Weekly Traffic Control Report

August 22, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 8/23/2019
Slurry Seal
Zolezzi Lane: Arrowcreek Parkway to Thomas Creek Road

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Zolezzi Lane: Arrowcreek Parkway to Thomas Creek Road
Sparks Boulevard: Interstate-80 to E Prater Way
S Rock Boulevard: Glendale Avenue to Center of Truckee Bridge
S 15th Street: Hymer Avenue to Glendale Avenue
S 16th Street: Glendale Avenue to Hymer Avenue

Saturday 8/24/2019
Slurry Seal
Highland Ranch Parkway: Sun Valley Road to Pyramid Highway

Sunday 8/25/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Highland Ranch Parkway: Sun Valley Road to Pyramid Highway
S Rock Boulevard: Glendale Avenue to Center of Truckee Bridge
S 15th Street: Hymer Avenue to Glendale Avenue
S 16th Street: Glendale Avenue to Hymer Avenue
Zolezzi Lane: Arrowcreek Parkway to Thomas Creek Road

Monday 8/26/2019
Slurry Seal
Lemmon Drive: US 395 to North Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Lemmon Drive: US 395 to North Virginia Street
Zolezzi Lane: Arrowcreek Parkway to Thomas Creek Road
Sparks Boulevard: Interstate-80 to E Prater Way

Tuesday 8/27/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Sparks Boulevard: Interstate-80 to E Prater Way

Wednesday 8/28/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Sparks Boulevard: Interstate-80 to E Prater Way
Highland Ranch Parkway: Sun Valley Road to Pyramid Highway

Thursday 8/29/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Highland Ranch Parkway: Sun Valley Road to Pyramid Highway
Lemmon Drive: US 395 to North Virginia Street

Friday 8/30/2019
NO WORK SCHEDULED

Saturday 8/31/2019
NO WORK SCHEDULED

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

The project is now substantially complete, however the contractor is finishing minor work that may require lane closures. The west bound ramp from California to Keystone will be closed Saturday August for landscape work.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

New traffic signal at the intersection of N. Virginia and Lemmon Drive

Lane closures for rough grading on Heindel Rd. and shoulder closures on N. Virginia.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

The project will involve pavement rehabilitation and reconstruction on State Street from Virginia Street to Sinclair Street, First Street from Center Street to Lake Street, and Lake Street from the southern approach of the Truckee River bridge to First Street.

For the safety of you and your vehicle, parking on the street will be prohibited within the construction zones from 7am-6pm. For additional street parking, a nearby side street must be used; please adhere to the “no parking” restrictions. Access will be maintained to businesses for the duration of the project; however, we will coordinate driveway closures individually as business accesses are being reconstructed. There is also a potential for short traffic delays during asphalt removal and paving operations but we will do our best to get traffic to and from residences or businesses as quickly and safely as possible.

During construction, the RTC RIDE bus service (Sierra Spirit and Routes 1, 5, 9, 13, 14, and 19) may be temporarily impacted within the project area. However, any detours or changes to bus stop locations will be noted in advance at the affected bus stop.

Starting August 26, 2019, at 5:00 a.m. through August 30, 2019 at 6:00 p.m.:

  • State Street
    • From Virgina to Sinclair closed to thru traffic. Construction crews will be working on concrete improvements on the north side of the roadway.
    • Businesses and residences within the closure will be provided eastbound access from Virginia and Center. Westbound traffic will be detoured at Sinclair to Liberty to Center.
    • Pedestrian detours will be in place during construction.
  • First Street
    • From Center to Lake open to westbound traffic only. Eastbound traffic will be detoured at Center to Second to Lake Street. Construction crews will be working on concrete imporvements on the north and south side of the roadway.
    • Pedestrian detours will be in place during construction.
  • Lake Street
  • From Mill Street to Second Street open to traffic in both directions in the construction zone. 

 

RENO CONSOLIDATED 19-02 Project – North Hills Boulevard from Golden Valley Road to Buck Drive and The intersection of Hunter Lake Drive at Foster Drive.

North Hills Blvd:

  • Demolition, sidewalk and drainage work with one lane closure.
  • Two-way traffic maintained at all times.
  • Please share the road to bicyclists.
  • From Golden Valley to Beckwourth, one lane closure, two lanes open with two-way traffic.
  • From Beckwourth to Buck, one lane closure, with flaggers to direct traffic one way at the time.

Hunter Lake/Foster Dr:

  • Message boards will be up on Monday August 26th.
  • Construction to start on Tuesday September 3rd.

 

RENO CONSOLIDATED 19-03 Project – Sierra Highlands Drive, Colbert Drive, Hammill Lane, Ralston Street, and Ohm Place.

Ralston Street between University Terrace and 11th Street; Starting August 5th at 7:00 am thru October 3rd construction will be in progress with concrete removal and replacement for sidewalk and curb/gutters; roadway reconstruction. Traffic controls in place along Ralston Street.

For the safety of you and your vehicle, parking on the street will be prohibited within the Ralston Street construction zones from 7am-7pm, Monday through Friday from August 5th to the first of October. During construction, we will also provide access for trash pickup on Tuesdays – please place your Green Waste cans out on Tuesday for pickup. For additional street parking, a nearby side street must be used; please adhere to the “no parking” restrictions.

 

SPARKS CONSOLIDATED 19-01 – 15TH STREET, FRANKLIN WAY, HULDA COURT, AND EL RANCHO DRIVE

Starting August 26, 2019, at 7:00 a.m. through Saturday August 31, 2019:

  • 15th Street
    • From C Street to Prater Way open to traffic in both directions in the construction zone. Construction crews are finishing concrete improvements and doing clean-up for the Rib Cook-off.El Rancho Drive from G Street to Oddie Blvd will be open to traffic in both directions. Traffic lanes will shift for construction of concrete improvements on the west side of the roadway.
  • Traffic on Franklin Way from East Greg Street to Spice Islands Drive will be open to northbound traffic only in the construction zone. Southbound traffic will be detoured at Greg Street to Purina Way to Spice Island Drive. Construction crews will be working on concrete improvements.

Pedestrian detours will be in place during construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Construction is occurring from Plumb Ln through Mt Rose St and on select side streets within the Midtown areas.

  • Between Plumb Ln and Mt Rose St traffic will be reduced to southbound only, northbound traffic will be detoured at Regency Way to Vassar St.
  • The following side streets are also under construction and closed to through traffic, local access is provided:
    • Tahoe/Saint Lawrence (between Virginia St and Forest St)
    • Moran (between Virginia St and Center St)
    • East Taylor (between Virginia St and Center St)
    • Martin (between Virginia St and Haskell St)
    • Arroyo (between Virginia St and Haskell St)
    • Cheney (between Virginia St and Center St)

For the most up to date information on traffic control, please visit the Virginia Street Website.  

 

See weekly traffic report archive