Weekly Traffic Control Report

May 26, 2023

2023 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday 5/29/2023
Pavement Crack Sealing 7pm – 7am
Ampere Drive: Rock Boulevard to Edison Way
Edison Way:   Rock Boulevard to Edison Way
Corporate Boulevard:   Capital Boulevard to Mill Street
Financial Boulevard:   Capital Boulevard to Mill Street
Energy Way:   Rock Boulevard to Edison Way
Brookside Court:   Rock Boulevard to end of cul-de-sac
Joule Street:   Rock Boulevard to Edison Way
Reactor Way:   Rock Boulevard to Energy Way

Tuesday 5/30/2023
Micro-Surfacing
Calle De La Plata:   Pyramid Hwy to Encanto Drive
Seventh Avenue:   Tassel Drive to Sun Valley Boulevard

Pavement Crack Sealing 7pm-7am
Golden Valley Road:   Marlin Drive to Spearhead Drive
Catron Drive:   Parr Boulevard to Parr Circle
Sierra Street:   Virginia Street to Eleventh Street
Plaza Street:   Virginia Street to Lake Street
Vine Street:   Second Street to University Terrace
Plumb Lane:   McCarran Boulevard to Orange Lane
Wells Avenue:   Virginia Street to Sixth Street
Kuenzli Street:   Kietzke Lane to Sunshine Lane
Lewis Street:   W. end of Street to Golden Lane
Manuel Street:   Second Street to Kuenzli Street
Prosperity Street:   Kietzke Lane to Golden Lane
Villanova Drive:   Harvard Way to Terminal Way
Wrondel Way:   Hubbard Way to Apple Street
Energy Way:   Rock Boulevard to Edison Way
Brookside Court:   Rock Boulevard to end of cul-de-sac
Joule Street:   Rock Boulevard to Edison Way
Reactor Way:   Rock Boulevard to Energy Way
Ridgeview Drive:   Plumas Street to Lakeside Drive
Coliseum Way:   Peckham Lane to Moana Lane
Meadowood Mall Link:   Meadowood Mall Circle to McCarran Boulevard
Meadowood Mall Way:   Kietzke Lane to Virginia Street
Talbot Lane:   end of cul-de-sac to Redfield Parkway
De Spain Lane:   Mt. Rose Hwy to Butch Cassidy
Wedge Parkway:   Whites Creek Lane to Arrowcreek Parkway
Wedge Parkway:   Mt. Rose Hwy to De Spain Lane

Wednesday 5/31/2023
Micro-Surfacing
Calle De La Plata:   Pyramid Hwy to Encanto Drive
Sun Valley Boulevard:   7th Avenue to E. Highland Ranch Parkway

Pavement Crack Sealing 7pm-7am
Plumb Lane:   McCarran Boulevard to Orange Lane
Wells Avenue:   Virginia Street to Sixth Street
Kuenzli Street:   Kietzke Lane to Sunshine Lane
Lewis Street:   W. end of Street to Golden Lane
Manuel Street:   Second Street to Kuenzli Street
Prosperity Street:   Kietzke Lane to Golden Lane
Villanova Drive:   Harvard Way to Terminal Way
Wrondel Way:   Hubbard Way to Apple Street
Coliseum Way:   Peckham Lane to Moana Lane
Meadowood Mall Link:   Meadowood Mall Circle to McCarran Boulevard
Meadowood Mall Way:   Kietzke Lane to Virginia Street
Talbot Lane:   S. end of cul-de-sac to Redfield Parkway
De Spain Lane:   Mt. Rose Hwy to Butch Cassidy
Wedge Parkway:   Whites Creek Lane to Arrowcreek Parkway
Wedge Parkway:   Mt. Rose Hwy to De Spain Lane
Sandhill Road:   Double R Boulevard to Double Diamond Parkway
Double Eagle Court:   end of cul-de-sac to Gateway Drive
Prototype Court:   W. end of cul-de-sac to Gateway Drive
Zolezzi Lane:   S.E. side of Circle to the same spot in Circle
Foothill Road: Thomas Creek Rd to So. Virginia Street
Technology Way:   Double R Boulevard to Double Diamond Parkway

Thursday 6/1/2023
Micro-Surfacing
Neighborhood Way:   Eagle Canyon Drive to Eagle Canyon Drive
Icon Court:   Isidor Court to N. Isidor Court
Ingenuity Avenue:   Hawco Court to Haco Court
Clayton Place:   Isidor Court to E. of Isidor Court
Sun Valley Boulevard:   7th Avenue to E. Highland Ranch Parkway 

Pavement Crack Sealing 7pm-7am
Manuel Street:   Second Street to Kuenzli Street
Prosperity Street:   Kietzke Lane to Golden Lane
Villanova Drive:   Harvard Way to Terminal Way
Wrondel Way:   Hubbard Way to Apple Street
Zolezzi Lane:   S.E. side of Circle to the same spot in Circle
Foothill Road: Thomas Creek Road to So. Virginia Street
Technology Way:   Double R Boulevard to Double Diamond Parkway
Trademark Drive:   Double R Boulevard to end of cul-de-sac
Colbert Drive:   Longley Lane to Maestro Drive
Longley Lane:   Virginia Street to Rock Boulevard
Louie Lane:   Barron Way to Longley Lane
Barron Way:   Louie Lane to Reno Corporate Drive
Quail Manor Court:   Airway Drive to Airway Drive

Friday 6/2/2023
Micro-Surfacing
Belmar Drive:   Earthstone Drive to Los Altos Parkway
Kiley Parkway East:   Windmill Farms Parkway to Wingfield Hills Road
Lupin Drive:   Fifth Avenue to 9th Avenue

Pavement Patching
Plumas Street:   Plumb Lane to California Avenue
Apple Street:   Kirman Avenue to Kietzke Lane

Pavement Crack Sealing 7pm-7am
Plumb Lane:   McCarran Boulevard to Orange Lane
Wells Avenue:   Virginia Street to Sixth Street
Kuenzli Street:   Kietzke Lane to Sunshine Lane
Lewis Street:   W. end of Street to Golden Lane

HOLCOMB AVENUE REHABILITATION
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Construction crews working on the east side of Holcomb Avenue between Burns Street and Liberty Street. Northbound traffic on Holcomb will be shifted and one lane of traffic in each direction will be maintained.

Parking on street will be limited within areas of improvements and driveways will be temporarily impacted during construction. Short traffic delays and detours may occur.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 
RTC Project Manager, Alex Wolfson, P.E., PTOE, RSP1 – (775) 332-2139

Minor shoulder closures may occur for final construction items.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Construction crews working on center median (concrete) and landscaping.

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Intermittent traffic lane shifts during construction hours.
  • Construction crews are continuing to work on installing underground light conduit, retaining wall, signals and fence removals. Additional construction crews will work on storm drain installations.
  • New traffic pattern – travel lanes (one in each direction) shifted to the south side of Oddie Boulevard from Sullivan Lane to east of US-395 ramps.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PEPPERMILL BUS RAPID TRANSIT
RTC Project Manager, Ian Chamberlain – (775) 335-0023

Single bus lane closure adjacent to transit station on northbound S. Virginia Street in place.

SKY VISTA WIDENING AND REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

A single lane and shoulder closure will be in place northbound between Greg Street and the I-80 Eastbound Ramps.  Anticipate lane closures and short traffic delays at night for striping operations.

SUTRO STREET AND ENTERPRISE ROAD REHABILITATION
RTC Project Manager, Maria Paz Fernandez, P.E.  – (775) 335-1861

Sutro Street – 9th Street to Oddie Boulevard:

  • Lanes open in both directions.
  • Sutro/9th Street intersection closure – weekend of July 8th.

Enterprise Road – Evans Avenue to Valley Road:

  • Road closed – June 5th through June 30th.

4TH STREET AND WOODLAND AVENUE ROUNDABOUT INSTALLATION
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction in progress. The project is anticipated to be completed by the end of August 2023.

Lane reconfigurations and two-way traffic control on W. 4th Street and Woodland Avenue have been installed. Intermittent flagging operations at this intersection could cause delays of up to 20 minutes.

Mesa Park Road from W. 4th Street to 500 feet north remains closed and the closure has been extended through the month of June while construction of the following occurs:

  • Retaining wall below Mesa Park Road.
  • 4th Street westbound lanes.
  • Northern portion of the roundabout.

Normal construction hours are 7:00 a.m. – 5:00 p.m., Monday through Friday.

For more information, visit 4th-woodland-roundabout.com

 