Weekly Traffic Control Report

July 24, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Saturday 7/25

Micro-Surfacing
Kresge Lane: McCarran Boulevard to Watson Way
Bergin Way: Kresge Lane to end of pavement
Overmeyer Road: Bergin Way to Watson Way
Watson Way: Glendale Avenue to Dunn Circle

Monday 7/27

Micro-Surfacing
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Arrowcreek Parkway: Geyser Road to Thomas Creek Road
Kresge Lane: McCarran Boulevard to Watson Way
Bergin Way: Kresge Lane to end of pavement
Overmeyer Road: Bergin Way to Watson Way
Watson Way: Glendale Avenue to Dunn Circle
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge
Prototype Drive: Gateway Drive to Double R Boulevard
Second Street: Virginia Street to Giroux Street

Tuesday 7/28

Micro-Surfacing
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street

Wednesday 7/29

Micro-Surfacing
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Thursday 7/30

Micro-Surfacing
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Friday 7/31

Micro-Surfacing
Booth Street: California Avenue to Idlewild Drive
Third Street: Sierra Street to Vine Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Booth Street: California Avenue to Idlewild Drive
Third Street: Sierra Street to Vine Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between Spice Island Drive and railroad tracks during the hours of 7:00 AM to 6:00 PM.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/17 – 7/31

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.  Work is expected to be substantially complete by the end of September 2020.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Work includes construction of a new Bus RAPID Station on the east side of Virginia Street just south of Plumb Lane. Construction is scheduled to begin July 27, 2020, with substantial completion scheduled for the middle of October 2020.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction is in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

  • Intermittent shoulder closure at various intersections.
  • One lane closure, two-way traffic maintained.  Expect delays.
  • Construction work on the east side of Sun Valley Boulevard.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Center Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center Street to Liberty Street: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center Street to Liberty Street.
    • Northbound traffic can also use Mt Rose Street to Plumas Street to Liberty Street.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Avenue, Center Street, Plumas Street, or Haskell Street; which include:
    • La Rue Avenue, Martin Street, Taylor Street, Cheney Street, St Lawrence Avenue, Thoma Street, California Street, Moran Street, and Stewart Street.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • West Stadium Parking Garage to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 