Weekly Traffic Control Report

August 30, 2018

REGIONAL TRANSPORTATION COMMISSION TRAFFIC CONTROL REPORT

WEEKLY TRAFFIC CONTROL REPORT

August 30, 2018

2:00 PM PST

4TH STREET AND PRATER WAY BUS RAPID TRANSIT PROJECT
Construction is in progress.  For current traffic information Click here.

  • Traffic control and work zones will be in place and changing frequently, use caution and look for flaggers for direction.
  • Expect traffic delays.

 

2018 PREVENTIVE MAITENANCE PROGRAM
This schedule contains temperature sensitive work and may be modified if weather conditions are unfavorable.

Thursday 8/30

Pavement Crack Sealing
Del Webb Parkway (East): Somersett Ridge Parkway to Somersett Parkway
Del Webb Parkway (West): Somersett Ridge Parkway to Somersett Parkway
South Verdi Road: Bridge Street to Garson Road
Mae Anne Avenue: Lasalle Heights to Sharlands Avenue

Micro Surfacing
Vista Boulevard: Wingfield Springs Parkway to Hubble Drive (North)
Country Club Drive: Lakeshore Boulevard to Mt. Rose Highway (SR 431)

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
East Victorian Avenue: Stanford Way to McCarran Boulevard
Victorian Avenue: Pyramid Way to Stanford Way
Vista Boulevard: Wingfield Springs Parkway to Hubble Drive (North
Country Club Drive: Lakeshore Boulevard to Mt. Rose Highway (SR 431)

Friday 8/31

Pavement Crack Sealing
Del Webb Parkway (East): Somersett Ridge Parkway to Somersett Parkway
Del Webb Parkway (West): Somersett Ridge Parkway to Somersett Parkway
South Verdi Road: Bridge Street to Garson Road
Mae Anne Avenue: Lasalle Heights to Sharlands Avenue

Micro Surfacing
Greenbrae Drive: Rock Boulevard to 4th Street
South Stanford Way: Nugget Avenue to railroad tracks
Country Club Drive: Lakeshore Boulevard to Mt. Rose Highway (SR 431)

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
East Glendale Avenue: McCarran Boulevard to Meredith Way
Glen Carran Circle: Stanford Way (South) to Stanford Way (North)
Greenbrae Drive: Rock Boulevard to 4th Street
South Stanford Way: Nugget Avenue to railroad tracks
Country Club Drive: Lakeshore Boulevard to Mt. Rose Highway (SR 431)

Saturday 9/1 – Monday 9/3

No work is scheduled.

Tuesday 9/4

Pavement Crack Sealing
Longley Lane: Houston Drive to Rock Boulevard
Cashill Boulevard: McCarran Boulevard to Skyline Boulevard
Airway Drive: Neil Road to Longley Lane
Neil Road: Del Monte Lane to McCarran Boulevard
Del Monte Lane: Neil Road to View Crest Drive
Lakeside Drive: Huffaker Lane to north side park gate
Foothill Road: Virginia Street to Caribou Road
Carat Drive: Double Diamond Parkway to Steamboat Parkway
Rio Wrangler Parkway: Western Skies Drive to Steamboat Parkway
Steamboat Parkway: Damonte Ranch Parkway to Rio Wrangler Parkway
Wedge Parkway: Mount Rose Highway to Whites Creek Lane
Thomas Creek Road: Zolezzi Lane to Mount Rose Highway
Arrowcreek Parkway: Thomas Creek Road to private entrance gate
Eastlake Boulevard: cattle guard at north end to 1/3 mile north

Pavement Patching
Vassar Street: Virginia Street to Terminal Way
Mill Street: Lake Street to Rock Boulevard

Micro Surfacing
Rock Boulevard: Victorian Avenue to McCarran Boulevard
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Rock Boulevard: Victorian Avenue to McCarran Boulevard

Wednesday 9/5

Pavement Patching
Mill Street: Lake Street to Rock Boulevard
Ryland Street: Holcomb Avenue to Kirman Avenue

Micro Surfacing
Rock Boulevard: Victorian Avenue to McCarran Boulevard

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Rock Boulevard: Victorian Avenue to McCarran Boulevard
Vista Boulevard: Wingfield Parkway to North Hubble Drive

Thursday 9/6

Pavement Patching
Liberty Street: Arlington Avenue to Center Street
Center Street: Truckee River Bridge to Ninth Street

Micro Surfacing
Virginia Street: Business 395 to Stead Boulevard 

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Virginia Street: Business 395 to Stead Boulevard
Vista Boulevard: Wingfield Parkway to North Hubble Drive

Friday 9/7

Pavement Patching
Fifth Street: West Street to cul-de-sac
Ninth Street: Virginia Street to Shoshone Road

Micro Surfacing
Virginia Street: Business 395 to Stead Boulevard

Pavement Striping (NIGHT WORK: 7:00 PM to 5:00 AM)
Virginia Street: Business 395 to Stead Boulevard
Vista Boulevard: Wingfield Parkway to North Hubble Drive

 

ITS PROJECT – PHASE 2A
Work will include conduit and pull box installation at the following locations:

  • N Virginia St between Comstock and 15th St – Work complete
  • Wells St EB on ramp, shoulder area – Work complete
  • McCarran between Greg and Nugget – Night work begins week of 8/26-9/7; southbound slow lane closure.
  • McCarran between Prater and Baring – Day work begins week of 9/10-9/28; occasional shoulder closure northbound direction

 

SOUTHEAST CONNECTOR PROJECT
From Greg St to South Meadows Pkwy and Veterans Pkwy (5.5 miles)

  • The Southeast connector is open to traffic. The speed limit is 45 mph. Look for traffic signs and use caution as everyone becomes familiar with the new roadway, signalized intersections, and the multi-use path.
  • Intermittent shoulder closures and single lane closures in specific locations will occur over the next several months.  Details will be provided on this weekly report.
  • More information is available at the project website www.SouthEastConnector.com.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
The Utility Phase of the Virginia Street Bus RAPID Transit Extension Project is underway.

  • South Virginia St will be open to southbound traffic only from Liberty St to Plumb Ln.
  • Northbound traffic from Plumb Ln past Wells Ave will be closed.
  • Side streets within the midtown area are open and provide effective access to businesses and residences.
  • Watch for arrow boards and flaggers.

For more information visit Virginia Street Website.

 

 

 

See weekly traffic report archive