INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139
Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout December.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Happy Holidays! Drive Safe!
Construction activities will resume January 3, 2023.
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- One traffic lane in each direction will be maintained along Oddie Boulevard
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824
Lane and shoulder closures will be in place.
SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881
Granite Construction Company is working in both the southbound and northbound lanes along Sparks Boulevard between Lincoln Way and Greg Street. Daytime single-lane closures will be in place in both the northbound and southbound directions between Greg Street and the I-80 eastbound off-ramp. These closures and associated work are weather dependent.
Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.
TE SPOT 10 – SOUTH PROJECT (ROUNDAVOUT INSTALLATION AT WOODLAND AVE/4TH STREET
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865
The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is underway. Traffic lane shoulder closures and detours will occur at various times throughout the project. Please observe all traffic controls, work zone speed limits and flaggers when construction is occurring. Weather permitting, underground utility relocation work will occur during the winter. There is no work anticipated for the rest of the year. The construction of the roundabout will begin in the spring of 2023.
TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139
Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time. Work resumes in January. Drivers should anticipate lane and shoulder closures.