BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:
1. East 9th Street and Montello Street Intersection
2. Valley Road and Sadleir Way Intersection
3. Sutro Street and Haddock Drive Intersection
4. Lemmon Drive and North Virginia Street Intersection
5. Kirman Avenue and Moran Street Intersection
6. Mill Street and Sunshine Lane Intersection
7. Locust Street and Colorado River Boulevard Intersection
8. Grove Street and Yori Way Intersection
9. Hunter Lake Drive and Foster Drive Intersection
10. Sierra Center Parkway at Sierra Town Center
11. York Way and 4th Street Intersection
12. Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/9 – 3/13
Short term shoulder closures at: Baring Blvd. and McCarran Blvd.; Sparks Blvd. at Disc Dr.; Vista Blvd. at Disc Dr.; Baring Blvd. at N. Truckee Ln.; Sparks Blvd at Shadow Ln.

3/16 – 3/27
Shoulder closures at I-580 southbound on-ramp at Damonte Ranch Pkwy, I80 ramps at McCarran and Robb Dr.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about 5 weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/9 – 3/20
Underground construction will begin at McCarran Blvd and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Mt Rose St/Holcomb Ave: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area will require closure of either Center St or Mary St at Virginia St. While construction work is occurring on the west side of the roundabout, both Center St and Mary St are closed at Virginia St.
  • Detours will be in place.