Weekly Traffic Control Report

August 25, 2023

2023 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
**Note: This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Sunday 8/27/2023
Pavement Striping 7pm – 7am
Sparks Boulevard: Baring Boulevard to Pyramid Highway
Disc Drive: Sparks Boulevard to Vista Boulevard
Longley Lane: Virginia Street to Rock Boulevard
Wells Avenue: Virginia Street to Seventh Street
Various Project Streets – 2nd Coat Striping

Monday 8/28/2023
Pavement Striping 7pm – 7am
Sparks Boulevard: Baring Boulevard to Pyramid Highway
Disc Drive: Sparks Boulevard to Vista Boulevard
Longley Lane: Virginia Street to Rock Boulevard
Wells Avenue: Virginia Street to Seventh Street
Various Project Streets – 2nd Coat Striping

Tuesday 8/29/2023
Pavement Striping 7pm – 7am 
Sparks Boulevard: Baring Boulevard to Pyramid Highway
Disc Drive: Sparks Boulevard to Vista Boulevard
Longley Lane: Virginia Street to Rock Boulevard
Wells Avenue: Virginia Street to Seventh Street
Various Project Streets – 2nd Coat Striping

Wednesday 8/30/2023
Pavement Striping 7pm – 7am
Sparks Boulevard: Baring Boulevard to Pyramid Highway
Disc Drive: Sparks Boulevard to Vista Boulevard
Longley Lane: Virginia Street to Rock Boulevard
Wells Avenue: Virginia Street to Seventh Street
Various Project Streets – 2nd Coat Striping

Thursday 8/31/2023
Pavement Striping 7pm – 7am
Sparks Boulevard: Baring Boulevard to Pyramid Highway
Disc Drive: Sparks Boulevard to Vista Boulevard
Longley Lane: Virginia Street to Rock Boulevard
Wells Avenue: Virginia Street to Seventh Street
Various Project Streets – 2nd Coat Striping

Friday 9/1/2023
Pavement Striping 7pm – 7am
Sparks Boulevard: Baring Boulevard to Pyramid Highway
Disc Drive: Sparks Boulevard to Vista Boulevard
Longley Lane: Virginia Street to Rock Boulevard
Wells Avenue: Virginia Street to Seventh Street
Various Project Streets – 2nd Coat Striping

4TH STREET AND WOODLAND AVENUE ROUNDABOUT INSTALLATION
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

  • Construction of the eastbound travel lanes and roundabout is in progress.
  • Intermittent flagging operations at this intersection could cause delays of up to 20 minutes.
  • Normal construction hours are 7:00 a.m. – 5:00 p.m., Monday through Friday.
  • Effective August 12th through late September work will take place on Saturdays from 7:00 a.m. to 5:00 p.m. Additionally, 24-hour operations will occur between August 28th through late September, Monday morning at 7:00 a.m. to Saturday Morning 7:00 a.m.

Mesa Park Road is closed again and will remain closed through Phase 2 of construction. This closure has been extended through late September while construction of the following occurs:

  • 4th Street eastbound lanes and islands
  • Southern portion of the roundabout

The project is anticipated to be completed by Fall of 2023.
For more information, visit https://www.4th-woodland-roundabout.com/

ARROWCREEK PARKWAY REHABILITATION PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844

Lane reductions will be in place on Arrowcreek Parkway, Damonte Ranch Parkway, and S. Virginia Street in the project area as final striping and signal work take place.

CALIFORNIA AVENUE RECONSTRUCTION-NEWLANDS CIRCLE TO ARLINGTON PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Paving has been completed and the contractor is completing final activities related to raising utilities, striping and landscaping.

HOLCOMB AVENUE REHABILITATION PROJECT
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Project reached substantial completion.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction crews will be finishing landscape work and final striping.
  • Road is expected to be open with no restrictions by Friday September 1st.

Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):

  • Construction crews are working on the south side of Oddie Boulevard installing underground conduit for street lighting, storm drain and retaining curb.
  • Two-way traffic will remain in place on the north side of Oddie Boulevard.

Phase 3 – east of US 395 Ramps to Sutro Street (Reno):

  • Paving operations in place. US 395 ramp closures during night time only (9:00 p.m. – 5:00 a.m.) from September 5th– 7th.
  • Two-way traffic will remain in place on the south side of Oddie Boulevard.
  • The northern half of Oddie Boulevard and Montello Street intersection will be closed through Friday, September 29th.  Detours are in place.

Phase 4 – Sutro Street to I-80 Ramps (Reno):

  • Ongoing underground work (storm drain installation).
  • Intermittent traffic lane shifts during construction hours.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

 