Weekly Traffic Control Report

February 18, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Winter suspension.
  • Construction will resume as soon as weather permits it.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin on a traffic signal at the intersection of Sharlands Ave. and Mae Anne Ave.  Potential lane and sidewalk closures will take place throughout February 2021.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Rock Blvd & Edison Way:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Mill St. & Lake St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center St. & 1st St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Center St. & Plaza St.:

  • Construction in progress with signal and new traffic equipment.
  • Lane and shoulder closures are expected throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Project is complete with roadway open to traffic. For the most up to date information on the project, please visit the Virginia Street Website

 