Weekly Traffic Control Report

December 20, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 12/20
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane
Plumas Street: Plumb Lane to Marsh Avenue
Mt. Rose Street: Arlington Avenue to Plumas Street
Lakeside Drive: McCarran Boulevard to Plumb Lane

Monday 12/23  –  Friday 12/27
No work is scheduled.  Work will resume on Monday 12/30.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Lane closures with traffic control will be in effect to allow installation of pedestrian railing and curb modification.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Friday 12/20
Pullbox replacement on Baring Boulevard and Truckee Lane with occasional lane and shoulder closures.

Monday 12/23  –  Friday 12/27
No work during the holiday.

Monday 12/30  –  Tuesday 12/31
Pullbox replacement on Baring Boulevard and Truckee Lane with occasional lane and shoulder closures.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Friday 12/13  –  Monday 12/23
Occasional lane closure for signal equipment installation for a new traffic signal at the intersection of N Virginia Street and Lemmon Drive.

Traffic signal activation tentatively scheduled for 12/23.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Thursday 1/2
Construction of new traffic signal at Evans Avenue and Enterprise Road, possible lane and shoulder closures.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Red Rock Road at Silver Lake Boulevard Traffic Signal Installation
• Traffic Control in effect weekdays from 7 a.m. to 5 p.m. throughout December.
• Eastbound, westbound, southbound traffic lanes will be reduced to one lane for underground utility work.
• Expect flagger operation through the project for equipment and materials moving throughout the project.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Mt Rose St/Holcomb Ave to Martin St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Martin St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave or Haskell St, which include:
    • Pueblo St, Arroyo St, Caliente St, Vassar St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Starting in early 2020, traffic control will extend northward from Martin St towards Liberty St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

See weekly traffic report archive