Weekly Traffic Control Report

June 9, 2023

2023 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Sunday 6/11/2023
Pavement Crack Sealing 7pm – 7am
Disc Drive: Vista Boulevard to Sparks Boulevard
Sparks Boulevard: Baring Boulevard to Pyramid Highway
E Prater Way: Stanford Way to Sparks Boulevard
Victorian Avenue: El Rancho Boulevard to Pyramid Highway
Longley Lane: Virginia Street to Rock Boulevard
Meadowood Mall Way: Kietzke Land to Virginia Street
Meadowood Mall Link: McCarran Boulevard to Meadowood Mall Circle
Plumb Lane: McCarran Boulevard to Orange Lane
Wells Avenue: Virginia Street to Sixth Street

Monday 6/12/2023
Pavement Patching
Vine Street: Second Street to University Terrace
Lewis Street: Golden Lane to Maine Street
Sierra Street: Virginia Street to Eleventh Street
Wedekind Road: Sutro Street to City Limits

Pavement Crack Sealing 7pm – 7am
Disc Drive: Vista Boulevard to Sparks Boulevard
Sparks Boulevard: Baring Boulevard to Pyramid Highway
E Prater Way: Stanford Way to Sparks Boulevard
Victorian Avenue: El Rancho Boulevard to Pyramid Highway
Longley Lane: Virginia Street to Rock Boulevard
Meadowood Mall Way: Kietzke Land to Virginia Street
Meadowood Mall Link: McCarran Boulevard to Meadowood Mall Circle
Plumb Lane: McCarran Boulevard to Orange Lane
Wells Avenue: Virginia Street to Sixth Street

Pavement Striping 7pm – 7am
Coliseum Way: Peckham Lane to Moana Lane
Ridgeview Drive: Plumas Street to Lakeside Drive
Quail Manor Court: Airway Drive to Airway Drive

Tuesday 6/13/2023
Micro-Surfacing
Thomas Creek Road: Zolezzi Lane to SR431

Pavement Patching 
Lewis Street: Golden Lane to Maine Street
Sierra Street: Virginia Street to Eleventh Street
Wedekind Road: Sutro Street to City Limits
Seventh Avenue: Tassel Drive to Sun Valley Boulevard
Golden Valley Road: North Hills Boulevard to Pontiac Drive
Golden Valley Road: Marlin Drive to Spearhead Drive

Pavement Crack Sealing 7pm – 7am
Disc Drive: Vista Boulevard to Sparks Boulevard
Sparks Boulevard: Baring Boulevard to Pyramid Highway
E Prater Way: Stanford Way to Sparks Boulevard
Victorian Avenue: El Rancho Boulevard to Pyramid Highway
Longley Lane: Virginia Street to Rock Boulevard
Meadowood Mall Way: Kietzke Land to Virginia Street
Meadowood Mall Link: McCarran Boulevard to Meadowood Mall Circle
Plumb Lane: McCarran Boulevard to Orange Lane
Wells Avenue: Virginia Street to Sixth Street

Pavement Striping 7pm – 7am
Thomas Creek Road: Zolezzi Lane to SR431

Wednesday 6/14/2023
Micro-Surfacing
Thomas Creek Road: Zolezzi Lane to SR431

Pavement Patching 
Seventh Avenue: Tassel Drive to Sun Valley Boulevard
Golden Valley Road: North Hills Boulevard to Pontiac Drive

Pavement Crack Sealing 7pm – 7am
Disc Drive: Vista Boulevard to Sparks Boulevard
Sparks Boulevard: Baring Boulevard to Pyramid Highway
E Prater Way: Stanford Way to Sparks Boulevard
Victorian Avenue: El Rancho Boulevard to Pyramid Highway
Longley Lane: Virginia Street to Rock Boulevard
Meadowood Mall Way: Kietzke Land to Virginia Street
Meadowood Mall Link: McCarran Boulevard to Meadowood Mall Circle
Plumb Lane: McCarran Boulevard to Orange Lane
Wells Avenue: Virginia Street to Sixth Street

Pavement Striping 7pm – 7am
Thomas Creek Road: Zolezzi Lane to SR431

Thursday 6/15/2023
Micro-Surfacing
Coliseum Way: Peckham Lane to Moana Lane
Ridgeview Drive: Plumas Street to Lakeside Drive
Quail Manor Court: Airway Drive to Airway Drive

Pavement Patching
Golden Valley Road: Marlin Drive to Spearhead Drive
Somersett Ridge Parkway: US HWY40 to Del Webb Parkway
South Verdi Road: Bridge Street to Garson Road

Pavement Crack Sealing 7pm – 7am
Disc Drive: Vista Boulevard to Sparks Boulevard
Sparks Boulevard: Baring Boulevard to Pyramid Highway
E Prater Way: Stanford Way to Sparks Boulevard
Victorian Avenue: El Rancho Boulevard to Pyramid Highway
Longley Lane: Virginia Street to Rock Boulevard
Meadowood Mall Way: Kietzke Land to Virginia Street
Meadowood Mall Link: McCarran Boulevard to Meadowood Mall Circle
Plumb Lane: McCarran Boulevard to Orange Lane
Wells Avenue: Virginia Street to Sixth Street

Pavement Striping 7pm – 7am
Locust Street: Casazza Drive to Mill Street

Friday 6/16/2023
Micro-Surfacing
Wedge Parkway: Whites Creek Lane to Arrowcreek Parkway
Wedge Parkway: SR 431 to De Spain Lane
Zolezzi Lane: Ventana Parkway to Ventana Parkway
De Spain Lane: SR 431 to Butch Cassidy Street

Pavement Patching
Somersett Ridge Parkway: US HWY40 to Del Webb Parkway
South Verdi Road: Bridge Street to Garson Road
Victorian Avenue: El Rancho Boulevard to Pyramid Way
Sparks Boulevard: Baring Boulevard to Pyramid Hwy
Disc Drive: Sparks Boulevard to Vista Boulevard

Pavement Striping 7pm – 7am
Wedge Parkway: Whites Creek Lane to Arrowcreek Parkway
Wedge Parkway: SR 431 to De Spain Lane
Zolezzi Lane: Ventana Parkway to Ventana Parkway

HOLCOMB AVENUE REHABILITATION
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Construction crews working on the west side of Holcomb Avenue between Burns Street and Liberty Street. Southbound traffic on Holcomb will be shifted and one lane of traffic in each direction will be maintained.

On-street parking will be limited within areas of improvements and driveways will be temporarily impacted during construction. Short traffic delays and detours may occur.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 
RTC Project Manager, Alex Wolfson, P.E., PTOE, RSP1 – (775) 332-2139

Minor shoulder closures may occur for final construction items.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Construction crews finishing work on center median (concrete) and landscaping.

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Intermittent traffic lane shifts during construction hours.
  • Construction crews are continuing to work on installing underground light conduit, retaining wall, signals and fence removals. Additional construction crews will work on storm drain installations.
  • New traffic pattern – travel lanes (one in each direction) shifted to the south side of Oddie Boulevard from Sullivan Lane to east of US-395 ramps.
  • Paving operations work starting on June 16 through June 30. Half intersection closures (Sullivan, El Rancho & Silverada). Detours in place.

Phase 4 – Sutro Street to I-80 Ramps (Reno):

  • Tentative start date for underground construction work July 5th.
    • One traffic lane in each direction will be maintained along Oddie Boulevard.
    • Intermittent traffic lane shifts during construction hours.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PEPPERMILL BUS RAPID TRANSIT
RTC Project Manager, Ian Chamberlain – (775) 335-0023

Single bus lane closure adjacent to transit station on northbound S. Virginia Street in place.

SKY VISTA WIDENING AND REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Anticipate lane closures and short traffic delays at night for striping operations.

SUTRO STREET AND ENTERPRISE ROAD REHABILITATION
RTC Project Manager, Maria Paz Fernandez, P.E.  – (775) 335-1861

Sutro Street – 9th Street to Oddie Boulevard:

  • Lanes open in both directions.
  • Sutro/9th Street intersection closure – weekend of July 8th through July 10th.

Enterprise Road – Evans Avenue to Valley Road:

  • Construction crews have begun removal of pavement.
  • Road closed – June 5th through June 30th. Detours in place.

4TH STREET AND WOODLAND AVENUE ROUNDABOUT INSTALLATION
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of the westbound travel lanes and roundabout has begun. Intermittent flagging operations at this intersection could cause delays of up to 20 minutes. Normal construction hours are 7:00 a.m. – 5:00 p.m., Monday through Friday.

Mesa Park Road from W. 4th Street to 500 feet north remains closed and the closure has been extended through the month of June while construction of the following occurs:

  • 4th Street westbound lanes and islands.
  • Northern portion of the roundabout.

The project is anticipated to be completed by the end of August 2023
For more information, visit 4th-woodland-roundabout.com

 

See weekly traffic report archive