Weekly Traffic Control Report

June 28, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 7/1/2019

Pavement Crack Sealing (Nightwork)

Sparks Boulevard: I-80 Right of Way to E Prater Way
Marietta Way: Glendale Avenue to End of Pavement
S Rock Boulevard: Glendale Avenue Middle of Truckee Bridge
S 15th Street: Hymer Avenue to Glendale Avenue
S 16th Street: Glendale Avenue to Hymer Avenue
S 18th Street: Glendale Avenue to Crane Way
S 19th Street: Hymer Avenue to Pacific Avenue
S 21st Street: Greg Street to Pacific Avenue
Pacific Avenue: S 21st Street to S 19th Street

Tuesday 7/2/2019

Pavement Crack Sealing (Nightwork)

Sparks Boulevard: I-80 Right of Way to E Prater Way
Marietta Way: Glendale Avenue to End of Pavement
S Rock Boulevard: Glendale Avenue Middle of Truckee Bridge
S 15th Street: Hymer Avenue to Glendale Avenue
S 16th Street: Glendale Avenue to Hymer Avenue
S 18th Street: Glendale Avenue to Crane Way
S 19th Street: Hymer Avenue to Pacific Avenue
S 21st Street: Greg Street to Pacific Avenue
Pacific Avenue: S 21st Street to S 19th Street

Slurry Seal
Del Webb Parkway East: Somersett Parkway to Somersett Ridge Parkway
Del Webb Parkway West: Somersett Ridge Parkway to Somersett Parkway

Wednesday 7/3/2019

Pavement Crack Sealing (Nightwork)

Sparks Boulevard: I-80 Right of Way to E Prater Way
Marietta Way: Glendale Avenue to End of Pavement
S Rock Boulevard: Glendale Avenue Middle of Truckee Bridge
S 15th Street: Hymer Avenue to Glendale Avenue
S 16th Street: Glendale Avenue to Hymer Avenue
S 18th Street: Glendale Avenue to Crane Way
S 19th Street: Hymer Avenue to Pacific Avenue
S 21st Street: Greg Street to Pacific Avenue
Pacific Avenue: S 21st Street to S 19th Street

Slurry Seal
Del Webb Parkway East: Somersett Parkway to Somersett Ridge Parkway
Del Webb Parkway West: Somersett Ridge Parkway to Somersett Parkway

Thursday 7/4

NO WORK SCHEDULED

 

Friday 7/5

NO WORK SCHEDULED

 

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
From Newlands Circle to Booth Street

Starting July 8, 2019, at 6:00 a.m. through July 12, 2019:

  • California Ave/Keystone Ave Intersection will be open to traffic in both directions in the construction zone.
  • Booth St will be open to one way traffic Northbound between Westfield Ave and Idlewild Dr for paving operations.  Booth St will be closed to all traffic between California Ave and  Westfield Ave during this same time period.
  • Keystone Ave will also remain closed to northbound traffic from Booth St to Riverside Dr.
  • Keystone Ave will not be accessible from California Ave.

Detours will be in place during construction. For safety reasons, there is no pedestrian access through California Ave from Newlands Cir to Booth St during construction.

In mid-July, the California Avenue/Keystone Avenue intersection will return to a full closure so crews can finish construction before Reno High School is back in session.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
Construction is occurring from Plumb Ln through Mt Rose St and on select side streets within the Midtown areas.

  • Between Plumb Ln and Mt Rose St traffic will be reduced to southbound only, northbound traffic will be detoured at Wells Ave to Vassar St.
  • The following side streets are also under construction and closed to through traffic, local access is provided:
    •  Tahoe/Saint Lawrence (between Virginia St and Forest St)
    • Moran (between Virginia St and Center St)
    • East Taylor (between Virginia St and Center St)
    • Martin (between Virginia St and Haskell St)
    • Caliente (between Virginia St and Haskell St)
  • NV Energy Gas is operating within the vicinity of S Virginia St (in Midtown).

For the most up to date information on traffic control, please visit the Virginia Street Website.  