Weekly Traffic Control Report

February 15, 2019

4TH STREET AND PRATER WAY BUS RAPID TRANSIT PROJECT

Construction is in progress.

  • Intermittent closures will occur throughout the project to facilitate project closeout.
  • Expect lane shifts and minor traffic delays.

For current traffic information Click here.

 

TRAFFIC ENGINEERING SPOT 7 – PACKAGE 2

Work will include the following locations:

2/18 – 2/22
Mill St – Edison to McCarran:  WB lane closure

Signal equipment installation at:
Prater at Howard
Prater at Vista

Striping and signal work at:
Victorian Ave at 11th St and 14th St:  lane closures

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

The Utility Phase of the Virginia Street Bus RAPID Transit Extension Project is underway

  •  Traffic control is one-way southbound from Liberty St to Wells Ave.
  •  Northbound detour starts at Wells Ave and continues to Vassar St, Holcomb Ave and Center St.
  • There will be intermittent nonconsecutive side street closures.  During the closure, construction crews will have flaggers in place to assist customers to businesses in the area.
  • Remaining side streets within the midtown area are open and provide effective access to businesses and residences.
  • Watch for arrow boards and flaggers.

For more information, visit Virginia Street Website.

 

 

 

See weekly traffic report archive