Weekly Traffic Control Report

October 13, 2017

REGIONAL TRANSPORTATION COMMISSION TRAFFIC CONTROL REPORT

October 13, 2017

9:00 AM PST

4TH STREET AND PRATER WAY BUS RAPID TRANSIT PROJECT

  • Construction is in progress. For current traffic information Click here.
  • Traffic control and work zones will be in place and changing frequently. Use caution and look for flaggers for direction. Expect traffic delays.


ANNUAL PAVEMENT PRESERVATION PROJECT

Various roads within the cities of Sparks, Reno and Washoe County. Traffic control will include isolated lane shifts and/or lane closures with possible flagger controls.

Friday 10/13
Raise Utilities
Lake St: Fourth St to Sixth St
Second St: Truckee River Bridge to Giroux St
Plumas St: McCarran Blvd to Plumb Ln
Moana Ln: Plumas St to Baker Ln

Pavement Striping (7:00 PM to 5:00 AM)
Plumb Ln: Sharon Wy to Ferris Dr
Lincoln Wy: Howard Dr to RV Park Entrance
Gateway Dr: South Meadows Pkwy to Offenhauser Dr
Offenhauser Dr: Gateway Dr to Portman Ave
Lake St: Fourth St to Sixth St
Second St: Truckee River Bridge to Giroux St
Caughlin Pkwy: McCarran Blvd to Sierra Crest Wy
Montello St: Ninth St to Oddie Blvd
Keystone Ave: California Ave to Coleman Dr
Village Blvd: Lakeshore Blvd to Eagle Dr
College Dr: Village Blvd to Mt Rose Hwy
Incline Wy: Country Club Dr to Southwood Blvd
Northwood Blvd: Tahoe Blvd (W) to Tahoe Blvd (E)
Southwood Blvd: Tahoe Blvd (W) to Tahoe Blvd (E)
Tanager St: Village Blvd to Southwood Blvd
McCourry Blvd: Northwood Blvd to Mt Rose Hwy
Mays Blvd: Southwood Blvd to Lakeshore Blvd
Lakeshore Blvd: Tahoe Blvd (W) to Tahoe Blvd (E)
Country Club Dr: Lakeshore Blvd to Mt Rose Hwy
Keystone Ave: California Ave to Seventh St
Terminal Wy: Plumb Ln to Mill St
Maestro Dr: Longley Ln to Double R Blvd
Third St: Sierra St to Vine St

Saturday 10/14
No Work Scheduled

Sunday 10/15
Pavement Striping (7:00 PM to 5:00 AM)
Various Program Streets: 2nd coat paint application
Various Program Streets: final thermoplastic application

Monday 10/16
Raise Utilities
Plumas St: McCarran Blvd to Plumb Ln
Moana Ln: Plumas St to Baker Ln

Traffic Loop Replacement
Keystone Ave: California Ave to Seventh St

Pavement Striping (7:00 PM to 5:00 AM)
Various Program Streets: 2nd coat paint application
Various Program Streets: final thermoplastic application

Tuesday 10/17
Raise Utilities
Plumas St: McCarran Blvd to Plumb Ln
Moana Ln: Plumas St to Baker Ln

Traffic Loop Replacement
Keystone Ave: California Ave to Seventh St

Pavement Striping (7:00 PM to 5:00 AM)
Various Program Streets: 2nd coat paint application
Various Program Streets: final thermoplastic application

Wednesday 10/18
Traffic Loop Replacement
Keystone Ave: California Ave to Seventh St
Second St: Truckee River Bridge to Giroux St

Pavement Striping (7:00 PM to 5:00 AM)
Various Program Streets: 2nd coat paint application
Various Program Streets: final thermoplastic application

Thursday 10/19
Traffic Loop Replacement
Keystone Ave: California Ave to Seventh St
Second St: Truckee River Bridge to Giroux St

Pavement Striping (7:00 PM to 5:00 AM)
Various Program Streets: 2nd coat paint application
Various Program Streets: final thermoplastic application

Friday 10/20
Traffic Loop Replacement
Second St: Truckee River Bridge to Giroux St

PYRAMID WAY AND MCCARRAN BLVD INTERSECTION PROJECT

  • Construction is in progress. For current traffic information Click here.
  • Traffic control and work zones will be in place and changing frequently. Use caution and look for flaggers for direction. Expect traffic delays.


SOUTHEAST CONNECTOR PROJECT

From Pembroke Dr to South Meadows Pkwy and Veterans Pkwy (4.5 miles)

  • Flaggers may be located at Mira Loma Dr and Pembroke Dr to control vehicular traffic. Flaggers will stop traffic for short durations to allow construction vehicles to cross Mira Loma Dr and Pembroke Dr.
  • Be aware and pay attention to the traffic control signs. Lane reductions are in place at the intersection of South Meadows Pkwy and Veterans Pkwy. Brief delays are expected.

 