Weekly Traffic Control Report

July 15, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Sunday 7/17

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Clean Water Way: McCarran Boulevard to Cor Soi
Mill Street: Rock Boulevard to McCarran Boulevard
Terminal Way: Mill Street to Plumb Lane
Peckham Lane: Virginia Street to Longley Lane

Monday 7/18

Micro-Surfacing
La Posada Drive: Cordoba Boulevard to End of Curb

Micro-Milling
Incline Way: Country Club Drive to Southwood Boulevard

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Mayberry Drive: Fourth Street to Hunter Lake Drive
Third Street: Sierra Street to Vine Street
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Ralston Street: University Terrace to Eleventh Street
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street

Tuesday 7/19

Micro-Surfacing
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Micro-Milling
Incline Way: Country Club Drive to Southwood Boulevard
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Mayberry Drive: Fourth Street to Hunter Lake Drive
Third Street: Sierra Street to Vine Street
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Ralston Street: University Terrace to Eleventh Street
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Circuit Court: Isidor Court. to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Wednesday 7/20

Micro-Surfacing
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Micro-Milling
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Mayberry Drive: Fourth Street to Hunter Lake Drive
Third Street: Sierra Street to Vine Street
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Ralston Street: University Terrace to Eleventh Street
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Thursday 7/21

Micro-Surfacing
La Posada Drive: Cordoba Boulevard to End of Curb
Peckham Lane: Virginia Street to Longley Lane

Micro-Milling
Terminal Way: Plumb Lane to Mill Street

Chip Sealing
Incline Way: Country Club Drive to Southwood Boulevard

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Mayberry Drive: Fourth Street to Hunter Lake Drive
Third Street: Sierra Street to Vine Street
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Ralston Street: University Terrace to Eleventh Street
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
La Posada Drive: Cordoba Boulevard to End of Curb
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way
Peckham Lane: Virginia Street to Longley Lane

Friday 7/22

Micro-Surfacing
Greenbrae Drive: El Rancho Boulevard to Rock Boulevard
Victorian Ave: Prater Way to El Rancho Boulevard
Peckham Lane: Virginia Street to Longley Lane

Micro-Milling
Terminal Way: Plumb Lane to Mill Street

Chip Sealing
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
La Posada Drive: Cordoba Boulevard to End of Curb
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Ct. to Academy Way
Greenbrae Drive: El Rancho Boulevard to Rock Boulevard
Victorian Avenue: Prater Way to El Rancho Boulevard
Peckham Lane: Virginia Street to Longley Lane

Saturday 7/23

Micro-Milling
Terminal Way: Plumb Lane to Mill Street

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin July 18, 2022 on Sharlands Avenue from Robb Drive to Mae Anne Avenue. Shoulder or lane closures are possible.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row between Apollo Way and Wyoming Avenue is closed to through traffic. Downhill traffic is detoured at Apollo Way back to Wyoming Avenue.
  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Apollo Way. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Expect delays during the morning and afternoon rush and consider alternate routes. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Intermittent lane closures on Pyramid Way.

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway. This week the contractor continues removing drives and sidewalk to be improved. Forming and pouring new sidewalk, curb and gutter will begin.

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 25, 2022.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street is on-going with other construction on the Mill Street project. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin July 2022.