Weekly Traffic Control Report

July 5, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 7/5
NO WORK SCHEDULED

Monday 7/8
Pavement Crack Sealing (Night Work)
Mill St: Lake St to I-580 On/Off Ramps
Louise St: Market St to Mill St
Redwood Pl: Market St to Mill St
Market St: Villanova Dr to Kietzke Ln
Yale Wy: Harvard Wy to Market St
Automotive Wy: Kietzke Ln to Market St
Kirman Ave: Kuenzli St to Ryland St
Valley Rd: Fourth St to Enterprise Wy
Condor Wy: Airmotive Wy to end of street

Tuesday 7/9
Pavement Crack Sealing (Night Work)
Mill St: Lake St to I-580 On/Off Ramps
Louise St: Market St to Mill St
Redwood Pl: Market St to Mill St
Market St: Villanova Dr to Kietzke Ln
Yale Wy: Harvard Wy to Market St
Automotive Wy: Kietzke Ln to Market St
Kirman Ave: Kuenzli St to Ryland St
Valley Rd: Fourth St to Enterprise Wy
Condor Wy: Airmotive Wy to end of street

Wednesday 7/10
Pavement Crack Sealing (Night Work)
Seventh St: Robb Dr to Washington St
Seventh St: Sierra St to Virginia St
S 15th St: Hymer Ave to Glendale Ave
S 16th St: Glendale Ave to Hymer Ave
S 18th St: Glendale Ave to Crane Wy
S 19th St: Hymer Ave to Pacific Ave
S 21st St: Greg St to Pacific Ave
Pacific Ave: S 21st St to S 19th St
Tacchino St: Depaoli St to Fourth St
Depaoli St: Fifth St to Tacchino St
Ferrari St: Fourth St to Fifth St

Thursday 7/11
Pavement Crack Sealing (Night Work)
Seventh St: Robb Dr to Washington St
Seventh St: Sierra St to Virginia St
S 15th St: Hymer Ave to Glendale Ave
S 16th St: Glendale Ave to Hymer Ave
S 18th St: Glendale Ave to Crane Wy
S 19th St: Hymer Ave to Pacific Ave
S 21st St: Greg St to Pacific Ave
Pacific Ave: S 21st St to S 19th St
Tacchino St: Depaoli St to Fourth St
Depaoli St: Fifth St to Tacchino St
Ferrari St: Fourth St to Fifth St

Friday 7/12
Pavement Crack Sealing (Night Work)
Seventh St: Robb Dr to Washington St
Seventh St: Sierra St to Virginia St
S 15th St: Hymer Ave to Glendale Ave
S 16th St: Glendale Ave to Hymer Ave
S 18th St: Glendale Ave to Crane Wy
S 19th St: Hymer Ave to Pacific Ave
S 21st St: Greg St to Pacific Ave
Pacific Ave: S 21st St to S 19th St
Tacchino St: Depaoli St to Fourth St
Depaoli St: Fifth St to Tacchino St
Ferrari St: Fourth St to Fifth St

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
From Newlands Circle to Booth Street

Starting July 8, 2019, at 6:00 a.m. through July 12, 2019:

  • California Ave/Keystone Ave Intersection will be open to traffic in both directions in the construction zone.
  • Booth St will be open to one-way traffic Northbound between Westfield Ave and Idlewild Dr for paving operations.  Booth St will be closed to all traffic between California Ave and  Westfield Ave during this same time period.
  • Keystone Ave will also remain closed to northbound traffic from Booth St to Riverside Dr.
  • Keystone Ave will not be accessible from California Ave.

Detours will be in place during construction. For safety reasons, there is no pedestrian access through California Ave from Newlands Cir to Booth St during construction.

In mid-July, the California Avenue/Keystone Avenue intersection will return to a full closure so crews can finish construction before Reno High School is back in session.

SPARKS CONSOLIDATED 19-01 – 15TH STREET, FRANKLIN WAY, HULDA COURT, AND EL RANCHO DRIVE

Starting July 10, 2019, at 7:00 a.m. through July 12, 2019:

  • 15th Str from Victorian Ave to Prater Wy will be open to traffic in both directions in the construction zone.  Construction crews will be working on the east side concrete improvements.
  • El Rancho Dr from G St to Oddie Blvd will be open to traffic in both directions. Traffic lanes will be reduced to one-lane in each direction and moved over to west half of the roadway for construction of concrete improvements on the east side.
  • Traffic on Franklin Wy from Greg St to the Railroad Tracks will not be impacted.
  • Hulda Ct traffic will not be impacted.

Pedestrian detours will be in place during construction.  El Rancho Dr pedestrian detour will be from Oddie Blvd into Paradise Park, down to Elementary Dr, and south to G St using existing sidewalk on the west side El Rancho Dr.  For safety reasons, there is no pedestrian access on the east side of El Rancho Dr from G St to Oddie Blvd during construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
Construction is occurring from Plumb Ln through Mt Rose St and on select side streets within the Midtown areas.

  • Between Plumb Ln and Mt Rose St traffic will be reduced to southbound only, northbound traffic will be detoured at Wells Ave to Vassar St.
  • The following side streets are also under construction and closed to through traffic, local access is provided:
    • Tahoe/Saint Lawrence (between Virginia St and Forest St)
    • Moran (between Virginia St and Center St)
    • East Taylor (between Virginia St and Center St)
    • Martin (between Virginia St and Haskell St)
    • Caliente (between Virginia St and Haskell St)
  • NV Energy Gas is operating within the vicinity of S Virginia St (in Midtown).