Weekly Traffic Control Report

February 4, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin March 7, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Construction begins Monday, February 7, 2022.  Work will begin on the south side of Mill Street between McCarran Boulevard and Edison Way.  The two right eastbound lanes will be closed with eastbound traffic reduced to one lane.  Driveway access and access to Financial Boulevard will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks)

  • Construction work starting on Monday February 7, 2022 and expected to last until mid-March.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.

Phase 1: Pyramid Way to Sullivan Lane (Sparks)

  • Drivers may see intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Intermittent partial or full closures (detours) at 12th Street and Rock Boulevard intersections during daytime working hours.
  • Construction crews are doing underground work, excavating/forming/building retaining walls.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at Oddiewellsproject.com .

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled.  Construction will continue in March 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place.  Please use caution driving through the intersection.

See weekly traffic report archive