Weekly Traffic Control Report

October 3, 2018

REGIONAL TRANSPORTATION COMMISSION TRAFFIC CONTROL REPORT

WEEKLY TRAFFIC CONTROL REPORT

October 3, 2018

3:00 PM PST

 

4TH STREET AND PRATER WAY BUS RAPID TRANSIT PROJECT
Construction is in progress.

  • Intermittent closures will occur throughout the project to facilitate project closeout.
  • Expect lane shifts and minor traffic delays.

For current traffic information Click here.

 

2018 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 10/1

Pavement Patching
Wells Avenue: Ninth Street to Sutro Street

Micro Surfacing
Cashill Boulevard: McCarran Boulevard to Skyline Boulevard

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Cashill Boulevard: McCarran Boulevard to Skyline Boulevard
Rio Wrangler Parkway: Western Skies Drive to Steamboat Parkway
Carat Avenue: Double Diamond Parkway to Steamboat Parkway

Tuesday 10/2

Micro Surfacing
Cashill Boulevard: McCarran Boulevard to Skyline Boulevard
Lupin Drive: 5th Avenue to 9th Avenue

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Cashill Boulevard: McCarran Boulevard to Skyline Boulevard
Lupin Drive: 5th Avenue to 9th Avenue
Rio Wrangler Parkway: Western Skies Drive to Steamboat Parkway
Carat Avenue: Double Diamond Parkway to Steamboat Parkway

Wednesday 10/3

Micro Surfacing
No Work Scheduled

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
No Work Scheduled

Thursday 10/4

Micro Surfacing
5th Street: Morrill Avenue to Valley Road
5th Street: Ferrari Street to Tacchino Street
8th Avenue: Sun Valley Boulevard to Lupin Drive
5th Avenue: Lupin Drive to Sun Valley Boulevard

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Cashill Boulevard: McCarran Boulevard to Skyline Boulevard
5th Street: Morrill Avenue to Valley Road
5th Street: Ferrari Street to Tacchino Street
8th Avenue: Sun Valley Boulevard to Lupin Drive
5th Avenue: Lupin Drive to Sun Valley Boulevard
Lupin Drive: 5th Avenue to 9th Avenue

Friday 10/5

Micro Surfacing
No Work Scheduled

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Cashill Boulevard: McCarran Boulevard to Skyline Boulevard
Lupin Drive: 5th Avenue to 9th Avenue

 

ITS PROJECT – PHASE 2A
Intermittent shoulder closures at the following locations:

• McCarran between Greg and Nugget – Sidewalk repairs and fiber installation 10/1/18-10/15/18.
• McCarran between Prater and Baring – Sidewalk repairs and fiber installation 10/1/18-10/15/18.

 

PYRAMID HWY & CALLE DE LA PLATA TRAFFIC SIGNAL

  • Work hours will be from 7:00am to 3:30pm.
  • Night Work to Resume Sunday 9/29 and Monday 10/1 from 8:00pm to 4:00am.
  • Lane closures and restrictions are taking place.

 

SOUTHEAST CONNECTOR PROJECT
From Greg St to South Meadows Pkwy and Veterans Pkwy (5.5 miles)

  • The Southeast connector is open to traffic.
  • The speed limit is 45 mph. Look for traffic signs and use caution as everyone becomes familiar with the new roadway, signalized intersections, and the multi-use path.
  • Intermittent shoulder closures and single lane closures in specific locations will occur over the next several weeks. Traffic control signs and personnel will be in place to direct traffic accordingly.

More information is available at the project website www.SouthEastConnector.com.

 

TRAFFIC ENGINEERING SPOT 7 – PACKAGE 2
Work will include the following locations:

9/24 – 10/15
• Prater Wy at Pullman Dr and Howard Dr – Lane closures

10/15 – 11/12
• Vista Blvd at Whitewood Dr and Prater Wy – Lane closures

11/19 – 11/25
• Virginia St at Grove St – Lane closures
• S Meadows Pkwy at Double R and both ramps at I 580 – Lane closures

11/20 – 11/24
• Mill St at Wells Ave – Lane closures

11/26 – 12/3
• Mill St at I 580 both ramps Longley Ln at Maestro Dr – Lane closures

12/3 – 12/8
• Mt Rose Hwy at Wedge Pkwy – Lane closures
• Pyramid Wy at Eagle Canyon Dr – Lane closures
• Pyramid Wy at Golden View Dr – Lane closures
• Sparks Blvd at Springland Dr/O’Callaghan Dr – Lane closures
• Victorian Ave at 11th St and 14th St – Lane closures

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
The Utility Phase of the Virginia Street Bus RAPID Transit Extension Project is underway

  • Traffic control is one-way southbound from Liberty St to Wells Ave.
  •  Northbound detour will start at Wells Ave and continue to Holcomb Ave and Center St.
  •  Side streets within the midtown area are open and provide effective access to businesses and residences.
  •  Watch for arrow boards and flaggers.

For more information visit Virginia Street Website.

 

 

 

See weekly traffic report archive