BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897
RTC’s contractor, Sierra Nevada Construction, will be working on the pedestrian crossing flasher at the following location:
- Mill Street and Kirman Avenue (near Renown)
Drivers should expect lane and shoulder closures. Pedestrian detours will be provided.
GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871
Installation is complete and the traffic signal is active. Final paving and striping will occur June 13, 2022.
INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871
Construction to begin June 2022.
KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872
- The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
- Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
- Starting June 13, Kings Row will be one-way (traveling down hill) between McCarran Boulevard and Wyoming Avenue. Detours will be in place for vehicles traveling through this area.
- In addition, the section of Kings Row between Apollo Way and Wyoming Avenue will be closed to through traffic, vehicles will detour at Apollo Way with routing back to Wyoming Avenue and Kings Row.
LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.
MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Traffic Control Changes!
Spanish Springs Construction will begin work on the NORTH side of Mill Street between McCarran Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Business and side street access will be maintained.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1: Pyramid Way to Sullivan Lane (Sparks):
- Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
- Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
- Roadwork activities:
- “Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
- Sullivan Lane – Northside instersection closure – Monday June 6 – Friday June 17, 2022.
One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com.
RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
California Avenue – Hunter Lake Drive to Booth Street
California Avenue is closed to through traffic. Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.
Mayberry Drive – Memory Lane to California Avenue
One lane in each direction is open to traffic. Please slow down through construction zones for the safety of the community and workers.
RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874
Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway. This week the contractor will begin removing the old pavement.
As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.
TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897
No work is scheduled for this project.
TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871
Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 2022.
TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871
Construction of traffic signal at Mill Street/Telegraph Street and South Meadows Boulevard/Wilbur May Boulevard to begin June 2022.