BUS STOP IMPROVEMENT & CONNECTIVITY PROGRAM – PHASE 4
RTC Project Manager, Kimberly Diegle, P.E.– (775) 335-1844
Lane and shoulder closures may be in place on North Virginia Street at Talus Way and Parr Boulevard; and on Glendale Avenue at Marietta Way.
INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139
Remaining construction will resume in April/May timeframe.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- One traffic lane in each direction will be maintained along Oddie Boulevard
- Construction crews working on installing steel tube fence, signal work and grade planters (weather permitting)
Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):
- Shoulder and lane closures during construction working hours
- One traffic lane in each direction will be maintained along Oddie Boulevard
- Construction crews working on installing underground light conduit, retaining wall, signals and fence removals (weather permitting)
- Mall Drive access closed until June – Detours to shopping center through Silverada and El Rancho accesses partially open (right-in/right-out) when feasible
- Starting March 10, 2023 (weather permitting) – new traffic pattern – travel lanes (in each direction) shifted to the south side of the road from Sullivan to Silverada
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
Lane and shoulder closures will be in place.
SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881
Installation of illuminated street signs will resume in March.
TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865
This project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work and the construction of a retaining wall below Mesa Park Road will resume late February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.
TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139
Traffic Signal at Mill Street and Telegraph Street – signal is active. Please use caution driving through the intersection.