Weekly Traffic Control Report

October 16 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 10/19/2020

 NO WORK SCHEDULED

Tuesday 10/20/2020

Utility Adjustments
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Booth Street: California Avenue to Riverside Drive

Wednesday 10/21/2020

Utility Adjustments
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Booth Street: California Avenue to Riverside Drive

Thursday 10/22/2020

Utility Adjustments
Plumas Street: Ridgeview Drive to Plumb Lane
Sinclair Street: Holcomb Avenue to Mill Street

Friday 10/23/2020

Utility Adjustments
Sierra Street: Eleventh Street to California Avenue

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

10/1 – 10/19: no work planned, waiting on NDOT project on I-580.

 

KUENZLI STREET PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is in progress and expected to be completed by 10/23.

Giroux Street from E 2nd Street to Kuenzli:
Expect lane closures for pavement slurry sealing and striping this week.

Kuenzli Street from Giroux Street to Kirman Avenue:
Expect lane closures for pavement slurry sealing and striping this week.

Kuenzli Street/Locust Street:
Expect lane closures for pavement slurry sealing and striping this week.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is substantially complete. Minor traffic control between Evan Creek Drive and McCarran Boulevard for punch list items to be done.

Please use caution in construction zones for the safety of the public and the construction workers.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on the RAPID Station on Virginia Street eastside just south of Plumb Lane. Traffic controls are in place along northbound Virginia Street with lane shifts.

Please use caution in construction zones for the safety of the public and the construction workers.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.
Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard

  • 9/28 – 10/23:
    • Southbound traffic closed between 7th Avenue and Highland Ranch Parkway
    • Detour (southbound):

 

      • Highland Ranch Parkway to Midninght Drive to Lightning Drive to Magenta Drive to 7th Avenue
    • Intermittent closures (no access) at intersections:
      • Arapaho Drive
      • Leon Drive
      • Middle Fork Drive
      • Sidehill Drive
      • Quartz Lane
      • 8th Avenue
      • Mineral Avenue
      • Staci Way
  • Highland Ranch Parkway Intersection
    • Intermittent closures, but open during peak commute periods.
    • Detour:
      • To Debussey Drive/Donatello Drive

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street within this open to traffic with isolated and intermeidan shoulder and/or lane closures. Look for detour signage as appropriate.
  • 8th Street to 9th Street: North Virginia Street within this segment is closed to southbound traffic. Southbound is detoured at 9th to Sierra Street. Look for detour signage as appropriate.
  • 9th Street to 15th Street: traffic is one-lane in each direction. Some on-street parking is closed.
  • 15th Street to Sierra Street/Comstock Drive Intersection: traffic is reduced to one-way northbound direction only. Southbound traffic in this area is detoured at Sierra Street and utilizes 15th Street back to North Virginia Street. This closure is anticipated to be in place until the project is completed this fall.
  • 8th Street and 9th Street at North Virginia Street: Look for construction signage as appropriate or isolated lane or shoulder closures.

South Virginia Street:

  • Plumb Lane to Liberty Street: two-way traffic with isolated shoulder and street parking closures to work on final punch list work.