INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139
Beginning the week of September 26, 2022, Q&D will begin patching roadway and sidewalk at the following locations:
- Sharlands Avenue from Robb Drive to Mae Anne Avenue.
- Double R Boulevard from Sandhill Road to South Meadows Parkway.
- Lane and shoulder closures will be in place for this work.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- Construction crews will be working on Saturdays through the end of November 2022.
- Underground work includes lighting conduits, planter and irrigation installation, form and pour sidewalk concrete and privacy wall installation (post and panels).
- Traffic changeover to new pavement, north side of Oddie Boulevard.
- One traffic lane in each direction will be maintained along Oddie Boulevard.
- Milling and paving operations to start by mid-November:
- Detours – half intersection closures at Rock Boulevard and 12th Street.
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139
Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane will continue through November 2022. Detours will be in place around the vicinity of the project.
SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
Lane and shoulder closures will be in place.
SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881
Granite Construction Company is working in both the southbound and northbound lanes as well as the median along Sparks Boulevard between Lincoln Way and Greg Street. Daytime single-lane closures will be in place in the northbound direction between Greg Street and the I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.
Drivers should expect delays during the morning commute, look for signs and traffic control devices; please drive with caution.
TE SPOT 10 – SOUTH PROJECT
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865
Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Traffic lane shoulder closures and detours will occur at various times throughout the project. Currently, work includes relocation of overhead utilities to underground. Utility work requiring some traffic control will be occurring during the week. Please observe all traffic control, work zone speed limits and flaggers. The construction of the roundabout will begin in the Spring of 2023.
TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139
Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.