2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874
Friday 11/19
Utility Adjustment
Moana Lane: Plumas Street to Neil Road
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Saturday 11/20
No Work
Sunday 11/21
No Work
Monday 11/22
Utility Adjustment
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road
Tuesday 11/23
Utility Adjustment
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road
TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897
Construction continues at the following locations:
- Victorian Avenue & 16th Street
- Veterans Parkway & Long Meadow Drive
Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 a.m. to 3:00 p.m. Monday through Friday.
ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871
Construction of underground infrastructure is complete. New fiber optic cable will be installed through the month of November at the following locations:
- Lake Street from First Street to Second Street.
TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139
Construction will be postponed until next spring for pavement slurry seal. The intersection is open for normal operations.
New roadway configuration in place, please use caution driving through the intersection.
KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872
Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.
- Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
- On-street parking is closed during daytime working hours on Kings Row (7:00 a.m. to 5:00 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
Q&D continues work on the new retaining wall near Walgreens.
- Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
- Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months. Please use Sky Vista Parkway to access Walgreens.
This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.
- Business access will be maintained. For additional information on construction status, visit the Porject website at http://northvalleysimprovements.com/lemmon-drive/.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1: Pyramid Way to Sullivan Lane (Sparks):
Construction begins on Monday November 29, 2021.
- Drivers may see shoulder and lane closures on Oddie Boulevard during daytime working hours.
- NV Energy crews will be removing existing facilities
This week drivers can expect to see crews setting up traffic control to prepare for underground and trenching work on the shoulder.
One lane on each direction along Oddie Boulevard will be maintained. For additional information on construction status, visit the Porject website at http://Oddiewellsproject.com