Weekly Traffic Control Report

April 10, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  • East 9th Street and Montello Street Intersection
  • Valley Road and Sadleir Way Intersection
  • Sutro Street and Haddock Drive Intersection
  • Lemmon Drive and North Virginia Street Intersection
  • Kirman Avenue and Moran Street Intersection
  • Mill Street and Sunshine Lane Intersection
  • Locust Street and Colorado River Boulevard Intersection
  • Grove Street and Yori Way Intersection
  • Hunter Lake Drive and Foster Drive Intersection
  • Sierra Center Parkway at Sierra Town Center
  • York Way and 4th Street Intersection
  • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/13 – 4/16

Patching on Baring and Sparks Blvd. Single lane closures during paving operations.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/13 – 4/28

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 13 – April 28: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/13-4/20                      

No work until 4/16

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
    • Northbound traffic is detoured via side streets to Center St to Liberty St.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website.  