Weekly Traffic Control Report

July 26, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Sunday 7/28/2019

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
David Allen Parkway: Kiley Parkway East to Fortunato Loop
Lazy 5 Parkway: Pyramid Highway to David Allen Parkway
Clearacre Lane: Wedekind Road to McCarran Boulevard
Valley Road: Fourth Street to Enterprise Way
Yale Street: Harvard Way to Market Street
Telegraph Street: Vassar Street to Greg Street
Redwood Place: Market Street to Mill Street
Matley Lane: Vassar Street to Mill Street
Market Street: Villanova Drive to Kietzke Lane

Monday 7/29/2019

Slurry Seal
Seventh Street: Robb Drive to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
South Meadows Parkway: Double R Boulevard to Cul-De-Sac
Kirman Avenue: Kuenzli Street to Ryland Street
El Rancho Drive: Clearacre Lane to Moorpark Court
Matley Lane: Vassar Street to Mill Street
Condor Way: Airmotive Way to End of Street
Louise Street: Market Street to Mill Street
Automotive Way: Kietzke Lane to Market Street
Valley Road: Fourth Street to Enterprise Way
Yale Street: Harvard Way to Market Street
Telegraph Street: Vassar Street to Greg Street
Redwood Place: Market Street to Mill Street
Matley Lane: Vassar Street to Mill Street

Tuesday 7/30/2019

Slurry Seal
Seventh Street: Robb Drive to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Virginia Street
Kirman Avenue: Kuenzli Street to Ryland Street
El Rancho Drive: Clearacre Lane to Moorpark Court
Matley Lane: Vassar Street to Mill Street
Condor Way: Airmotive Way to End of Street
Louise Street: Market Street to Mill Street
Automotive Way: Kietzke Lane to Market Street
David Allen Parkway: Kiley Parkway East to Fortunato Loop
Lazy 5 Parkway: Pyramid Highway to David Allen Parkway

Wednesday 7/31/2019

Slurry Seal
Seventh Street: Robb Drive to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
South Meadows Parkway: Double R Boulevard to Cul-De-Sac
David Allen Parkway: Kiley Parkway East to Fortunato Loop
Lazy 5 Parkway: Pyramid Highway to David Allen Parkway

Thursday 8/1/2019

Slurry Seal
Eagle Canyon Drive: Pyramid Highway to W Calle De La Platta

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Eagle Canyon Drive: Pyramid Highway to W Calle De La Platta
South Meadows Parkway: Double R Boulevard to Cul-De-Sac

Friday 8/2/2019

Slurry Seal
Eagle Canyon Drive: Pyramid Highway to W Calle De La Platta

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Eagle Canyon Drive: Pyramid Highway to W Calle De La Platta
Seventh Street: Robb Drive to Virginia Street

Saturday 8/3/2019

Slurry Seal
Eagle Canyon Drive: Pyramid Highway to W Calle De La Platta

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Eagle Canyon Drive: Pyramid Highway to W Calle De La Platta
South Meadows Parkway: Double R Boulevard to Cul-De-Sac

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

From Newlands Cir to Booth St

Starting July 11, 2019, at 6:00 a.m. through August 8, 2019:

  • California Ave/Keystone Ave Intersection will be closed to traffic in both directions in the construction zone.
  • Booth St is now open to traffic between Westfield Ave and Idlewild Dr.  and Business access off Booth St will be provided between California Ave and Westfield Ave during this  same time period.
  • Keystone Ave is now open to northbound and Southbound traffic from and to Foster.
  • Keystone Ave will not be accessible from California Ave.

Detours will be in place during construction. For safety reasons, there is no pedestrian access through California Ave from Newlands Cir to Booth St during construction.

In early August the California Ave/Keystone Ave intersection will reopen before Reno High School is back in session.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

New traffic signal at the intersection of N. Virginia and Lemmon Drive

Construction scheduled to begin July 24, 2019.
Potholing for utilities

Lane closures for traffic signal conduit installation.

 

SPARKS CONSOLIDATED 19-01 – 15TH STREET, FRANKLIN WAY, HULDA COURT, AND EL RANCHO DRIVE

Starting July 29, 2019, at 7:00 a.m. through Saturday, August 3, 2019:

  • 15th Street
    • From C Street to Prater Way open to traffic in both directions in the construction zone.  Construction crews will be working on concrete improvements and NV Energy crews will be lowering shallow gas services.
    • From Victorian Avenue to C Street closed to thru traffic.  Businesses and residences within the closure will be provided access from Victorian Avenue or the Alley on 16th Street between Victorian Avenue and C Street.  Traffic will be detoured at 15th Street to 16th to C Street or Victorian Avenue and to Victorian Plaza Circle to C Street or Victorian Avenue.  Construction crews will be working on utilities, median, and concrete improvements.
  •  C Street from 16th to 15th Street open to eastbound traffic only in the construction zone.  Traffic will be detoured at 15th Street to Victorian Avenue to 16th Street.  Construction crews will be working on utilities and concrete improvements.
  •  El Rancho Drive from G Street to Oddie Blvd will be open to traffic in both directions.  Traffic lanes will be moved over to the west half of the roadway for construction of concrete improvements on the east side. There will be two southbound and one northbound traffic lane.
  • Traffic on Franklin Way from East Greg Street to Spice Islands Drive will be open to southbound traffic only in the construction zone.  Northbound traffic will be detoured at Spice Islands Drive to Purina Way to East Greg Street.  Construction crews will be working on concrete improvements.
  • Hulda Court traffic will be impacted with driveway closures for concrete improvements.

Pedestrian detours will be in place during construction.  El Rancho Drive pedestrian detour will be from Oddie Blvd into Paradise Park, down to Elementary Drive, and south to G St using existing sidewalk on the west side El Rancho Dr.  For safety reasons, there is no pedestrian access on the east side of El Rancho Drive from G St to Oddie Blvd during construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Construction is occurring from Plumb Ln through Mt Rose St and on select side streets within the Midtown areas.

  • Between Plumb Ln and Mt Rose St traffic will be reduced to southbound only, northbound traffic will be detoured at Wells Ave to Vassar St.
  • The following side streets are also under construction and closed to through traffic, local access is provided:
    • Tahoe/Saint Lawrence (between Virginia St and Forest St)
    • Moran (between Virginia St and Center St)
    • East Taylor (between Virginia St and Center St)
    • Martin (between Virginia St and Haskell St)
    • Caliente (between Virginia St and Haskell St)

For the most up to date information on traffic control, please visit the Virginia Street Website.  

See weekly traffic report archive