2023 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
**Note: This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Sunday 7/9/2023
Pavement Striping 7pm – 7am
Wedekind Road: Sutro Street to End of City Limits
Monday 7/10/2023
Micro-Surfacing (Slurry)
South Verdi Road: Bridge Street to Garson Road
Golden Valley Road: North Hills Boulevard to Pontiac Drive
Golden Valley Road: Marlin Drive to Spearhead
Patriot Boulevard: Virginia Street to Colbert Lane
Brinkby Avenue: Plumas Street to Virginia Street
Pavement Striping 7pm – 7am
Cola Court: Cul de Sac to Vista Boulevard
Loop Road: Vista Boulevard to Horsemans Park
Packer Way: Cul de Sac to Glendale Avenue
Salomon Circle: Loop Road to End of Pavement
S Stanford Way: Glendale Avenue to S McCarran Boulevard
S Verdi Road: Bridge Street to Garson Road
Golden Valley Road: North Hills Boulevard to Pontiac Drive
Golden Valley Road: Marlin Drive to Spearhead
Patriot Boulevard: Virginia Street to Colbert Lane
Brinkby Avenue: Plumas Street to Virginia Street
Tuesday 7/11/2023
Micro-Surfacing (Slurry)
Plumas Street: Plumb Lane to California Avenue
Sandhill Road: Double R Boulevard to Double Diamond Parkway
Prototype Court: W End of Cul de Sac to Gateway Drive
Portman Avenue: Patriot Boulevard to Offenhauser Drive
Pavement Patching
College Drive: Isidor Court to Isidor Court
Lakeshore Boulevard: SR 28 to Village Boulevard
Mays Boulevard: Southwood Boulevard to Lakeshore Boulevard
Southwood Boulevard: SR 28 to SR28
Village Boulevard: Tahoe Boulevard to Eagle Drive
Pavement Striping 7pm – 7am
Plumas Street: Plumb Lane to California Avenue
Sandhill Road: Double R Boulevard to Double Diamond Parkway
Prototype Court: W End of Cul de Sac to Gateway Drive
Portman Avenue: Patriot Boulevard to Offenhauser Drive
Wednesday 7/12/2023
Micro-Surfacing (Slurry)
Edison Way: Rock Boulevard to Edison Way
Brookside Court: Rock Boulevard to End of Cul de Sac
Trademark Drive: Double R Boulevard to End of Cul de Sac
Pavement Patching 7pm – 7am
Sparks Boulevard: Baring Boulevard to Pyramid Way
Disk Drive: Vista Boulevard to Sparks Boulevard
Pavement Striping 7pm – 7am
Edison Way: Rock Boulevard to Edison Way
Brookside Court: Rock Boulevard to End of Cul de Sac
Trademark Drive: Double R Boulevard to End of Cul de Sac
Thursday 7/13/2023
Micro-Surfacing (Slurry)
Victorian Avenue: El Rancho Boulevard to Pyramid Way
Meadowood Mall Link: Meadowood Mall Circle to McCarran Boulevard
Louie Lane: Barron Way to Longley Lane
Bluestone Drive: Portman Avenue to Huffaker Lane
Pavement Patching 7pm – 7am
Sparks Boulevard: Baring Boulevard to Pyramid Way
Disk Drive: Vista Boulevard to Sparks Boulevard
Pavement Striping 7pm – 7am
Victorian Avenue: El Rancho Boulevard to Pyramid Way
Meadowood Mall Link: Meadowood Mall Circle to McCarran Boulevard
Louie Lane: Barron Way to Longley Lane
Bluestone Drive: Portman Avenue to Huffaker Lane
E Prater Way: Stanford Way to Sparks Boulevard
Golden Valley Road: Marlin Drive to Spearhead Way
Friday 7/14/2023
Micro-Surfacing (Slurry)
Plumb Lane: McCarran Boulevard to Orange Lane
Greg Street: N End Plain Cement Concrete to Bridge Joint
E Greg Street: S McCarran Boulevard to RR Xing
Wolverine Way: Glendale Avenue to Stanford Way
Pavement Patching 7pm – 7am
Sparks Boulevard: Baring Boulevard to Pyramid Way
Disk Drive: Vista Boulevard to Sparks Boulevard
Pavement Striping 7pm – 7am
Plumb Lane: McCarran Boulevard to Orange Lane
Greg Street: N End of Plain Cement Concrete to Bridge Joint
E Greg Street: S McCarran to RR Xing
Wolverine Way: Glendale Avenue to Stanford Way
Saturday 7/15/2023
Micro-Surfacing (Slurry)
Catron Drive: Parr Boulevard to Parr Circle
4TH STREET AND WOODLAND AVENUE ROUNDABOUT INSTALLATION
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction of the westbound travel lanes and roundabout has begun. Intermittent flagging operations at this intersection could cause delays of up to 20 minutes. Normal construction hours are 7:00 a.m. – 5:00 p.m., Monday through Friday.
Mesa Park Road from W. 4th Street to 500 feet north remains closed and the closure has been extended through mid-July while construction of the following occurs:
- 4th Street westbound lanes and islands
- Northern portion of the roundabout
The project is anticipated to be completed by Fall of 2023.
For more information, visit https://www.4th-woodland-roundabout.com/
ARROWCREEK PARKWAY REHABILITATION PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Lane and shoulder closures will be in place on Arrowcreek Parkway, S. Virginia Street, and Damonte Ranch Parkway. Two-way traffic will be maintained on Arrowcreek Parkway, but watch for traffic shifts and expect delays.
CALIFORNIA AVE. RECONSTRUCTION-NEWLANDS CIRCLE TO ARLINGTON PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Construction begins Monday June 19, 2023. Contractor is currently planning to maintain two-way traffic but expect delays.
HOLCOMB AVENUE REHABILITATION PROJECT
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881
Construction crews working on the pavement removal (cold milling) and permanent pavement patching on Holcomb Avenue between Burns Street and Liberty Street commencing after the July 4th holiday. Traffic on Holcomb will be shifted and one lane of traffic in each direction will be maintained.
Sinclair Street will remain closed between the Sinclair/Thoma Intersection and the Sinclair/Holcomb Intersection for reconfiguration and full depth reconstruction.
Parking on street will be limited within areas of improvements and driveways will be temporarily impacted during construction. Short traffic delays and detours may occur.
INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Alex Wolfson, P.E., PTOE, RSP1 – (775) 332-2139
Minor shoulder closures may occur for final construction items.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- Construction crews finishing work on center median (concrete) and landscaping.
Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):
- Paving operations through July 10th. Half intersection closures (Sullivan, El Rancho & Silverada). Detours in place.
- Traffic will be swapped to the northside tentatively on Wednesday July 12.
Phase 3 – east of US 395 Ramps to Sutro Street (Reno):
- Intermittent traffic lane shifts during construction hours.
- Traffic swapped to the southside.
- Concrete work (sidewalk and retaining curb)
Phase 4 – Sutro Street to I-80 Ramps (Reno):
-
- Intermittent traffic lane shifts during construction hours.
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
Lane and shoulder closures will be in place.
SUTRO STREET AND ENTERPRISE ROAD REHABILITATION PROJECT
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Sutro Street – 9th Street to Oddie Boulevard:
- Road open – intermittent land closure for stripping, raising utilities and other minor work.
Enterprise Road – Evans Avenue to Valley Road:
- Road open – intermittent lane closure for stripping, raising utilities and other minor work.