch Parkway Intersection:
    • Intermittent closures, but open during peak commute periods.
    • Detour:
      • To Debussey Drive/Donatello Drive

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to 9th Street: paving operations are planned for the week of September 28. This will require North Virginia Street within this segment to be closed to north-south traffic. Traffic along Maple, 8th Street and 9th Street will have interim disruptions during normal working hours, flaggers will be providing direction to traffic. Look for detour signage as appropriate.
  • 9th Street to 15th Street: traffic is reduced to one-lane in each direction. Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection: traffic is reduced to one-way northbound direction only. Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street. This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street: paving operations may temporarily impact 8th Street at North Virginia Street.
  • 9th Street: paving operations may temporarily impact 9th Street at North Virginia Street. 9th Street is reduced to eastbound (one-lane) traffic between North Virginia Street and Center Street. Westbound traffic is directed to use 8th Street.

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center Street at Cheney Street: closed to buses and large trucks through the end of the month to allow for concrete curing. The street is open but reduced to one lane for through traffic. Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website

September 17, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 9/17

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mill Street: Wells Avenue to Lake Street
Mill Street: Matley Lane to Terminal Way
East Nugget Avenue: McCarran Boulevard to End of Pavement

Monday 9/21

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: second coat paint application
Mill Street: Wells Avenue to Lake Street
Mill Street: Matley Lane to Terminal Way

Tuesday 9/22

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: second coat paint application
Mill Street: Wells Avenue to Lake Street
Mill Street: Matley Lane to Terminal Way

Wednesday 9/23

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: second coat paint application

Thursday 9/24

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: second coat paint application

Friday 9/25

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Various Project Streets: second coat paint application

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is substantially complete.  There will be minor traffic impacts at the intersection of Greg Street and Spice Island Drive through September 2020.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

9/18 – 9/25: no work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is in progress 9/14 – 9/21

Giroux Street from E 2nd Street to Kuenzli:

  • Traffic lanes have been reduced to one lane for pedestrian sidewalk improvements.

Kuenzli Street from Giroux Street to Kirman Avenue:

  • Traffic lanes have been reduced to one lane for pedestrian sidewalk improvements.

Kuenzli Street/Locust Street:

  • The traffic signal at Kuenzli Street and Locust Street is being removed, expect 4-way stop controls.
  • Locust Street between E  2nd Street and Kuenzli Street is closed for signal removal.  Please detour to Kuenzli Street and Kirman Avenue intersection.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.
Traffic controls are in place along the project. Traffic is reduced to one-lane in each direction with some flagger controls, minor delays expected.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along northbound Virginia Street with lane shifts.

Please use caution in the construction zone.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

Sun Valley Boulevard:

  • Intermittent shoulder closure at various intersections.
  • One lane closures with two-way traffic maintained with flaggers.
    • 9/14 – 9/25: from 7th Avenue to Staci Way and from Mineral Avenue to Middlefork Drive
    • 9/17 – 9/22: from Middlefork Drive to Leon Drive
    • Starting Monday 9/28: Road closure with detours.  Expect LONGER than usual delays.

7th Avenue intersection:

  • Intermittent shoulder and lane closure with possible detours.
    • 9/17 – 9/25: one lane closure from Applegate Drive to Sun Valley Boulevard. Detours in place.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place – southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 8th Street to 9th Street: through traffic is detoured to Sierra Street – local traffic permitted.
  • 9th Street to 15th Street: traffic is reduced to one-lane in each direction.  Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection: traffic is reduced to one-way northbound direction only.
    • Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street.  This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.
  • 9th Street: is reduced to eastbound (one-lane) traffic between North Virginia Street and Center Street.  Westbound traffic is directed to use 8th Street.

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center Street at Cheney Street: closed to buses and large trucks through the end of the month to allow for concrete curing. The street is open but reduced to one lane for through traffic. Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

September 11, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 9/11

Micro-Surfacing
East Nugget Avenue: McCarran Boulevard to end of pavement
East Nugget Court: Nugget Avenue to cul-de-sac

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Nugget Avenue: McCarran Boulevard to end of pavement
East Nugget Court: Nugget Avenue to cul-de-sac
East Greg Street: Stanford Way to McCarran Boulevard
East Greg Street: Railroad Crossing to Sparks Boulevard
Watson Way: Kresge Lane to Glendale Avenue
Dunn Circle: Glendale Avenue to Watson Way

Saturday 9/12

Micro-Surfacing
East Nugget Avenue: McCarran Boulevard to end of pavement
Evans Avenue: Jodi Drive to Enterprise Drive
Booth Street: California Avenue to Riverside Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Nugget Avenue: McCarran Boulevard to end of pavement
Evans Avenue: Jodi Drive to Enterprise Drive
Booth Street: California Avenue to Riverside Drive

Monday 9/13

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Greg Street: railroad crossing to Sparks Boulevard
Dunn Circle: Glendale Avenue to Watson Way
Watson Way: Kresge Lane to Glendale Avenue

Tuesday 9/14

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Greg Street: railroad crossing to Sparks Boulevard
Dunn Circle: Glendale Avenue to Watson Way
Watson Way: Kresge Lane to Glendale Avenue

Wednesday 9/15

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mill Street: Wells Avenue to Lake Street
Mill Street: Matley Lane to Terminal Way
Evans Avenue: Jodi Drive to Enterprise Drive
Booth Street: California Avenue to Riverside Drive

Thursday 9/16

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mill Street: Wells Avenue to Lake Street
Mill Street: Matley Lane to Terminal Way
East Nugget Avenue: McCarran Boulevard to end of pavement
Evans Avenue: Jodi Drive to Enterprise Drive
Booth Street: California Avenue to Riverside Drive

Friday 9/17

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mill Street: Wells Avenue to Lake Street
Mill Street: Matley Lane to Terminal Way
East Nugget Avenue: McCarran Boulevard to end of pavement

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by early September 2020.

Traffic is reduced to one-lane in each direction between McCarran Boulevard and railroad tracks. Two-way traffic will continue within the construction zone

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

9/18 – 9/25

No work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction begins September 14, 2020.  Expect lane reductions and detours along Kuenzli Street, Giroux Street, and Kirman Avenue.  More details to follow next week.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.
Traffic controls are in place along the project. Traffic is reduced to one-lane in each direction with some flagger controls, minor delays expected.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along Northbound Virginia Street with lane shifts.

Please use caution in the construction zone.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

  • Starting Monday 9/28:
    • Intermittent shoulder closures at various intersections.  One lane closures with two-way traffic maintained. Expect LONGER than usual delays.
  • Sun Valley Boulevard:
    • One lane closure from Quartz Lane to Leon Drive.
    • One lane closure from 7th Avenue to Staci Drive.
  • 7th Avenue intersection:
    • Intermittent shoulder and lane closure with detours.
    • Between Sidehill Drive and Sun Valley Boulevard:
      • Monday and Tuesday 9/14 – 9/15: road closure during working hours only.  Detours in place.  Road open overnight.
      • Wednesday thru Friday 9/16 – 9/18: intermittent one-lane closure with flaggers.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center Street at Cheney Street: closed to buses and large trucks through the end of the month to allow for concrete curing.  The street is open but reduced to one lane for through traffic.  Detours will be in place.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 8th Street to 9th Street: traffic is reduced to southbound direction only.
    • Northbound traffic is detoured to Sierra Street.
  • 9th Street to 15th Street: traffic is reduced to one-lane in each direction.  Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection: traffic is reduced to one-way northbound direction only.
    • Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street.  This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

September 4, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 9/7/2020

NO WORK (LABOR DAY)

Tuesday 9/8/2020

Micro-Surfacing
East Greg Street: Stanford Way to McCarran Boulevard
East Greg Street: Railroad Crossing to Sparks Boulevard
Dunn Circle: Glendale Avenue to Watson Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Plumas Street: Ridgeview Drive to Plumb Lane
East Greg Street: Stanford Way to McCarran Boulevard
East Greg Street: Railroad Crossing to Sparks Boulevard
Dunn Circle: Glendale Avenue to Watson Way

Wednesday 9/9/2020

Micro-Surfacing
East Greg Street: Stanford Way to McCarran Boulevard
East Greg Street: Railroad Crossing to Sparks Boulevard
Watson Way: Kresge Lane to Glendale Avenue

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Greg Street: Stanford Way to McCarran Boulevard
East Greg Street: Railroad Crossing to Sparks Boulevard
Watson Way: Kresge Lane to Glendale Avenue

Thursday 9/10/2020

Micro-Surfacing
Mill Street: Wells Avenue to Lake Street
Mill Street: Matley Lane to Terminal Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mill Street: Wells Avenue to Lake Street
Mill Street: Matley Lane to Terminal Way
East Greg Street: Stanford Way to McCarran Boulevard
East Greg Street: Railroad Crossing to Sparks Boulevard
Watson Way: Kresge Lane to Glendale Avenue
Dunn Circle: Glendale Avenue to Watson Way

Friday 9/11/2020

Micro-Surfacing
East Nugget Avenue: McCarran Boulevard to End of Pavement
East Nugget Court: Nugget Avenue to Cul-De-Sac

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Nugget Avenue: McCarran Boulevard to End of Pavement
East Nugget Court: Nugget Avenue to Cul-De-Sac
East Greg Street: Stanford Way to McCarran Boulevard
East Greg Street: Railroad Crossing to Sparks Boulevard
Watson Way: Kresge Lane to Glendale Avenue
Dunn Circle: Glendale Avenue to Watson Way

Saturday 9/12/2020

Micro-Surfacing
Evans Avenue: Jodi Drive to McCarran Boulevard
Booth Street: California Avenue to Riverside Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Evans Avenue: Jodi Drive to McCarran Boulevard
Booth Street: California Avenue to Riverside Drive

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between McCarran Boulevard and railroad tracks. Two-way traffic will continue within the construction zone

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

9/4 – 9/15

No work planned, waiting on NDOT project on I-580.

 

KUENZLI ST. PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction begins September 14, 2020. Expect lane reductions and detours along Kuenzli St., Giroux St., and Kirman Ave. More details to follow next week.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.
Traffic controls are in place along the project. Traffic is reduced to one-lane in each direction with some flagger controls, minor delays expected.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along Northbound Virginia Street with lane shifts.

Please use caution in the construction zone.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

  • Traffic Closure with Detours – starting Monday September 28

 

    • Intermittent shoulder closure at various intersections.
    • One lane closure, two-way traffic maintained. Expect LONGER than usual delays.
  • Sun Valley Boulevard:
    • One lane closure from Quartz Lane to Leon Drive.
  • One lane closure from 7th Avenue to Staci Drive.
  • 7th Avenue intersection:
  • Intermittent shoulder and lane closure with detours.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with daily, isolated shoulder and street parking closures to install project appurtenances.
    • During isolated occasions, northbound traffic between Center Street and Liberty Street will be detoured to Center Street (at Center Street).

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 15th Street to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
    • Paving operations on Monday, August 31 and Tuesday, September 1.  Detours will be in place, look for flaggers and signage.  Minor delays expected.
  • 15th Street to 8th Street: traffic is reduced to one-lane in each direction.  Some on-street parking is closed.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

August 28, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 8/28

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Third Street to California Avenue

Sunday 8/30

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Maple Street to California Avenue
Arlington Avenue: First Street to Skyline Boulevard

Monday 8/31

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Maple Street to California Avenue
Arlington Avenue: First Street to Skyline Boulevard
Plumas Street: Ridgeview Drive to Plumb Lane
Lakeside Drive: Brinkby Avenue to Moana Lane

Tuesday 9/1

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Maple Street to California Avenue
Plumas Street: Ridgeview Drive to Plumb Lane
Lakeside Drive: Brinkby Avenue to Moana Lane

Wednesday 9/2

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Maple Street to California Avenue
Plumas Street: Ridgeview Drive to Plumb Lane
Lakeside Drive: Brinkby Avenue to Moana Lane

Thursday 9/3

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Maple Street to California Avenue
Plumas Street: Ridgeview Drive to Plumb Lane
Lakeside Drive: Brinkby Avenue to Moana Lane

Friday 9/4

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Plumas Street: Ridgeview Drive to Plumb Lane
Lakeside Drive: Brinkby Avenue to Moana Lane

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between McCarran Boulevard and railroad tracks. Two-way traffic will continue within the construction zone

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

8/28 – 9/15

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.
Traffic controls are in place along the project. Traffic is reduced to one-lane in each direction with some flagger controls, minor delays expected.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along Northbound Virginia Street with lane shifts.

Please use caution in the construction zone.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

  • Intermittent shoulder closure at various intersections.
  • One lane closure, two-way traffic maintained. Expect LONGER than ususal delays.
  • Construction work on the east side of Sun Valley Boulevard. One lane closure from Quartz Lane to Leon Drive
  • 7th Avenue intersection: intermittent lane closure with detours.
    • 8/31 – 9/4: 7th Avenue westbound closed with detour in place via 6th Avenue and Staci Way.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with daily, isolated shoulder and street parking closures to install project appurtenances.
    • During isolated occasions, northbound traffic between Center Street and Liberty Street will be detoured to Center Street (at Center Street).

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 15th Street to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
    • Paving operations on Monday, August 31 and Tuesday, September 1.  Detours will be in place, look for flaggers and signage.  Minor delays expected.
  • 15th Street to 8th Street: traffic is reduced to one-lane in each direction.  Some on-street parking is closed.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

August 20, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Thursday 8/20

Micro-Surfacing
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Plumas Street: Ridgeview Drive to Plumb Lane
Sierra Street: Third Street to California Avenue
Kietzke Lane: south end cul-de-sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

Friday 8/21

Micro-Surfacing
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Plumas Street: Ridgeview Drive to Plumb Lane
Sierra Street: Third Street to California Avenue

Saturday 8/22

Micro-Surfacing
East Greg Street: Spice Island Drive to Sparks Boulevard

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Greg Street: Spice Island Drive to Sparks Boulevard

Sunday 8/23

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Greg Street: Spice Island Drive to Sparks Boulevard
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: Westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to east end of pavement
Kietzke Lane: south end cul-de-sac to Virginia Street

Monday 8/24

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: Westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to East End of Pavement
Kietzke Lane: south end cul-de-sac to Virginia Street

Tuesday 8/25

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: south end cul-de-sac to Virginia Street

Wednesday 8/26

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Third Street to California Avenue

Thursday 8/27

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Third Street to California Avenue

Friday 8/28

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Third Street to California Avenue

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between McCarran Boulevard and railroad tracks. Two-way traffic will continue within the construction zone

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

8/21 – 9/15

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard. Traffic controls are in place along the project.  Traffic is reduced to one-lane in each direction with some flagger controls, minor delays expected.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along Northbound Virginia Street with lane shifts.

Please use caution in the construction zone.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

  • Intermittent shoulder closure at various intersections.
  • One lane closure, two-way traffic maintained. Expect delays.
  • Construction work on the east side of Sun Valley Boulevard. One lane closure from Quartz Lane to Leon Drive
  • 7th Avenue intersection: intermittent lane closure with detours.
    • 8/20 – 8/28: westbound lane closed with detour in place.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with daily, isolated shoulder and street parking closures to install project appurtenances.
    • During isolated occasions, northbound traffic between Center Street and Liberty Street will be detoured to Center Street (at Center Street).

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 15th Street to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
  • 15th Street to 8th Street: traffic is reduced to one-lane in each direction.  Some on-street parking is closed.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

August 14, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Saturday 8/15/2020

Micro-Surfacing
Greg Street: Truckee River Bridge to Industrial Way
Greg Street: Stanford Way to McCarran Boulevard

Monday 8/17/2020

Micro-Surfacing
Plumas Street: Ridgeview Drive to Plumb Lane

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Plumas Street: Ridgeview Drive to Plumb Lane
Keystone Avenue: California Avenue to Seventh Street
Keystone-Booth Connector: Keystone Avenue to Booth Street
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: Westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to East End of Pavement

Tuesday 8/18/2020

Micro-Surfacing
Plumas Street: Ridgeview Drive to Plumb Lane

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Plumas Street: Ridgeview Drive to Plumb Lane
Keystone Avenue: California Avenue to Seventh Street
Keystone-Booth Connector: Keystone Avenue to Booth Street
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: Westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to East End of Pavement
Kietzke Lane: South End Cul-De-Sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

Wednesday 8/19/2020

Micro-Surfacing
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Idlewild Drive: Riviera Street to Booth Street
Kietzke Lane: South End Cul-De-Sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

Thursday 8/20/2020

Micro-Surfacing
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Plumas Street: Ridgeview Drive to Plumb Lane
Sierra Street: Third Street to California Avenue
Kietzke Lane: South End Cul-De-Sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

Friday 8/21/2020

Micro-Surfacing
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Plumas Street: Ridgeview Drive to Plumb Lane
Sierra Street: Third Street to California Avenue

Saturday 8/22/2020

Micro-Surfacing
East Greg Street: Spice Island Drive to Sparks Boulevard

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Greg Street: Spice Island Drive to Sparks Boulevard

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between McCarran Boulevard and railroad tracks. Two-way traffic will continue within the construction zone.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

8/14 – 9/15

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.
Traffic control is in place along the whole project. Traffic is reduced to one-lane in each direction with some flagger controls, minor delays expected. Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along Northbound Virginia Street with lane shifts. Please use caution in the construction zone.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

    • Intermittent shoulder closure at various intersections.
    • One lane closure, two-way traffic maintained. Expect delays.
    • Construction work on the east side of Sun Valley Boulevard. One lane closure from Quartz to Leon Drive
    • 7th Avenue intersection: intermittent lane closure with detours.
      • 8/20 – 8/21: 7th Avenue west bound at Sun Valley Boulevard will be closed with detour in place.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with daily, isolated shoulder and street parking closures to install project appurtenances.
    • During isolated occasions northbound between Center Street and Liberty will be detoured to Center Street (at Center Street).

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 15th Street to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
  • 15th Street to 8th Street: traffic is reduced to one-lane in each direction. Some on-street parking is closed.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

August 7, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 8/7

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Kietzke Lane: south end cul-de-sac to Virginia Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: south end cul-de-sac to Virginia Street
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to end
Legends “I”: George Ferris Drive to Scheels Drive
George Ferris Drive: Lincoln Way east roundabout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way

Sunday 8/9

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Kietzke Lane: south end cul-de-sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: south end cul-de-sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to end
Legends “I”: George Ferris Drive to Scheels Drive
George Ferris Drive: Lincoln Way east roundabout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to east end of pavement

Monday 8/10

Pavement Settlement Investigation
Rio Wrangler Parkway: Brittany Park Drive to Misty Meadows Drive

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Keystone Avenue: California Avenue to Seventh Street
Keystone-Booth Connector: Keystone Avenue to Booth Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Keystone Avenue: California Avenue to Seventh Street
Keystone-Booth Connector: Keystone Avenue to Booth Street
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to end
Legends “I”: George Ferris Drive to Scheels Drive
George Ferris Drive: Lincoln Way east roundabout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to east end of pavement

Tuesday 8/11

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Keystone Avenue: California Avenue to Seventh Street
Keystone-Booth Connector: Keystone Avenue to Booth Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Keystone Avenue: California Avenue to Seventh Street
Keystone-Booth Connector: Keystone Avenue to Booth Street
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to east end of pavement
Kietzke Lane: south end cul-de-sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

Wednesday 8/12

Pavement Patching
Watson Way: Kresge Lane to Glendale Avenue

Micro-Surfacing
Idlewild Drive: Riviera Street to Booth Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Idlewild Drive: Riviera Street to Booth Street
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to east end of pavement
Kietzke Lane: south end cul-de-sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

Thursday 8/13

Micro-Surfacing
Plumas Street: Ridgeview Drive to Plumb Lane
Sierra Street: Third Street to California Avenue

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Plumas Street: Ridgeview Drive to Plumb Lane
Sierra Street: Third Street to California Avenue
Kietzke Lane: south end cul-de-sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

Friday 8/14

Micro-Surfacing
Plumas Street: Ridgeview Drive to Plumb Lane
Sierra Street: Third Street to California Avenue

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Plumas Street: Ridgeview Drive to Plumb Lane
Sierra Street: Third Street to California Avenue
Kietzke Lane: south end cul-de-sac to Virginia Street
Sierra Rose Drive: Talbot Road to Kietzke Lane

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks.   The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between Spice Island Drive and railroad tracks during the hours of 7:00 AM to 6:00 PM.

Greg Street will be closed to through traffic between McCarran Boulevard and Franklin Way beginning Friday, August 7 at 7:00 PM until Monday, August 10 at 5:00 AM. for paving operations.

During paving operations, eastbound traffic on Greg Street will be detoured at Franklin Way to Glendale Avenue to McCarran Boulevard to Greg Street. Westbound traffic on Greg Street will be detoured at McCarran Boulevard to Glendale Avenue to Franklin Way to Greg Street.

Business-access traffic will be maintained on Greg Street between Franklin Way and the train tracks near Spice Island Drive. A traffic flagger will help direct residents in and out of the Apollo Mobile Home Park. All business and residential traffic should enter from the Greg Street/Franklin Way intersection.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

8/6 – 9/15

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.

Traffic control is in place along the whole project.  Traffic is reduced to one lane in each direction with some flagger controls, minor delays expected.  Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane.

Traffic controls are in place along Virginia Street with lane shifts.  Please use caution in the construction zone.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

    • Intermittent shoulder closure at various intersections.
    • One lane closure, two-way traffic maintained. Expect delays.
    • Construction work on the east side of Sun Valley Boulevard. One lane closure from Quartz to Leon Drive
    • 7th Avenue intersection: intermittent lane closure with detours.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Center Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center Street to Liberty Street: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center Street to Liberty Street.
    • Northbound traffic can also use Mt Rose Street to Plumas Street to Liberty Street.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Avenue, Center Street, Plumas Street, or Haskell Street; which include:
    • La Rue Avenue, Martin Street, Taylor Street, Cheney Street, St Lawrence Avenue, Thoma Street, California Street, Moran Street, and Stewart Street.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 15th Street to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
  • 15th Street to 8th Street: traffic is reduced to one-lane in each direction. Some on-street parking is closed.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 31 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 7/31/2020

Micro-Surfacing
Sierra Street: 11th Street to 3rd Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: 11th Street to 3rd Street
Prototype Drive: Gateway Drive to Double R Boulevard
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Sunday 8/2/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to End
Legends “I”: George Ferris Drive to Scheels Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to End
Legends “I”: George Ferris Drive to Scheels Drive

Monday 8/3/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
George Ferris Drive: Lincoln Way East Round-A-Bout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
George Ferris Drive: Lincoln Way East Round-A-Bout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Tuesday 8/4/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends Bay: Lincoln Way West Round-A-Bout to End

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends Bay: Lincoln Way West Round-A-Bout to End
Sierra Street: 11th Street to 3rd Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Wednesday 8/5/2020

Pavement Patching
Watson Way: Kresge Lane to Glendale Avenue

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: Westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to East End of Pavement
Watson Way: Kresge Lane to Glendale Avenue

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: Westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to East End of Pavement
Watson Way: Kresge Lane to Glendale Avenue
Sierra Street: 11th Street to 3rd Street

Thursday 8/6/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Kietzke Lane: South End Cul-De-Sac to Virginia Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: South End Cul-De-Sac to Virginia Street
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to End
Legends “I”: George Ferris Drive to Scheels Drive

Friday 8/7/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Kietzke Lane: South End Cul-De-Sac to Virginia Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: South End Cul-De-Sac to Virginia Street
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to End
Legends “I”: George Ferris Drive to Scheels Drive
George Ferris Drive: Lincoln Way East Round-A-Bout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between Spice Island Drive and railroad tracks during the hours of 7:00 AM to 6:00 PM.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/31 8/15

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.  Work is expected to be substantially complete by the end of September 2020.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Work includes construction of a new Bus RAPID Station on the east side of Virginia Street just south of Plumb Lane. Construction is scheduled to begin July 27, 2020, with substantial completion scheduled for the middle of October 2020.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

    • Intermittent shoulder closure at various intersections.
    • One lane closure, two-way traffic maintained. Expect delays.
    • Construction work on the east side of Sun Valley Boulevard. One lane closure from Quartz to Leon Dr.
    • 7th Ave intersection:
      • Intermittent lane closure with detours.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Center Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty Street: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center Street to Liberty Street.
    • Northbound traffic can also use Mt Rose Street to Plumas Street to Liberty Street.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Avenue, Center Street, Plumas Street, or Haskell Street; which include:
    • La Rue Avenue, Martin Street, Taylor Street, Cheney Street, St Lawrence Avenue, Thoma Street, California Street, Moran Street, and Stewart Street.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 15th Street to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
  • 15th Street to 8th Street: traffic is reduced to one-lane in each direction. Some on-street parking is closed.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

 

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 24, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Saturday 7/25

Micro-Surfacing
Kresge Lane: McCarran Boulevard to Watson Way
Bergin Way: Kresge Lane to end of pavement
Overmeyer Road: Bergin Way to Watson Way
Watson Way: Glendale Avenue to Dunn Circle

Monday 7/27

Micro-Surfacing
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Arrowcreek Parkway: Geyser Road to Thomas Creek Road
Kresge Lane: McCarran Boulevard to Watson Way
Bergin Way: Kresge Lane to end of pavement
Overmeyer Road: Bergin Way to Watson Way
Watson Way: Glendale Avenue to Dunn Circle
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge
Prototype Drive: Gateway Drive to Double R Boulevard
Second Street: Virginia Street to Giroux Street

Tuesday 7/28

Micro-Surfacing
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street

Wednesday 7/29

Micro-Surfacing
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Thursday 7/30

Micro-Surfacing
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Friday 7/31

Micro-Surfacing
Booth Street: California Avenue to Idlewild Drive
Third Street: Sierra Street to Vine Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Booth Street: California Avenue to Idlewild Drive
Third Street: Sierra Street to Vine Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between Spice Island Drive and railroad tracks during the hours of 7:00 AM to 6:00 PM.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/17 – 7/31

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.  Work is expected to be substantially complete by the end of September 2020.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Work includes construction of a new Bus RAPID Station on the east side of Virginia Street just south of Plumb Lane. Construction is scheduled to begin July 27, 2020, with substantial completion scheduled for the middle of October 2020.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction is in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

  • Intermittent shoulder closure at various intersections.
  • One lane closure, two-way traffic maintained.  Expect delays.
  • Construction work on the east side of Sun Valley Boulevard.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Center Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center Street to Liberty Street: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center Street to Liberty Street.
    • Northbound traffic can also use Mt Rose Street to Plumas Street to Liberty Street.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Avenue, Center Street, Plumas Street, or Haskell Street; which include:
    • La Rue Avenue, Martin Street, Taylor Street, Cheney Street, St Lawrence Avenue, Thoma Street, California Street, Moran Street, and Stewart Street.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • West Stadium Parking Garage to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 17, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 7/20/2020

Micro-Surfacing
Double R Boulevard: South Meadows Parkway to Longley Lane
Sinclair Street: Holcomb Avenue to Mill Street
Lake Street: Mill Street to Sixth Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Sinclair Street: Holcomb Avenue to Mill Street
Lake Street: Mill Street to Sixth Street
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Wedekind Road: Lund Lane to Malapi Way
Merchant Street: Sullivan Lane to Commerce Street
Howard Drive: Nichols Boulevard to Sparks Boulevard

Tuesday 7/21/2020

Micro-Surfacing
Double R Boulevard: South Meadows Parkway to Longley Lane
Commercial Row: Arlington Avenue to Lake Street
Fifth Street: West Street to Virginia Street

Traffic Signal Loop Replacement
Double R Boulevard: Amston Lane to Double Diamond Parkway

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Commercial Row: Arlington Avenue to Lake Street
Fifth Street: West Street to Virginia Street

Wednesday 7/22/2020

Micro-Surfacing
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge
Sinclair Street: Holcomb Avenue to Mill Street
Lake Street: Mill Street to Sixth Street

Thursday 7/23/2020

Micro-Surfacing
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street
Commercial Row: Arlington Avenue to Lake Street
Fifth Street: West Street to Virginia Street

Friday 7/24/2020

Micro-Surfacing
Prototype Drive: Gateway Drive to Double R Boulevard
Second Street: Virginia Street to Giroux Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge
Prototype Drive: Gateway Drive to Double R Boulevard
Second Street: Virginia Street to Giroux Street

 

GREG STREET REHABILITATION PROJECT
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Blvd and the railroad tracks. The reconstruction is expected to be completed by mid-August.

Starting on Monday, July 20th, traffic is reduced to one-lane in each direction between Spice Island Drive and railroad tracks during the hours of 7:00 AM to 6:00 PM

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/17 – 7/31

No work planned, waiting on NDOT project on I580.

 

LAKESIDE DRIVE REHABILITATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

 Construction is scheduled to start on Lakeside Drive between Evans Creek Drive and McCarran Blvd. on Monday, 7/20/20. This will be a roadway reconstruction, some curb/gutter and driveway replacements, and ADA pedestrian ramp improvements.   This is a 50 working day contract and should be substantially complete the end of September 2020.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

This will be the construction of a new Bus RAPID Station on the east side of Viginia Street just south of Plumb Lane. Construction is scheduled to start 7/27/20 and a 60 day working day contract with substantial completion scheduled for the first of October 2020.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Way between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb&Gutter, Sidewalk and Drainage improvements.

  • Intermittent shoulder closure and one lane closure, two way traffic maintained. Expect delays.
  • Middle Fork to Leon Dr – ROAD CLOSURE: 7/20 – 7/24
    • DETOUR:  Northbound traffic along Sun Valley Blvd will be detoured to take the right at Middle Fork, left at Smokey Canyon, left at Leon and finally right on Sun Valley Blvd to continue north.
    • DETOUR: Southbound traffic will take the right at Leon Dr, left at Middle Fork Dr, left at Amargosa, left at Middle Fork Dr and finally right at Sun Valley Blvd to continue south.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to CenterSt: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street is closed.
    • Detours are in place. Southbound detour is to Sierra St, northbound detour is to Center St.
  • West Stadium Parking Garage to Serra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Searra St and 15th St.
  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 9, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 7/13/2020

Micro-Surfacing
Howard Drive: Nichols Boulevard to Sparks Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Merchant Street: Sullivan Lane to Commerce Street
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Nugget Avenue: McCarran Boulevard to End of Pavement
Nugget Court: Nugget Avenue to Cul-de-Sac
15th Street: Victorian Avenue to C Street
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Watson Way: Glendale Avenue to Dunn Circle
Bergin Way: Kresge Lane to End of Pavement
Overmeyer Road: Bergin Way to Watson Way
Kresge Lane: McCarran Boulevard to Watson Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Richard Springs Boulevard: Shelby Drive to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Tuesday 7/14/2020

Micro-Surfacing
Howard Drive: Nichols Boulevard to Sparks Boulevard
Springland Drive: Sparks Boulevard to Baring Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Merchant Street: Sullivan Lane to Commerce Street
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Nugget Avenue: McCarran Boulevard to End of Pavement
Nugget Court: Nugget Avenue to Cul-de-Sac
15th Street: Victorian Avenue to C Street
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Watson Way: Glendale Avenue to Dunn Circle
Bergin Way: Kresge Lane to End of Pavement
Overmeyer Road: Bergin Way to Watson Way
Kresge Lane: McCarran Boulevard to Watson Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Howard Drive: Nichols Boulevard to Sparks Boulevard
Springland Drive: Sparks Boulevard to Baring Boulevard
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Wednesday 7/15/2020

Micro-Surfacing
Wedekind Road: Lund Lane to Malapi Way
Merchant Street: Sullivan Lane to Commerce Street
Greenbrae Drive: Orovada Street El Rancho Boulevard
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Traffic Signal Loop Replacement
El Rancho Drive: Wedekind Road to McCarran Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Merchant Street: Sullivan Lane to Commerce Street
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Nugget Avenue: McCarran Boulevard to End of Pavement
Nugget Court: Nugget Avenue to Cul-de-Sac
15th Street: Victorian Avenue to C Street
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Watson Way: Glendale Avenue to Dunn Circle
Bergin Way: Kresge Lane to End of Pavement
Overmeyer Road: Bergin Way to Watson Way
Kresge Lane: McCarran Boulevard to Watson Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Wedekind Road: Lund Lane to Malapi Way
Merchant Street: Sullivan Lane to Commerce Street
Greenbrae Drive: Orovada Street El Rancho Boulevard

Thursday 7/16/2020

Micro-Surfacing
El Rancho Drive: Wedekind Road to McCarran Boulevard
Orovada Street: Silverada Boulevard to Greenbrae Drive
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
El Rancho Drive: Wedekind Road to McCarran Boulevard
Orovada Street: Silverada Boulevard to Greenbrae Drive
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Howard Drive: Nichols Boulevard to Sparks Boulevard
Springland Drive: Sparks Boulevard to Baring Boulevard

Friday 7/17/2020

Micro-Surfacing
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Eastlake Boulevard: Coyote Drive to Duck Hill Road
Wedekind Road: Lund Lane to Malapi Way
Merchant Street: Sullivan Lane to Commerce Street
Greenbrae Drive: Orovada Street El Rancho Boulevard
Howard Drive: Nichols Boulevard to Sparks Boulevard

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/9 – 7/15

No work planned, waiting on NDOT project on I580.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Wy between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

GREG STREET REHABILITATION PROJECT
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction to begin on Greg Street between McCarran Blvd and the railroad tracks beginning Sunday night July 12th. The reconstruction is expected to take five (5) weeks to complete.

During the nighttime hours of 7:00 PM to 5:00 AM, traffic is reduced to one-lane in each direction between McCarran Boulevard and Spice Island Drive.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
Crews currently working along the west side of Sun Valley Blvd (southbound).

  • Quartz to Leon:
    • one lane closure, two way traffic maintained. Expect delays.
  • Leon to Highland Ranch Pkwy:
    • one lane closure, two way traffic maintained. Expect delays.
  • Highland Ranch Pkwy:
    • shoulder closure. Signal timing reset. Expect delays.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to CenterSt: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street is closed.
    • Detours are in place. Southbound detour is to Sierra St, northbound detour is to Center St.
  • West Stadium Parking Garage to Serra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Searra St and 15th St.
  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 2, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 7/6/2020

Micro-Surfacing
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Tuesday 7/7/2020

Micro-Surfacing
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Wednesday 7/8/2020

Micro-Surfacing
West Calle De La Plata: Isidor Court to Eagle Canyon Drive
Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Thursday 7/9/2020

Micro-Surfacing
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
West Calle De La Plata: Isidor Court to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Friday 7/10/2020

Micro-Surfacing
Richard Springs Boulevard: Shelby Drive to Eagle Canyon Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Richard Springs Boulevard: Shelby Drive to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/6 – 7/15

No work planned, waiting on NDOT project on I580.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Wy between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
Crews currently working along the west side of Sun Valley Blvd (southbound).

  • Quartz to Leon:
    • one lane closure, two way traffic maintained. Expect delays.
  • Leon to Highland Ranch Pkwy:
    • one lane closure, two way traffic maintained. Expect delays.
  • Highland Ranch Pkwy:
    • shoulder closure. Signal timing reset. Expect delays.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

The project is substantially complete.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to CenterSt: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thomas St, California St, Moran St, and Stewart St.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between Center St and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

June 26, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 6/29
Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Greg Street: Rock Boulevard to McCarran Boulevard
East Greg Street: Stanford Way to Sparks Boulevard

Tuesday 6/30
Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Virginia Street to California Avenue

Wednesday 7/1
Micro-Surfacing
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street

Thursday 7/2
Micro-Surfacing
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Fifth Street: West Street to Virginia Street
Overmeyer Road: Bergin Way to Watson Way
Bergin Way: Kresge Lane to End of Pavement
Watson Way: Glendale Avenue to Dunn Circle
Kresge Lane: McCarran Boulevard to Watson Way

Friday 7/3
NO WORK SCHEDULED

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/22 – 7/10
No work planned, waiting on NDOT project on I580.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Wy between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress.  Crews currently working along the west side of Sun Valley Blvd.

  • 7th Ave and Middle Fork: one lane closure, two way traffic maintained. Expect delays.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

The project is substantially complete.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Vassar St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.  Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 8th St: traffic is reduced to one-lane in each direction.
  • 8th St: northern shoulder is closed between Center St and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

June 22, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Sunday 6/21/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: I-80 Overpass to Brierley Way
George Ferris Drive: Lincoln Way Round-A-Bout to Legends Bay
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends Way: Scheels Drive to George Ferris Drive
Legends Bay: Lincoln Way Round-A-Bout to End of Pavement

Monday 6/22/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: Neil Kietzke Round-A-Bout to Virginia Street
Battle Born Way: Galletti Way to Victorian Avenue
2nd Street: Virginia Street to Girioux Street
Lake Street: Mill Street to Sixth Street

Tuesday 6/23/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street

Wednesday 6/24/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Court Street: Arlington Avenue to Virginia Street
Commercial Row: Arlington Avenue to Lake Street

Thursday 6/25/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Lake Street: Mill Street to Sixth Street
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Sierra Street: Eleventh Street to California Avenue

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/15 – 7/1
No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/15 – 6/22
Q&D has remaining concrete work at Mill and Kirman and Keystone at 7th.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Vassar Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar Street to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: is reduced to one-lane in each direction
  • 8th Street: northern shoulder is closed between Center Street and North Virginia Street

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress.  Crews currently working along the west side of Sun Valley Blvd.

  • 7th Ave and Middle Fork: one lane closure, two way traffic maintained. Expect delays.

 

 

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

June 11, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Saturday 6/13/2020

Pavement Patching
Golden Valley Road: Marlin Drive to Opal Station Drive
Seventh Avenue: Golden Valley Drive to Sun Valley Boulevard

Monday 6/15/2020

Pavement Patching
Sierra Street: Virginia Street to California Avenue
2nd Street: Virginia Street to Girioux Street
Kietzke Lane: Neil Kietzke Round-A-Bout to Virginia Street

Pavement Crack Sealing
Golden Valley Road: Marlin Drive to Opal Station Drive
Seventh Avenue: Golden Valley Drive to Sun Valley Boulevard
Tanberg Drive: Seventh Avenue to Mineral Avenue

Tuesday 6/16/2020

Pavement Crack Sealing
Golden Valley Road: Marlin Drive to Opal Station Drive
Seventh Avenue: Golden Valley Drive to Sun Valley Boulevard
Tanberg Drive: Seventh Avenue to Mineral Avenue
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Sierra Highlands Drive: Idelbury Drive to Seventh Street

Wednesday 6/17/2020

Pavement Crack Sealing
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Sierra Highlands Drive: Idelbury Drive to Seventh Street
Springland Drive: Sparks Boulevard to Baring Boulevard
Howard Drive: Prater Way to Sparks Boulevard

Thursday 6/18/2020

Pavement Patching (NIGHT WORK: 5:00 PM to 6:00 AM)
Marina Gateway: Lincoln Way to Prater Way
Greg Street: Rock Boulevard to McCarran Boulevard
East Greg Street: Stanford Way to Sparks Boulevard
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: I-80 Overpass to Brierley Way
George Ferris Drive: Lincoln Way Round-A-Bout to Legends Bay
East Lincoln Way: Sparks Boulevard to McCarran Boulevard

Pavement Crack Sealing
Springland Drive: Sparks Boulevard to Baring Boulevard
Howard Drive: Prater Way to Sparks Boulevard
El Rancho Drive: Wedekind Road to McCarran Boulevard
Wedekind Road: Sullivan Lane to McCarran Boulevard

Friday 6/19/2020

Pavement Crack Sealing
El Rancho Drive: Wedekind Road to McCarran Boulevard
Wedekind Road: Sullivan Lane to McCarran Boulevard
Greenbrae Drive: Orovada Street to El Rancho Boulevard
Merchant Street: Sullivan Lane to Commerce Street
Orovada Street: Greenbrae Drive to Sparks City Limits

 

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/15 – 7/1
No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/15 – 6/22
Q&D has remaining concrete work at Mill and Kirman and Keystone at 7th.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Vassar Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar Street to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: is reduced to one-lane in each direction
  • 8th Street: northern shoulder is closed

For the most up to date information on traffic control, please visit the Virginia Street Website

 

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

June 4, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 6/8/2020

Pavement Patching
Pembroke Drive: Piping Rock Drive to E. Parkway Drive
Greg Street: Rock Boulevard to McCarran Boulevard
Overmeyer Road: Bergin Way to Watson Way
Bergin Way: Kresge Lane to End of Pavement
Watson Way: Glendale Avenue to Dunn Circle

Pavement Crack Sealing
West Calle De La Plata: Pyramid Highway to Eagle Canyon Drive

Tuesday 6/9/2020

Pavement Patching
Springland Drive: Sparks Boulevard to Baring Boulevard
Greenbrae Drive: Orovada Street to El Rancho Boulevard

Pavement Crack Sealing
West Calle De La Plata: Pyramid Highway to Eagle Canyon Drive
Richard Springs Boulevard: Eagle Canyon Drive to Shelby Drive

Wednesday 6/10/2020

Pavement Patching
Greenbrae Drive: Orovada Street to El Rancho Boulevard
Orovada Street: Greenbrae Drive to Sparks City Limits
El Rancho Drive: Wedekind Road to McCarran Boulevard

Pavement Crack Sealing
Richard Springs Boulevard: Eagle Canyon Drive to Shelby Drive
Wingfield Hills Road: Vista Boulevard to Rolling Meadows Drive

Thursday 6/11/2020

Pavement Patching
El Rancho Drive: Wedekind Road to McCarran Boulevard
Wedekind Road: Sullivan Lane to McCarran Boulevard

Pavement Crack Sealing
Wingfield Hills Road: Vista Boulevard to Rolling Meadows Drive
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Friday 6/12/2020

Pavement Patching
Wingfield Hills Road: Vista Boulevard to Rolling Meadows Drive
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Pavement Crack Sealing
Seventh Street:
El Rancho Drive: Wedekind Road to McCarran Boulevard
Wedekind Road: Sullivan Lane to McCarran Boulevard

 

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/15 – 5/22

No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/22 – 6/8

No work planned. Q&D has remaining concrete work at Mill and Kirman scheduled for 6/8/20.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Vassar Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar Street to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

May 29, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 5/29/2020
Pavement Patching
Double R Boulevard: Prototype Drive to South Meadows Parkway
Prototype Drive: Gateway Drive to Double R Boulevard
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

Saturday 5/30/2020
NO WORK SCHEDULED

Sunday 5/31/2020
NO WORK SCHEDULED

Monday 6/1/2020
Pavement Patching
Sierra Highlands Drive: Idelbury Drive to Seventh Street
Double R Boulevard: South Meadows Parkway to Longley Lane
Kietzke Lane: Neil Kietzke Round-A-Bout to Virginia Street

Pavement Crack Sealing
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Tuesday 6/2/2020
Pavement Patching
Sierra Highlands Drive: Idelbury Drive to Seventh Street
Plumas Street: Ridgeview Drive to Plumb Lane
Lakeside Drive: Moana Lane to Brinkby Avenue

Pavement Crack Sealing
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Wednesday 6/3/2020
Pavement Patching
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Commercial Row: Arlington Avenue to Lake Street
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Sierra Street: Virginia Street to California Avenue

Pavement Crack Sealing
Arrow Creek Parkway: Thomas Creek to Geyser Road

Thursday 6/4/2020
Pavement Patching
Mill Street: Lake Street to Terminal Way
15th Street: Victorian Avenue to C Street
Merchant Street: Sullivan Lane to Commerce Street
Washington Street: Second Street to Fourth Street
Keystone Avenue: California Avenue to Seventh Street
Idlewild Drive: Riviera Street to Booth Street

Pavement Crack Sealing
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

Friday 6/5/2020
Pavement Patching
Richard Springs Boulevard: Eagle Canyon Drive to Shelby Drive
West Calle De La Plata: Pyramid Highway to Eagle Canyon Drive
Keystone Avenue: California Avenue to Seventh Street
2nd Street: Virginia Street to Girioux Street

Pavement Crack Sealing
Double R Boulevard: South Meadows Parkway to Longley Lane
Kietzke Lane: Neil Kietzke Round-A-Bout to Virginia Street

 

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/22 – 6/8

No work planned. Q&D has remaining concrete work at Mill and Kirman scheduled for 6/8/20.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Project Completed

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

 

South Virginia Street:

  • Plumb Ln to Vassar Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar Street to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St. Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

May 22, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 5/25/2020
MEMORIAL DAY – NO WORK SCHEDULED

Tuesday 5/26/2020
Pavement Patching
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Wednesday 5/27/2020
Pavement Patching
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Thursday 5/28/2020
Pavement Patching
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Friday 5/29/2020
Pavement Patching
Arrowcreek Parkway: Geyser Road to Thomas Creek Road
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

 

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/22 – 6/8

No work planned. Q&D has remaining concrete work at Mill and Kirman scheduled for 6/8/20.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

5/18 – 5/22

Traffic signal at Red Rock/Silver Lake fully open. Construction completed.

Road construction is completed for McCarran portion of the project. Minor striping works returns the week of May 18th. Project to be fully completed by the 22nd. Expect closure of the new westbound lane for striping work.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

 

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

May 14, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/15- 5/22
No work planned, waiting on NDOT project on I580.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 5/1

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 20 – May 1: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/15 – 5/22

No work planned.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

5/11 – 5/22

Traffic signal at Red Rock/Silver Lake is now operational. WBL movement from Westbound Silver Lake to Southbound Red Rock is active.Traffic signal construction is complete. Road construction is completed for McCarran portion of the project. Minor striping works returns the week of May 18th. Project to be fully completed by the 22nd. Expect closure of the new westbound lane for striping work.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

 

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

May 7, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/27– 5/15
No work planned, waiting on NDOT project on I580.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 5/1

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 20 – May 1: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/4 – 5/18

Lane closures at Keystone at 7th for signal equipment installation

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

5/4 – 5/10

Traffic signal at Red Rock/Silver Lake is now operational. Work resumes on 5/7 for slurry and striping work at the intersection. Lane reduction down to one lane is expected. WBL movement from Westbound Silver Lake to Southbound Red Rock will be active.

Construction begins 5/4 for the McCarran portion of the project. Left lane closures on WB/EB N. McCarran at Clear Acre Ln to Northtowne Ln. Northbound US 395 on-ramp from N. McCarran is closed. Detour to NB US 395 at Clear Acre Ln.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

 

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Center St/Mary St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Center St/Mary St to Liberty St: traffic is detoured.
    • Southbound traffic is detoured to Liberty St. to Sinclair St to Holcombonb Avenue.
    • Northbound traffic is detoured to Holcomb Ave to Center St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

    • Roundabout work in this area requires closure of Mary St at Virginia St.
    • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

April 30, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/27– 5/15
No work planned, waiting on NDOT project on I580.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 5/1
The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.
Drivers can expect detours during the construction process, for everyone’s safety:
– April 20 – May 1: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/4 – 5/18
Lane closures at McCarran at Neil and Keystone at 7th for signal equipment installation

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

4/23
Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Center St/Mary St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Center St/Mary St to Liberty St: traffic is detoured.
    • Southbound traffic is detoured to Liberty St. to Sinclair St to Holcombonb Avenue.
    • Northbound traffic is detoured to Holcomb Ave to Center St. Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St. Center Street/Mary Street at Virginia Street:
  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

April 23, 2020

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

 

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/27– 5/15

No work planned waiting on NDOT project on I580.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 5/1

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 20 – May 1: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

 

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/27-5/1

Lane closures at McCarran at Neil and Keystone at 7th for signal equipment installation

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Center St/Mary St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Center St/Mary St to Liberty St: traffic is detoured.
    • Southbound traffic is detoured to Liberty St. to Sinclair St to Holcombonb Avenue.
    • Northbound traffic is detoured to Holcomb Ave to Center St. Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

 

For the most up to date information on traffic control, please visit the Virginia Street Website.  

April 17, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/20– 4/27

No Work planned

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/13 – 4/28

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 13 – April 28: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/20-4/30

Lane closures at Evans and Enterprise then McCarran at Neil for signal equipment installation

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Center St/Mary St: traffic is reduced to southbound direction only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Center St/Mary St to Liberty St: traffic is detoured.
    • Southbound traffic is detoured to Liberty St. to Sinclair St to Holcombonb Avenue.
    • Northbound traffic is detoured to Holcomb Ave to Center St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website.  

April 10, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  • East 9th Street and Montello Street Intersection
  • Valley Road and Sadleir Way Intersection
  • Sutro Street and Haddock Drive Intersection
  • Lemmon Drive and North Virginia Street Intersection
  • Kirman Avenue and Moran Street Intersection
  • Mill Street and Sunshine Lane Intersection
  • Locust Street and Colorado River Boulevard Intersection
  • Grove Street and Yori Way Intersection
  • Hunter Lake Drive and Foster Drive Intersection
  • Sierra Center Parkway at Sierra Town Center
  • York Way and 4th Street Intersection
  • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/13 – 4/16

Patching on Baring and Sparks Blvd. Single lane closures during paving operations.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/13 – 4/28

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 13 – April 28: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/13-4/20                      

No work until 4/16

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
    • Northbound traffic is detoured via side streets to Center St to Liberty St.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website.  

April 3, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  • East 9th Street and Montello Street Intersection
  • Valley Road and Sadleir Way Intersection
  • Sutro Street and Haddock Drive Intersection
  • Lemmon Drive and North Virginia Street Intersection
  • Kirman Avenue and Moran Street Intersection
  • Mill Street and Sunshine Lane Intersection
  • Locust Street and Colorado River Boulevard Intersection
  • Grove Street and Yori Way Intersection
  • Hunter Lake Drive and Foster Drive Intersection
  • Sierra Center Parkway at Sierra Town Center
  • York Way and 4th Street Intersection
  • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work at this time

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about five weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/6-4/20
Signal pole installation will begin at Mill/Kirman.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
    • Northbound traffic is detoured via side streets to Center St to Liberty St.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website.  

March 27, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  1. East 9th Street and Montello Street Intersection
  2. Valley Road and Sadleir Way Intersection
  3. Sutro Street and Haddock Drive Intersection
  4. Lemmon Drive and North Virginia Street Intersection
  5. Kirman Avenue and Moran Street Intersection
  6. Mill Street and Sunshine Lane Intersection
  7. Locust Street and Colorado River Boulevard Intersection
  8. Grove Street and Yori Way Intersection
  9. Hunter Lake Drive and Foster Drive Intersection
  10. Sierra Center Parkway at Sierra Town Center
  11. York Way and 4th Street Intersection
  12. Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work at this time

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about five weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work at this time.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

3/26 – 3/27
Expect temporary lane closure at the intersection of Red Rock and Silver Lake. Traffic signal to be turned on next Friday.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
    • Traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

 

For the most up to date information on traffic control, please visit the Virginia Street Website.  

March 20, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  1. East 9th Street and Montello Street Intersection
  2. Valley Road and Sadleir Way Intersection
  3. Sutro Street and Haddock Drive Intersection
  4. Lemmon Drive and North Virginia Street Intersection
  5. Kirman Avenue and Moran Street Intersection
  6. Mill Street and Sunshine Lane Intersection
  7. Locust Street and Colorado River Boulevard Intersection
  8. Grove Street and Yori Way Intersection
  9. Hunter Lake Drive and Foster Drive Intersection
  10. Sierra Center Parkway at Sierra Town Center
  11. York Way and 4th Street Intersection
  12. Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/16 – 3/27
Shoulder closures at I-580 southbound on-ramp at Damonte Ranch Pkwy, I80 ramps at McCarran and Robb Dr.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about five weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/9 – 3/20
Underground construction begins at Prater at I80.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

3/26 – 3/27
Expect temporary lane closure at the intersection of Red Rock and Silver Lake. Traffic signal to be turned on next Friday.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
    • Traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thomas St, California St, Moran St, and Stewart St. Center Street and Mary Street at Virginia Street:
  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

March 12, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:
1. East 9th Street and Montello Street Intersection
2. Valley Road and Sadleir Way Intersection
3. Sutro Street and Haddock Drive Intersection
4. Lemmon Drive and North Virginia Street Intersection
5. Kirman Avenue and Moran Street Intersection
6. Mill Street and Sunshine Lane Intersection
7. Locust Street and Colorado River Boulevard Intersection
8. Grove Street and Yori Way Intersection
9. Hunter Lake Drive and Foster Drive Intersection
10. Sierra Center Parkway at Sierra Town Center
11. York Way and 4th Street Intersection
12. Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/9 – 3/13
Short term shoulder closures at: Baring Blvd. and McCarran Blvd.; Sparks Blvd. at Disc Dr.; Vista Blvd. at Disc Dr.; Baring Blvd. at N. Truckee Ln.; Sparks Blvd at Shadow Ln.

3/16 – 3/27
Shoulder closures at I-580 southbound on-ramp at Damonte Ranch Pkwy, I80 ramps at McCarran and Robb Dr.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about 5 weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/9 – 3/20
Underground construction will begin at McCarran Blvd and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Mt Rose St/Holcomb Ave: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area will require closure of either Center St or Mary St at Virginia St. While construction work is occurring on the west side of the roundabout, both Center St and Mary St are closed at Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

March 6, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/2 – 4/3
Construction to improve the accessibility and connectivity of RTC’s bus stops begins on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

    • East 9th Street and Montello Street Intersection
    • Valley Road and Sadleir Way Intersection
    • Sutro Street and Haddock Drive Intersection
    • Lemmon Drive and North Virginia Street Intersection
    • Kirman Avenue and Moran Street Intersection
    • Mill Street and Sunshine Lane Intersection
    • Locust Street and Colorado River Boulevard Intersection
    • Grove Street and Yori Way Intersection
    • Hunter Lake Drive and Foster Drive Intersection
    • Sierra Center Parkway at Sierra Town Center
    • York Way and 4th Street Intersection
    • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/2 – 3/13
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and I-580 southbound on-ramp at Damonte Ranch Pkwy.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/2 – 3/6
Underground construction will begin at 7th St and Keystone Ave. Occasional lane and shoulder closures expected.

3/9 – 3/20
Underground construction will begin at McCarran Blvd and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Mt Rose St/Holcomb Ave: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.
Center Street and Mary Street at Virginia Street:
  • Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St. Mary St and Center St remain open to traffic away from Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

February 28, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/2 – 4/3
Construction to improve the accessibility and connectivity of RTC’s bus stops begins on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

    • East 9th Street and Montello Street Intersection
    • Valley Road and Sadleir Way Intersection
    • Sutro Street and Haddock Drive Intersection
    • Lemmon Drive and North Virginia Street Intersection
    • Kirman Avenue and Moran Street Intersection
    • Mill Street and Sunshine Lane Intersection
    • Locust Street and Colorado River Boulevard Intersection
    • Grove Street and Yori Way Intersection
    • Hunter Lake Drive and Foster Drive Intersection
    • Sierra Center Parkway at Sierra Town Center
    • York Way and 4th Street Intersection
    • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/2 – 3/13
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and I-580 southbound on-ramp at Damonte Ranch Pkwy.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/2 – 3/6
Underground construction will begin at 7th St and Keystone Ave. Occasional lane and shoulder closures expected.

3/2 – 3/20
Underground construction will begin at McCarran Blvd and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
  • Plumb Ln to Vassar St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Vassar St: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.
Center Street and Mary Street at Virginia Street:
  • Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St. Mary St and Center St remain open to traffic away from Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

February 20, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/18 – 2/28
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and I580 southbound on-ramp at Damonte.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/19 – 2/21
Underground construction will begin at 7th St. and Keystone Ave. Occasional lane and shoulder closures expected.

2/24 – 3/6
Underground construction will begin at McCarran Blvd. and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Pueblo St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Pueblo St: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St. Center Street and Mary Street at Virginia Street:
  • Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St. Mary St and Center St remain open to traffic away from Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

February 14, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/14 – 2/28
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and I580 southbound on-ramp at Damonte.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/4 – 2/14
Underground construction continues at Mill St and Kirman Ave. Occasional lane and shoulder closures expected.

2/17 – 2/21
Underground construction will begin at 7th St. and Keystone Ave.. Occasional lane and shoulder closures expected.

2/24 – 3/6
Underground construction will begin at McCarran Blvd. and Neil Rd. Occasional lane and shoulder closures expected.
TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
• Plumb Ln to Vassar St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
• Liberty St to Vassar St: traffic is reduced to southbound direction only.
• Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
• Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
o Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:
• Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St. Mary St and Center St remain open to traffic away from Virginia St.
• Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

February 7, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/30 – 2/14 
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and on Disc Dr from Sparks Blvd to Vista Blvd.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/4 – 2/21
Underground construction will begin at Mill St and Kirman Ave. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
  • Plumb Ln to Vassar St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Vassar St: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St. Two-way traffic is available north of Stewart St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.
Center Street and Mary Street at Virginia Street:
  • Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St.  Mary St and Center St remain open to traffic away from Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 31, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

No work currently scheduled.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Thursday 2/6
The Keystone on ramp from California Ave will be closed for fence repair.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/22 – 1/31
Shoulder and lane closures along Sparks Blvd from Baring Blvd to Disc Dr.

1/30 – 2/7
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr., Disc from Sparks to Vista and Vista from Disc to Los Altos.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Project complete.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/3 – 2/14
Underground construction will begin at Mill St and Kirman Ave. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Virginia Street:
    • Plumb Ln to Vassar St – two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
    • Vassar St to Stewart St – traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Plumas St to Liberty Street. Two-way traffic is available north of Stewart St.
    • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St. Center Street and Mary Street at Virginia Street:
    • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St.
    • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 24, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

No work currently scheduled.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Thursday 1/30
The Foster Drive on ramp from Booth St to Keystone Ave will be closed for pedestrian rail installation.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/22 – 1/31
Shoulder and lane closures along Sparks Blvd from Baring Blvd to Disc Dr.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Project complete.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/27 – 1/31
No work scheduled for this week.

2/3 – 2/14
Underground construction will begin at Mill St and Kirman Ave.  Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Vassar St to Stewart St – traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St.  Drivers can also use
  • Mt Rose Street to northbound Plumas St to Liberty Street.  Two-way traffic is available north of Stewart St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St.  During limited instances, both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 17, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 1/20
Pavement Crack Sealing
Locust Street: Casazza Drive to Ryland Street
Kirman Avenue: Ryland Street to Plumb Lane

Tuesday 1/21
Pavement Crack Sealing
Locust Street: Casazza Drive to Ryland Street
Kirman Avenue: Ryland Street to Plumb Lane

Wednesday 1/22
NO WORK SCHEDULED

Thursday 1/23/2020
NO WORK SCHEDULED

Friday 1/24
NO WORK SCHEDULED

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday 1/20
The Foster Drive on ramp from Booth to Keystone will be closed for pedestrian rail installation.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/13 – 1/21
Work will continue along Baring Blvd. Intermittent lane and shoulder closures should be expected. Pull boxes and a 55’ pole for a traffic camera will be installed at Baring Blvd and N Truckee Ln.

1/22 – 1/31
Shoulder and lane closures along Sparks Blvd from Baring Blvd to Disc Dr

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work activity currently scheduled. Traffic signal is in operation.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/7 – 1/24
Traffic signal construction at the intersection of Evans Ave and Enterprise Rd with shoulder and lane closures.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
• Vassar St to Stewart St – traffic is reduced to southbound direction only.
• Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Plumas St to Liberty Street. Two-way traffic is available north of Stewart St.
• Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
o Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:
• ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia Street. During limited instances, both streets may be closed at the same time.
• Detours will be in place.
For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 10, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 1/13/2020
Pavement Crack Sealing
Avenida De Landa: Sharlands Avenue to Robb Drive

Tuesday 1/14/2020
Pavement Crack Sealing
Avenida De Landa: Sharlands Avenue to Robb Drive

Wednesday 1/15/2020
Pavement Crack Sealing
Avenida De Landa: Sharlands Avenue to Robb Drive

Thursday 1/16/2020
NO WORK SCHEDULED

Friday 1/17/2020
NO WORK SCHEDULED

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday 1/20
The Foster Drive on ramp from Booth to Keystone will be closed for pedestrian rail installation.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/6 – 1/21
Work will continue along Baring Blvd.  Intermittent lane and shoulder closures should be expected.  Pull boxes and a 55’ pole for a traffic camera will be installed at Baring Blvd and N Truckee Ln.  

1/22 – 1/31
Shoulder and lane closures along Sparks Blvd from Baring Blvd to Disc Dr.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work currently scheduled.  Traffic signal is in operation.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/7 – 1/24
Construction will begin at the intersection of Evans Ave and Enterprise Rd with shoulder and lane closures.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Vassar St to Stewart St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St.  Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Stewart St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Caliente St, Vassar St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.