2023 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Sunday 5/21/2023
Pavement Crack Sealing – Night Work (7pm-7am)
Wedekind Road: Sutro Street to end curb and gutter left (City Limits)
Golden Valley Road: North Hills Boulevard to Pontiac Drive
Sun Valley Boulevard: 7th Avenue to E. Highland Ranch Parkway
Monday 5/22/2023
Pavement Patching
Foothill Road: Thomas Creek Road to S. Virginia Street
Thomas Creek Road: Zolezzi Lane to N. State Hwy 431
Pavement Crack Sealing 7pm – 7am
Golden Valley Road: North Hills Boulevard to Pontiac Drive
Sun Valley Boulevard: 7th Avenue to E. Highland Ranch Parkway
Moya Boulevard: Red Rock Road to Echo Avenue
Catron Drive: Parr Boulevard to Parr Circle
Tuesday 5/23/2023
Pavement Patching
Thomas Creek Road: Zolezzi Lane to N. State Hwy 431
Pavement Crack Sealing 7pm-7am
Moya Boulevard: Red Rock Road to Echo Avenue
Catron Drive: Parr Boulevard to Parr Circle
Sierra Street: Virginia Street to Eleventh Street
Plaza Street: Virginia Street to Lake Street
Vine Street: Second Street to University Terrace
Wednesday 5/24/2023
Pavement Patching
Thomas Creek Road: Zolezzi Lane to N. State Hwy 431
Ridgeview Drive: Plumas Street to Lakeside Drive
Pavement Crack Sealing 7pm-7am
Plaza Street: Virginia Street to Lake Street
Vine Street: Second Street to University Terrace
Plumb Lane: McCarran Boulevard to Orange Lane
Wells Avenue: Virginia Street to Sixth Street
Kuenzli Street: Kietzke Lane to Sunshine Lane
Lewis Street: West end of Street to Golden Lane
Thursday 5/25/2023
Pavement Patching
Ridgeview Drive: Plumas Street to Lakeside Drive
Talbot Lane: South end cul-de-sac to Redfield Parkway
Pavement Crack Sealing 7pm-7am
Plumb Lane: McCarran Boulevard to Orange Lane
Wells Avenue: Virginia Street to Sixth Street
Kuenzli Street: Kietzke Lane to Sunshine Lane
Lewis Street: West end of Street to Golden Lane
Manuel Street: Second Street to Kuenzli Street
Prosperity Street: Kietzke Lane to Golden Lane
Villanova Drive: Harvard Way to Terminal Way
Wrondel Way: Hubbard Way to Apple Street
Friday 5/26/2023
Pavement Patching
Lymbery Street: Moana Lane to Cadillac Place
Meadowood Mall Link: Meadowood Mall Circle to McCarran Boulevard
HOLCOMB AVENUE REHABILITATION PROJECT
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881
Construction crews working on the east side of Holcomb Avenue between Burns Street and Liberty Street. Northbound traffic on Holcomb will be shifted and one lane of traffic in each direction will be maintained.
Parking on street will be limited within areas of improvements and driveways will be temporarily impacted during construction. Short traffic delays and detours may occur.
INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Alex Wolfson, P.E., PTOE, RSP1 – (775) 332-2139
Minor shoulder closures may occur for final construction items.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- One traffic lane in each direction will be maintained along Oddie Boulevard.
- Construction crews working on center median (concrete) and landscaping.
Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):
- One traffic lane in each direction will be maintained along Oddie Boulevard.
- Intermittent traffic lane shifts during construction hours.
- Construction crews are continuing to work on installing underground light conduit, retaining wall, signals and fence removals. Additional construction crews will work on storm drain installations.
- New traffic pattern – travel lanes (one in each direction) shifted to the south side of Oddie Boulevard from Sullivan Lane to east of US-395 ramps.
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
PEPPERMILL BUS RAPID TRANSIT PROJECT
RTC Project Manager, Ian Chamberlain – (775) 335-0023
Lane closure on northbound S. Virginia Street will remain in current configuration.
SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
Lane and shoulder closures will be in place.
SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881
A single lane and shoulder closure will be in place northbound between Greg Street and the I-80 Eastbound Ramps.
SUTRO STREET AND ENTERPRISE ROAD REHABILITATION PROJECT
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Sutro Street – 9th Street to Oddie Boulevard:
- Lanes open on both directions. Intermittent traffic control for miscellaneous items (striping, raising utilities, etc.)
- Sutro/9th Street intersection closure – weekend of July 8th.
Enterprise Road – Evans Avenue to Valley Road:
- Road closed – June 5th through June 30th.
4TH STREET AND WOODLAND AVENUE ROUNDABOUT INSTALLATION
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865
Construction in progress. The project is anticipated to be completed by the end of August 2023.
Lane reconfigurations and two-way traffic control on W. 4th Street and Woodland Avenue have been installed and will be maintained through approximately May 26th. Intermittent flagging operations at this intersection could cause delays of up to 20 minutes.
Mesa Park Road from W. 4th Street to 500 feet north is closed until approximately May 26th, while construction of the following occurs:
- Retaining wall below Mesa Park Road.
- 4th Street westbound lanes.
- Northern portion of the roundabout.
Normal construction hours are 7:00 a.m. – 5:00 p.m., Monday through Friday.
For more information, visit 4th-woodland-roundabout.com