Weekly Traffic Control Report

July 2, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 7/6/2020

Micro-Surfacing
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Tuesday 7/7/2020

Micro-Surfacing
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Wednesday 7/8/2020

Micro-Surfacing
West Calle De La Plata: Isidor Court to Eagle Canyon Drive
Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Thursday 7/9/2020

Micro-Surfacing
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
West Calle De La Plata: Isidor Court to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Friday 7/10/2020

Micro-Surfacing
Richard Springs Boulevard: Shelby Drive to Eagle Canyon Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Richard Springs Boulevard: Shelby Drive to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/6 – 7/15

No work planned, waiting on NDOT project on I580.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Wy between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
Crews currently working along the west side of Sun Valley Blvd (southbound).

  • Quartz to Leon:
    • one lane closure, two way traffic maintained. Expect delays.
  • Leon to Highland Ranch Pkwy:
    • one lane closure, two way traffic maintained. Expect delays.
  • Highland Ranch Pkwy:
    • shoulder closure. Signal timing reset. Expect delays.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

The project is substantially complete.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to CenterSt: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thomas St, California St, Moran St, and Stewart St.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between Center St and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.