Weekly Traffic Control Report

October 28, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This project is substantially complete.

2022 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This project is substantially complete.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Beginning the week of September 26th Q&D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Q&D will also be patching roadway and small sections of sidewalk along Double R Boulevard from Sandhill Road to South Meadows Parkway. Lane and shoulder closures will be in place for this work.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction crews will work on Saturdays through the end of November 2022.
  • Underground work will include lighting conduits, planter and install irrigation, form and pour sidewalk concrete and install privacy wall (post and panels).
  • Traffic swap (to new pavement) north side of Oddie Boulevard
  • One lane in each direction will be maintained along Oddie Boulevard.
  • Milling and paving operations to start by mid-November:
    • Detours – Half intersection closures at Rock Boulevard and 12th Street

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.

Roadway pavement operations will begin on October 17th and end on October 28th. Peckham Lane, between S. Virginia Street and Baker Lane, will be closed. Business access to the Atlantis and Old Town Mall will be via S. Virginia Street. The intersection of Peckham Lane and Baker Lane will be intermittently closed.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

The free right turn lane from southbound Sparks Boulevard to westbound Greg Street is closed for the curing of concrete pavement. Trucks will be restricted from making this right turn movement and will be detoured to Greg Street via Vista Boulevard.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Lane, shoulder closures and detours will occur at various times throughout the project. Currently, work includes relocation of overhead utilities to underground. That work will continue through the end of October. Please observe all traffic control, work zone speed limits and flaggers. The construction of the roundabout will begin in the Spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022. Lane and shoulder closures will be in place during work hours.

See weekly traffic report archive