July 31 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 7/31/2020

Micro-Surfacing
Sierra Street: 11th Street to 3rd Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: 11th Street to 3rd Street
Prototype Drive: Gateway Drive to Double R Boulevard
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Sunday 8/2/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to End
Legends “I”: George Ferris Drive to Scheels Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to End
Legends “I”: George Ferris Drive to Scheels Drive

Monday 8/3/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
George Ferris Drive: Lincoln Way East Round-A-Bout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
George Ferris Drive: Lincoln Way East Round-A-Bout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Tuesday 8/4/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends Bay: Lincoln Way West Round-A-Bout to End

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends Bay: Lincoln Way West Round-A-Bout to End
Sierra Street: 11th Street to 3rd Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Wednesday 8/5/2020

Pavement Patching
Watson Way: Kresge Lane to Glendale Avenue

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: Westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to East End of Pavement
Watson Way: Kresge Lane to Glendale Avenue

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: Westbound I-80 Ramps to Brierley Way
Salomon Circle: Vista Boulevard to East End of Pavement
Watson Way: Kresge Lane to Glendale Avenue
Sierra Street: 11th Street to 3rd Street

Thursday 8/6/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Kietzke Lane: South End Cul-De-Sac to Virginia Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: South End Cul-De-Sac to Virginia Street
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to End
Legends “I”: George Ferris Drive to Scheels Drive

Friday 8/7/2020

Micro-Surfacing (Night Work: 7:00 PM to 7:00 AM)
Kietzke Lane: South End Cul-De-Sac to Virginia Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: South End Cul-De-Sac to Virginia Street
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends “C”: Scheels Drive to End
Legends “I”: George Ferris Drive to Scheels Drive
George Ferris Drive: Lincoln Way East Round-A-Bout to Legends Bay
Marina Gateway Drive: East Lincoln Way to East Prater Way

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between Spice Island Drive and railroad tracks during the hours of 7:00 AM to 6:00 PM.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/31 8/15

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.  Work is expected to be substantially complete by the end of September 2020.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Work includes construction of a new Bus RAPID Station on the east side of Virginia Street just south of Plumb Lane. Construction is scheduled to begin July 27, 2020, with substantial completion scheduled for the middle of October 2020.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

    • Intermittent shoulder closure at various intersections.
    • One lane closure, two-way traffic maintained. Expect delays.
    • Construction work on the east side of Sun Valley Boulevard. One lane closure from Quartz to Leon Dr.
    • 7th Ave intersection:
      • Intermittent lane closure with detours.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Center Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty Street: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center Street to Liberty Street.
    • Northbound traffic can also use Mt Rose Street to Plumas Street to Liberty Street.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Avenue, Center Street, Plumas Street, or Haskell Street; which include:
    • La Rue Avenue, Martin Street, Taylor Street, Cheney Street, St Lawrence Avenue, Thoma Street, California Street, Moran Street, and Stewart Street.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street (Bridge over I-80) is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • 15th Street to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
  • 15th Street to 8th Street: traffic is reduced to one-lane in each direction. Some on-street parking is closed.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

 

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 24, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Saturday 7/25

Micro-Surfacing
Kresge Lane: McCarran Boulevard to Watson Way
Bergin Way: Kresge Lane to end of pavement
Overmeyer Road: Bergin Way to Watson Way
Watson Way: Glendale Avenue to Dunn Circle

Monday 7/27

Micro-Surfacing
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Arrowcreek Parkway: Geyser Road to Thomas Creek Road
Kresge Lane: McCarran Boulevard to Watson Way
Bergin Way: Kresge Lane to end of pavement
Overmeyer Road: Bergin Way to Watson Way
Watson Way: Glendale Avenue to Dunn Circle
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge
Prototype Drive: Gateway Drive to Double R Boulevard
Second Street: Virginia Street to Giroux Street

Tuesday 7/28

Micro-Surfacing
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street

Wednesday 7/29

Micro-Surfacing
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Thursday 7/30

Micro-Surfacing
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Sierra Highlands Drive: Idlebury Way to Seventh Street
Summit Ridge Drive: Westcliff Lane to Fourth Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive

Friday 7/31

Micro-Surfacing
Booth Street: California Avenue to Idlewild Drive
Third Street: Sierra Street to Vine Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Booth Street: California Avenue to Idlewild Drive
Third Street: Sierra Street to Vine Street
Mae Anne Avenue: Sharlands Avenue to Robb Drive

 

GREG STREET REHABILITATION
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Boulevard and the railroad tracks. The reconstruction is expected to be completed by mid-August 2020.

Traffic is reduced to one-lane in each direction between Spice Island Drive and railroad tracks during the hours of 7:00 AM to 6:00 PM.

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/17 – 7/31

No work planned, waiting on NDOT project on I-580.

 

LAKESIDE DRIVE REHABILITATION
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Construction is in progress on Lakeside Drive between Evans Creek Drive and McCarran Boulevard.  Work is expected to be substantially complete by the end of September 2020.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

Work includes construction of a new Bus RAPID Station on the east side of Virginia Street just south of Plumb Lane. Construction is scheduled to begin July 27, 2020, with substantial completion scheduled for the middle of October 2020.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction is in progress on E Prater Way between McCarran Boulevard and Sparks Boulevard. The project is expected to take about six months to complete.

Two-way traffic will continue within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction is in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.

  • Intermittent shoulder closure at various intersections.
  • One lane closure, two-way traffic maintained.  Expect delays.
  • Construction work on the east side of Sun Valley Boulevard.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Lane to Center Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center Street to Liberty Street: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center Street to Liberty Street.
    • Northbound traffic can also use Mt Rose Street to Plumas Street to Liberty Street.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Avenue, Center Street, Plumas Street, or Haskell Street; which include:
    • La Rue Avenue, Martin Street, Taylor Street, Cheney Street, St Lawrence Avenue, Thoma Street, California Street, Moran Street, and Stewart Street.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street is closed.
    • Detours are in place. Southbound detour is to Sierra Street, northbound detour is to Center Street.
  • West Stadium Parking Garage to Sierra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Sierra Street and 15th Street.
  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia Street.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 17, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 7/20/2020

Micro-Surfacing
Double R Boulevard: South Meadows Parkway to Longley Lane
Sinclair Street: Holcomb Avenue to Mill Street
Lake Street: Mill Street to Sixth Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Sinclair Street: Holcomb Avenue to Mill Street
Lake Street: Mill Street to Sixth Street
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Wedekind Road: Lund Lane to Malapi Way
Merchant Street: Sullivan Lane to Commerce Street
Howard Drive: Nichols Boulevard to Sparks Boulevard

Tuesday 7/21/2020

Micro-Surfacing
Double R Boulevard: South Meadows Parkway to Longley Lane
Commercial Row: Arlington Avenue to Lake Street
Fifth Street: West Street to Virginia Street

Traffic Signal Loop Replacement
Double R Boulevard: Amston Lane to Double Diamond Parkway

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Commercial Row: Arlington Avenue to Lake Street
Fifth Street: West Street to Virginia Street

Wednesday 7/22/2020

Micro-Surfacing
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge
Sinclair Street: Holcomb Avenue to Mill Street
Lake Street: Mill Street to Sixth Street

Thursday 7/23/2020

Micro-Surfacing
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Second Street: Virginia Street to Giroux Street
Commercial Row: Arlington Avenue to Lake Street
Fifth Street: West Street to Virginia Street

Friday 7/24/2020

Micro-Surfacing
Prototype Drive: Gateway Drive to Double R Boulevard
Second Street: Virginia Street to Giroux Street

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Double R Boulevard: South Meadows Parkway to Longley Lane
Court Street: Arlington Avenue to Virginia Street
Washington Street: Second Street to I-80 Bridge
Prototype Drive: Gateway Drive to Double R Boulevard
Second Street: Virginia Street to Giroux Street

 

GREG STREET REHABILITATION PROJECT
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction is in progress on Greg Street between McCarran Blvd and the railroad tracks. The reconstruction is expected to be completed by mid-August.

Starting on Monday, July 20th, traffic is reduced to one-lane in each direction between Spice Island Drive and railroad tracks during the hours of 7:00 AM to 6:00 PM

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/17 – 7/31

No work planned, waiting on NDOT project on I580.

 

LAKESIDE DRIVE REHABILITATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

 Construction is scheduled to start on Lakeside Drive between Evans Creek Drive and McCarran Blvd. on Monday, 7/20/20. This will be a roadway reconstruction, some curb/gutter and driveway replacements, and ADA pedestrian ramp improvements.   This is a 50 working day contract and should be substantially complete the end of September 2020.

 

PARK LANE RAPID STATION PROJECT
RTC Project Manager, Warren Call, P.E. – (775)335-1881

This will be the construction of a new Bus RAPID Station on the east side of Viginia Street just south of Plumb Lane. Construction is scheduled to start 7/27/20 and a 60 day working day contract with substantial completion scheduled for the first of October 2020.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Way between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb&Gutter, Sidewalk and Drainage improvements.

  • Intermittent shoulder closure and one lane closure, two way traffic maintained. Expect delays.
  • Middle Fork to Leon Dr – ROAD CLOSURE: 7/20 – 7/24
    • DETOUR:  Northbound traffic along Sun Valley Blvd will be detoured to take the right at Middle Fork, left at Smokey Canyon, left at Leon and finally right on Sun Valley Blvd to continue north.
    • DETOUR: Southbound traffic will take the right at Leon Dr, left at Middle Fork Dr, left at Amargosa, left at Middle Fork Dr and finally right at Sun Valley Blvd to continue south.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to CenterSt: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street is closed.
    • Detours are in place. Southbound detour is to Sierra St, northbound detour is to Center St.
  • West Stadium Parking Garage to Serra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Searra St and 15th St.
  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 9, 2020

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 7/13/2020

Micro-Surfacing
Howard Drive: Nichols Boulevard to Sparks Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Merchant Street: Sullivan Lane to Commerce Street
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Nugget Avenue: McCarran Boulevard to End of Pavement
Nugget Court: Nugget Avenue to Cul-de-Sac
15th Street: Victorian Avenue to C Street
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Watson Way: Glendale Avenue to Dunn Circle
Bergin Way: Kresge Lane to End of Pavement
Overmeyer Road: Bergin Way to Watson Way
Kresge Lane: McCarran Boulevard to Watson Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Richard Springs Boulevard: Shelby Drive to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Tuesday 7/14/2020

Micro-Surfacing
Howard Drive: Nichols Boulevard to Sparks Boulevard
Springland Drive: Sparks Boulevard to Baring Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Merchant Street: Sullivan Lane to Commerce Street
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Nugget Avenue: McCarran Boulevard to End of Pavement
Nugget Court: Nugget Avenue to Cul-de-Sac
15th Street: Victorian Avenue to C Street
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Watson Way: Glendale Avenue to Dunn Circle
Bergin Way: Kresge Lane to End of Pavement
Overmeyer Road: Bergin Way to Watson Way
Kresge Lane: McCarran Boulevard to Watson Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Howard Drive: Nichols Boulevard to Sparks Boulevard
Springland Drive: Sparks Boulevard to Baring Boulevard
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Wednesday 7/15/2020

Micro-Surfacing
Wedekind Road: Lund Lane to Malapi Way
Merchant Street: Sullivan Lane to Commerce Street
Greenbrae Drive: Orovada Street El Rancho Boulevard
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Traffic Signal Loop Replacement
El Rancho Drive: Wedekind Road to McCarran Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Merchant Street: Sullivan Lane to Commerce Street
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Nugget Avenue: McCarran Boulevard to End of Pavement
Nugget Court: Nugget Avenue to Cul-de-Sac
15th Street: Victorian Avenue to C Street
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Watson Way: Glendale Avenue to Dunn Circle
Bergin Way: Kresge Lane to End of Pavement
Overmeyer Road: Bergin Way to Watson Way
Kresge Lane: McCarran Boulevard to Watson Way

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Wedekind Road: Lund Lane to Malapi Way
Merchant Street: Sullivan Lane to Commerce Street
Greenbrae Drive: Orovada Street El Rancho Boulevard

Thursday 7/16/2020

Micro-Surfacing
El Rancho Drive: Wedekind Road to McCarran Boulevard
Orovada Street: Silverada Boulevard to Greenbrae Drive
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
El Rancho Drive: Wedekind Road to McCarran Boulevard
Orovada Street: Silverada Boulevard to Greenbrae Drive
Commerce Street: Rock Boulevard to Oddie Boulevard Frontage Road
Howard Drive: Nichols Boulevard to Sparks Boulevard
Springland Drive: Sparks Boulevard to Baring Boulevard

Friday 7/17/2020

Micro-Surfacing
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Pembroke Drive: Piping Rock Drive to East Parkway Drive
Eastlake Boulevard: Coyote Drive to Duck Hill Road
Wedekind Road: Lund Lane to Malapi Way
Merchant Street: Sullivan Lane to Commerce Street
Greenbrae Drive: Orovada Street El Rancho Boulevard
Howard Drive: Nichols Boulevard to Sparks Boulevard

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/9 – 7/15

No work planned, waiting on NDOT project on I580.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Wy between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

GREG STREET REHABILITATION PROJECT
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Construction to begin on Greg Street between McCarran Blvd and the railroad tracks beginning Sunday night July 12th. The reconstruction is expected to take five (5) weeks to complete.

During the nighttime hours of 7:00 PM to 5:00 AM, traffic is reduced to one-lane in each direction between McCarran Boulevard and Spice Island Drive.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
Crews currently working along the west side of Sun Valley Blvd (southbound).

  • Quartz to Leon:
    • one lane closure, two way traffic maintained. Expect delays.
  • Leon to Highland Ranch Pkwy:
    • one lane closure, two way traffic maintained. Expect delays.
  • Highland Ranch Pkwy:
    • shoulder closure. Signal timing reset. Expect delays.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to CenterSt: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

North Virginia Street:

  • Maple Street to 8th Street: North Virginia Street is closed.
    • Detours are in place. Southbound detour is to Sierra St, northbound detour is to Center St.
  • West Stadium Parking Garage to Serra Street: traffic is reduced to northbound direction only.
    • Southbound traffic is detoured to Searra St and 15th St.
  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between the I-80 off ramp and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

July 2, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 7/6/2020

Micro-Surfacing
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Tuesday 7/7/2020

Micro-Surfacing
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Wednesday 7/8/2020

Micro-Surfacing
West Calle De La Plata: Isidor Court to Eagle Canyon Drive
Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Thursday 7/9/2020

Micro-Surfacing
West Calle De La Plata: Isidor Court to Eagle Canyon Drive

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Washington Street: Second Street to Sixth Street
Commercial Row: Arlington Avenue to Lake Street
Lake Street: Mill Street to Sixth Street
Second Street: Virginia Street to Girioux Street
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street
Court Street: Arlington Avenue to Virginia Street
Arlington Avenue: Skyline Boulevard to Truckee River Bridge

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
West Calle De La Plata: Isidor Court to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

Friday 7/10/2020

Micro-Surfacing
Richard Springs Boulevard: Shelby Drive to Eagle Canyon Drive

Pavement Striping (Night Work: 7:00 PM to 5:00 AM)
Richard Springs Boulevard: Shelby Drive to Eagle Canyon Drive
Wingfield Hills Road: Rolling Meadows Drive to Vista Boulevard

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

7/6 – 7/15

No work planned, waiting on NDOT project on I580.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Wy between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
Crews currently working along the west side of Sun Valley Blvd (southbound).

  • Quartz to Leon:
    • one lane closure, two way traffic maintained. Expect delays.
  • Leon to Highland Ranch Pkwy:
    • one lane closure, two way traffic maintained. Expect delays.
  • Highland Ranch Pkwy:
    • shoulder closure. Signal timing reset. Expect delays.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

The project is substantially complete.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to CenterSt: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Center St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thomas St, California St, Moran St, and Stewart St.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: traffic is reduced to one-lane in each direction.
  • 8th Street: northern shoulder is closed between Center St and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

June 26, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 6/29
Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Greg Street: Rock Boulevard to McCarran Boulevard
East Greg Street: Stanford Way to Sparks Boulevard

Tuesday 6/30
Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Sierra Street: Virginia Street to California Avenue

Wednesday 7/1
Micro-Surfacing
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street

Thursday 7/2
Micro-Surfacing
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Fifth Street: West Street to Virginia Street
Overmeyer Road: Bergin Way to Watson Way
Bergin Way: Kresge Lane to End of Pavement
Watson Way: Glendale Avenue to Dunn Circle
Kresge Lane: McCarran Boulevard to Watson Way

Friday 7/3
NO WORK SCHEDULED

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/22 – 7/10
No work planned, waiting on NDOT project on I580.

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction in progress on E Prater Wy between McCarran Blvd and Sparks Blvd. The project is expected to take about six months to complete.

Two-way traffic continues within the construction zone, with one lane in each direction.

The RTC appreciates the community’s patience during the construction process.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress.  Crews currently working along the west side of Sun Valley Blvd.

  • 7th Ave and Middle Fork: one lane closure, two way traffic maintained. Expect delays.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

The project is substantially complete.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Vassar St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar St to Liberty St: traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.  Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 8th St: traffic is reduced to one-lane in each direction.
  • 8th St: northern shoulder is closed between Center St and North Virginia St.

For the most up to date information on traffic control, please visit the Virginia Street Website

 

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

June 22, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Sunday 6/21/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: I-80 Overpass to Brierley Way
George Ferris Drive: Lincoln Way Round-A-Bout to Legends Bay
East Lincoln Way: Sparks Boulevard to McCarran Boulevard
Legends Way: Scheels Drive to George Ferris Drive
Legends Bay: Lincoln Way Round-A-Bout to End of Pavement

Monday 6/22/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Kietzke Lane: Neil Kietzke Round-A-Bout to Virginia Street
Battle Born Way: Galletti Way to Victorian Avenue
2nd Street: Virginia Street to Girioux Street
Lake Street: Mill Street to Sixth Street

Tuesday 6/23/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Mill Street: Lake Street to Terminal Way
Sinclair Street: Holcomb Avenue to Mill Street

Wednesday 6/24/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Court Street: Arlington Avenue to Virginia Street
Commercial Row: Arlington Avenue to Lake Street

Thursday 6/25/2020

Pavement Crack Sealing (Night Work: 7:00 PM to 5:00 AM)
Lake Street: Mill Street to Sixth Street
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Sierra Street: Eleventh Street to California Avenue

 

ITS PHASE 2B
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/15 – 7/1
No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/15 – 6/22
Q&D has remaining concrete work at Mill and Kirman and Keystone at 7th.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Vassar Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar Street to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: is reduced to one-lane in each direction
  • 8th Street: northern shoulder is closed between Center Street and North Virginia Street

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVE TO HIGHLAND RANCH PKWY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction in progress.  Crews currently working along the west side of Sun Valley Blvd.

  • 7th Ave and Middle Fork: one lane closure, two way traffic maintained. Expect delays.

 

 

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

June 11, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Saturday 6/13/2020

Pavement Patching
Golden Valley Road: Marlin Drive to Opal Station Drive
Seventh Avenue: Golden Valley Drive to Sun Valley Boulevard

Monday 6/15/2020

Pavement Patching
Sierra Street: Virginia Street to California Avenue
2nd Street: Virginia Street to Girioux Street
Kietzke Lane: Neil Kietzke Round-A-Bout to Virginia Street

Pavement Crack Sealing
Golden Valley Road: Marlin Drive to Opal Station Drive
Seventh Avenue: Golden Valley Drive to Sun Valley Boulevard
Tanberg Drive: Seventh Avenue to Mineral Avenue

Tuesday 6/16/2020

Pavement Crack Sealing
Golden Valley Road: Marlin Drive to Opal Station Drive
Seventh Avenue: Golden Valley Drive to Sun Valley Boulevard
Tanberg Drive: Seventh Avenue to Mineral Avenue
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Sierra Highlands Drive: Idelbury Drive to Seventh Street

Wednesday 6/17/2020

Pavement Crack Sealing
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Sierra Highlands Drive: Idelbury Drive to Seventh Street
Springland Drive: Sparks Boulevard to Baring Boulevard
Howard Drive: Prater Way to Sparks Boulevard

Thursday 6/18/2020

Pavement Patching (NIGHT WORK: 5:00 PM to 6:00 AM)
Marina Gateway: Lincoln Way to Prater Way
Greg Street: Rock Boulevard to McCarran Boulevard
East Greg Street: Stanford Way to Sparks Boulevard
Brierley Way: Lillard Way to Vista Boulevard
Vista Boulevard: I-80 Overpass to Brierley Way
George Ferris Drive: Lincoln Way Round-A-Bout to Legends Bay
East Lincoln Way: Sparks Boulevard to McCarran Boulevard

Pavement Crack Sealing
Springland Drive: Sparks Boulevard to Baring Boulevard
Howard Drive: Prater Way to Sparks Boulevard
El Rancho Drive: Wedekind Road to McCarran Boulevard
Wedekind Road: Sullivan Lane to McCarran Boulevard

Friday 6/19/2020

Pavement Crack Sealing
El Rancho Drive: Wedekind Road to McCarran Boulevard
Wedekind Road: Sullivan Lane to McCarran Boulevard
Greenbrae Drive: Orovada Street to El Rancho Boulevard
Merchant Street: Sullivan Lane to Commerce Street
Orovada Street: Greenbrae Drive to Sparks City Limits

 

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/15 – 7/1
No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

6/15 – 6/22
Q&D has remaining concrete work at Mill and Kirman and Keystone at 7th.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Vassar Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar Street to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: is reduced to one-lane in each direction
  • 8th Street: northern shoulder is closed

For the most up to date information on traffic control, please visit the Virginia Street Website

 

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

June 4, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 6/8/2020

Pavement Patching
Pembroke Drive: Piping Rock Drive to E. Parkway Drive
Greg Street: Rock Boulevard to McCarran Boulevard
Overmeyer Road: Bergin Way to Watson Way
Bergin Way: Kresge Lane to End of Pavement
Watson Way: Glendale Avenue to Dunn Circle

Pavement Crack Sealing
West Calle De La Plata: Pyramid Highway to Eagle Canyon Drive

Tuesday 6/9/2020

Pavement Patching
Springland Drive: Sparks Boulevard to Baring Boulevard
Greenbrae Drive: Orovada Street to El Rancho Boulevard

Pavement Crack Sealing
West Calle De La Plata: Pyramid Highway to Eagle Canyon Drive
Richard Springs Boulevard: Eagle Canyon Drive to Shelby Drive

Wednesday 6/10/2020

Pavement Patching
Greenbrae Drive: Orovada Street to El Rancho Boulevard
Orovada Street: Greenbrae Drive to Sparks City Limits
El Rancho Drive: Wedekind Road to McCarran Boulevard

Pavement Crack Sealing
Richard Springs Boulevard: Eagle Canyon Drive to Shelby Drive
Wingfield Hills Road: Vista Boulevard to Rolling Meadows Drive

Thursday 6/11/2020

Pavement Patching
El Rancho Drive: Wedekind Road to McCarran Boulevard
Wedekind Road: Sullivan Lane to McCarran Boulevard

Pavement Crack Sealing
Wingfield Hills Road: Vista Boulevard to Rolling Meadows Drive
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Friday 6/12/2020

Pavement Patching
Wingfield Hills Road: Vista Boulevard to Rolling Meadows Drive
Wingfield Springs Road: Poco Bueno Circle to Calle De Oro Parkway

Pavement Crack Sealing
Seventh Street:
El Rancho Drive: Wedekind Road to McCarran Boulevard
Wedekind Road: Sullivan Lane to McCarran Boulevard

 

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/15 – 5/22

No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/22 – 6/8

No work planned. Q&D has remaining concrete work at Mill and Kirman scheduled for 6/8/20.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Vassar Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar Street to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 8th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

May 29, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775)335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 5/29/2020
Pavement Patching
Double R Boulevard: Prototype Drive to South Meadows Parkway
Prototype Drive: Gateway Drive to Double R Boulevard
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

Saturday 5/30/2020
NO WORK SCHEDULED

Sunday 5/31/2020
NO WORK SCHEDULED

Monday 6/1/2020
Pavement Patching
Sierra Highlands Drive: Idelbury Drive to Seventh Street
Double R Boulevard: South Meadows Parkway to Longley Lane
Kietzke Lane: Neil Kietzke Round-A-Bout to Virginia Street

Pavement Crack Sealing
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Tuesday 6/2/2020
Pavement Patching
Sierra Highlands Drive: Idelbury Drive to Seventh Street
Plumas Street: Ridgeview Drive to Plumb Lane
Lakeside Drive: Moana Lane to Brinkby Avenue

Pavement Crack Sealing
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Wednesday 6/3/2020
Pavement Patching
Mae Anne Avenue: Sharlands Avenue to Robb Drive
Arlington Avenue: Skyline Boulevard to Truckee River Bridge
Commercial Row: Arlington Avenue to Lake Street
Third Street: Sierra Street to Vine Street
Fifth Street: West Street to Virginia Street
Sierra Street: Virginia Street to California Avenue

Pavement Crack Sealing
Arrow Creek Parkway: Thomas Creek to Geyser Road

Thursday 6/4/2020
Pavement Patching
Mill Street: Lake Street to Terminal Way
15th Street: Victorian Avenue to C Street
Merchant Street: Sullivan Lane to Commerce Street
Washington Street: Second Street to Fourth Street
Keystone Avenue: California Avenue to Seventh Street
Idlewild Drive: Riviera Street to Booth Street

Pavement Crack Sealing
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

Friday 6/5/2020
Pavement Patching
Richard Springs Boulevard: Eagle Canyon Drive to Shelby Drive
West Calle De La Plata: Pyramid Highway to Eagle Canyon Drive
Keystone Avenue: California Avenue to Seventh Street
2nd Street: Virginia Street to Girioux Street

Pavement Crack Sealing
Double R Boulevard: South Meadows Parkway to Longley Lane
Kietzke Lane: Neil Kietzke Round-A-Bout to Virginia Street

 

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/22 – 6/8

No work planned. Q&D has remaining concrete work at Mill and Kirman scheduled for 6/8/20.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Project Completed

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

 

South Virginia Street:

  • Plumb Ln to Vassar Street: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Vassar Street to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St. Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

May 22, 2020

2020 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 5/25/2020
MEMORIAL DAY – NO WORK SCHEDULED

Tuesday 5/26/2020
Pavement Patching
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Wednesday 5/27/2020
Pavement Patching
Eastlake Boulevard: Coyote Drive to Duck Hill Road

Thursday 5/28/2020
Pavement Patching
Arrowcreek Parkway: Geyser Road to Thomas Creek Road

Friday 5/29/2020
Pavement Patching
Arrowcreek Parkway: Geyser Road to Thomas Creek Road
Rio Wrangler Parkway: Veterans Parkway to Western Skies Drive

 

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work planned, waiting on NDOT project on I580.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/22 – 6/8

No work planned. Q&D has remaining concrete work at Mill and Kirman scheduled for 6/8/20.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

5/18 – 5/22

Traffic signal at Red Rock/Silver Lake fully open. Construction completed.

Road construction is completed for McCarran portion of the project. Minor striping works returns the week of May 18th. Project to be fully completed by the 22nd. Expect closure of the new westbound lane for striping work.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

 

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

May 14, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/15- 5/22
No work planned, waiting on NDOT project on I580.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 5/1

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 20 – May 1: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/15 – 5/22

No work planned.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

5/11 – 5/22

Traffic signal at Red Rock/Silver Lake is now operational. WBL movement from Westbound Silver Lake to Southbound Red Rock is active.Traffic signal construction is complete. Road construction is completed for McCarran portion of the project. Minor striping works returns the week of May 18th. Project to be fully completed by the 22nd. Expect closure of the new westbound lane for striping work.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

 

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Liberty St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

May 7, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/27– 5/15
No work planned, waiting on NDOT project on I580.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 5/1

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 20 – May 1: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/4 – 5/18

Lane closures at Keystone at 7th for signal equipment installation

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

5/4 – 5/10

Traffic signal at Red Rock/Silver Lake is now operational. Work resumes on 5/7 for slurry and striping work at the intersection. Lane reduction down to one lane is expected. WBL movement from Westbound Silver Lake to Southbound Red Rock will be active.

Construction begins 5/4 for the McCarran portion of the project. Left lane closures on WB/EB N. McCarran at Clear Acre Ln to Northtowne Ln. Northbound US 395 on-ramp from N. McCarran is closed. Detour to NB US 395 at Clear Acre Ln.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

 

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Center St/Mary St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Center St/Mary St to Liberty St: traffic is detoured.
    • Southbound traffic is detoured to Liberty St. to Sinclair St to Holcombonb Avenue.
    • Northbound traffic is detoured to Holcomb Ave to Center St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

    • Roundabout work in this area requires closure of Mary St at Virginia St.
    • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

April 30, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/27– 5/15
No work planned, waiting on NDOT project on I580.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 5/1
The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.
Drivers can expect detours during the construction process, for everyone’s safety:
– April 20 – May 1: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

5/4 – 5/18
Lane closures at McCarran at Neil and Keystone at 7th for signal equipment installation

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

4/23
Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Center St/Mary St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Center St/Mary St to Liberty St: traffic is detoured.
    • Southbound traffic is detoured to Liberty St. to Sinclair St to Holcombonb Avenue.
    • Northbound traffic is detoured to Holcomb Ave to Center St. Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St. Center Street/Mary Street at Virginia Street:
  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website

 

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

April 23, 2020

E PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 10/1

The Regional Transportation Commission (RTC) of Washoe County begins construction on a roadway rehabilitation project on East Prater Way between McCarran Boulevard and Sparks Boulevard. Two-way traffic will continue within the construction zone, with one lane in each direction. The project is expected to take about six months to complete. See attached Project Location Map by clicking here.

  • April 20 – June 19: The first phase of construction, expected to take about three months, will shift traffic to the south side of Prater Way. Signalized intersections at Howard Drive and Pullman Drive will remain open, but some side streets, including Woodside Drive, Marracco Drive, East Greenbrae Drive and Station Street will be closed to traffic at Prater Way. Traffic from side streets will be detoured to Howard Drive or Pullman Drive.

 

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project represents a $5.6-million investment in our community funded with fuel tax funds.

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/27– 5/15

No work planned waiting on NDOT project on I580.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/20 – 5/1

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 20 – May 1: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

 

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/27-5/1

Lane closures at McCarran at Neil and Keystone at 7th for signal equipment installation

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Center St/Mary St: traffic is reduced to southbound only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Center St/Mary St to Liberty St: traffic is detoured.
    • Southbound traffic is detoured to Liberty St. to Sinclair St to Holcombonb Avenue.
    • Northbound traffic is detoured to Holcomb Ave to Center St. Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street/Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

 

For the most up to date information on traffic control, please visit the Virginia Street Website.  

April 17, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/20– 4/27

No Work planned

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/13 – 4/28

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 13 – April 28: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/20-4/30

Lane closures at Evans and Enterprise then McCarran at Neil for signal equipment installation

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Mt Rose St/Holcomb Ave to Center St/Mary St: traffic is reduced to southbound direction only.
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.
  • Center St/Mary St to Liberty St: traffic is detoured.
    • Southbound traffic is detoured to Liberty St. to Sinclair St to Holcombonb Avenue.
    • Northbound traffic is detoured to Holcomb Ave to Center St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website.  

April 10, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  • East 9th Street and Montello Street Intersection
  • Valley Road and Sadleir Way Intersection
  • Sutro Street and Haddock Drive Intersection
  • Lemmon Drive and North Virginia Street Intersection
  • Kirman Avenue and Moran Street Intersection
  • Mill Street and Sunshine Lane Intersection
  • Locust Street and Colorado River Boulevard Intersection
  • Grove Street and Yori Way Intersection
  • Hunter Lake Drive and Foster Drive Intersection
  • Sierra Center Parkway at Sierra Town Center
  • York Way and 4th Street Intersection
  • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/13 – 4/16

Patching on Baring and Sparks Blvd. Single lane closures during paving operations.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

4/13 – 4/28

The Regional Transportation Commission (RTC) of Washoe County is almost finished with the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard. The reconstruction includes replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • April 13 – April 28: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/13-4/20                      

No work until 4/16

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
    • Northbound traffic is detoured via side streets to Center St to Liberty St.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website.  

April 3, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  • East 9th Street and Montello Street Intersection
  • Valley Road and Sadleir Way Intersection
  • Sutro Street and Haddock Drive Intersection
  • Lemmon Drive and North Virginia Street Intersection
  • Kirman Avenue and Moran Street Intersection
  • Mill Street and Sunshine Lane Intersection
  • Locust Street and Colorado River Boulevard Intersection
  • Grove Street and Yori Way Intersection
  • Hunter Lake Drive and Foster Drive Intersection
  • Sierra Center Parkway at Sierra Town Center
  • York Way and 4th Street Intersection
  • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work at this time

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about five weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

4/6-4/20
Signal pole installation will begin at Mill/Kirman.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Traffic signal at Red Rock/Silver Lake is now operational. *Caution* – westbound-left (Silver Lake to Red Rock movement) is a yield condition until permanent striping is done in late April/early May.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

South Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
    • Northbound traffic is detoured via side streets to Center St to Liberty St.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Northbound traffic can also use Mt Rose St to Plumas St to Liberty St.

Travelers with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

North Virginia Street:

  • West Stadium Parking Garage to 9th Street: is reduced to one-lane in each direction

For the most up to date information on traffic control, please visit the Virginia Street Website.  

March 27, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  1. East 9th Street and Montello Street Intersection
  2. Valley Road and Sadleir Way Intersection
  3. Sutro Street and Haddock Drive Intersection
  4. Lemmon Drive and North Virginia Street Intersection
  5. Kirman Avenue and Moran Street Intersection
  6. Mill Street and Sunshine Lane Intersection
  7. Locust Street and Colorado River Boulevard Intersection
  8. Grove Street and Yori Way Intersection
  9. Hunter Lake Drive and Foster Drive Intersection
  10. Sierra Center Parkway at Sierra Town Center
  11. York Way and 4th Street Intersection
  12. Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work at this time

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about five weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work at this time.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

3/26 – 3/27
Expect temporary lane closure at the intersection of Red Rock and Silver Lake. Traffic signal to be turned on next Friday.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
    • Traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

 

For the most up to date information on traffic control, please visit the Virginia Street Website.  

March 20, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

  1. East 9th Street and Montello Street Intersection
  2. Valley Road and Sadleir Way Intersection
  3. Sutro Street and Haddock Drive Intersection
  4. Lemmon Drive and North Virginia Street Intersection
  5. Kirman Avenue and Moran Street Intersection
  6. Mill Street and Sunshine Lane Intersection
  7. Locust Street and Colorado River Boulevard Intersection
  8. Grove Street and Yori Way Intersection
  9. Hunter Lake Drive and Foster Drive Intersection
  10. Sierra Center Parkway at Sierra Town Center
  11. York Way and 4th Street Intersection
  12. Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/16 – 3/27
Shoulder closures at I-580 southbound on-ramp at Damonte Ranch Pkwy, I80 ramps at McCarran and Robb Dr.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about five weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/9 – 3/20
Underground construction begins at Prater at I80.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

3/26 – 3/27
Expect temporary lane closure at the intersection of Red Rock and Silver Lake. Traffic signal to be turned on next Friday.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Center St and Mary St: traffic is reduced to southbound direction only.
  • Center St and Mary St to Mt Rose St/Holcomb Ave: traffic is detoured to Holcomb Ave.
    • Southbound traffic through traffic is detoured at Center St to Holcomb Ave
    • Northbound traffic through traffic is detoured at Holcomb Ave to Center St to Liberty St.
    • Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
    • Traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thomas St, California St, Moran St, and Stewart St. Center Street and Mary Street at Virginia Street:
  • Roundabout work in this area requires closure of Mary St at Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

March 12, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/10
Construction to improve the accessibility and connectivity of RTC’s bus stops began on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:
1. East 9th Street and Montello Street Intersection
2. Valley Road and Sadleir Way Intersection
3. Sutro Street and Haddock Drive Intersection
4. Lemmon Drive and North Virginia Street Intersection
5. Kirman Avenue and Moran Street Intersection
6. Mill Street and Sunshine Lane Intersection
7. Locust Street and Colorado River Boulevard Intersection
8. Grove Street and Yori Way Intersection
9. Hunter Lake Drive and Foster Drive Intersection
10. Sierra Center Parkway at Sierra Town Center
11. York Way and 4th Street Intersection
12. Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/9 – 3/13
Short term shoulder closures at: Baring Blvd. and McCarran Blvd.; Sparks Blvd. at Disc Dr.; Vista Blvd. at Disc Dr.; Baring Blvd. at N. Truckee Ln.; Sparks Blvd at Shadow Ln.

3/16 – 3/27
Shoulder closures at I-580 southbound on-ramp at Damonte Ranch Pkwy, I80 ramps at McCarran and Robb Dr.

 

RENO CONSOLIDATED 19-01 PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/16 – 4/20
The Regional Transportation Commission (RTC) of Washoe County is beginning the reconstruction of the segment of Sutro Street between Selmi Drive and North McCarran Boulevard on March 16, 2020. The reconstruction is expected to take about 5 weeks to complete. The RTC will be replacing the roadway, sidewalks, curbs and gutters.

Drivers can expect detours during the construction process, for everyone’s safety:

  • March 16 – 27: Sutro Street between Selmi Drive and North McCarran Boulevard will be open to southbound-only traffic. Drivers going northbound will be detoured to Clear Acre Lane to Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.
  • March 30 – April 17: Sutro Street between Selmi Drive and North McCarran Boulevard will be closed to traffic. Drivers will be detoured to Clear Acre Lane and Selmi Street. Drivers will still be able to exit from the Maverik gas station onto Sutro Street.

The RTC appreciates the community’s patience during the construction process and reminds the community that the roadway will be smoother and safer when the improvements are complete. This project is part of a larger project, called Reno Consolidated 19-01, which represents a $4.3 million investment in our community funded with fuel tax funds.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/9 – 3/20
Underground construction will begin at McCarran Blvd and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Mt Rose St/Holcomb Ave: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • Roundabout work in this area will require closure of either Center St or Mary St at Virginia St. While construction work is occurring on the west side of the roundabout, both Center St and Mary St are closed at Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

March 6, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/2 – 4/3
Construction to improve the accessibility and connectivity of RTC’s bus stops begins on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

    • East 9th Street and Montello Street Intersection
    • Valley Road and Sadleir Way Intersection
    • Sutro Street and Haddock Drive Intersection
    • Lemmon Drive and North Virginia Street Intersection
    • Kirman Avenue and Moran Street Intersection
    • Mill Street and Sunshine Lane Intersection
    • Locust Street and Colorado River Boulevard Intersection
    • Grove Street and Yori Way Intersection
    • Hunter Lake Drive and Foster Drive Intersection
    • Sierra Center Parkway at Sierra Town Center
    • York Way and 4th Street Intersection
    • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/2 – 3/13
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and I-580 southbound on-ramp at Damonte Ranch Pkwy.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/2 – 3/6
Underground construction will begin at 7th St and Keystone Ave. Occasional lane and shoulder closures expected.

3/9 – 3/20
Underground construction will begin at McCarran Blvd and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
  • Plumb Ln to Mt Rose St/Holcomb Ave: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Mt Rose St/Holcomb Ave: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.
Center Street and Mary Street at Virginia Street:
  • Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St. Mary St and Center St remain open to traffic away from Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

February 28, 2020

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

3/2 – 4/3
Construction to improve the accessibility and connectivity of RTC’s bus stops begins on March 2, 2020. As part of phase one of the project, construction crews will repair and replace sidewalks and driveways, place new concrete bus stop pads, and improve Americans with Disabilities Act (ADA) accessibility.

The project will begin with improvements to 12 bus stops, including stops located at or near:

    • East 9th Street and Montello Street Intersection
    • Valley Road and Sadleir Way Intersection
    • Sutro Street and Haddock Drive Intersection
    • Lemmon Drive and North Virginia Street Intersection
    • Kirman Avenue and Moran Street Intersection
    • Mill Street and Sunshine Lane Intersection
    • Locust Street and Colorado River Boulevard Intersection
    • Grove Street and Yori Way Intersection
    • Hunter Lake Drive and Foster Drive Intersection
    • Sierra Center Parkway at Sierra Town Center
    • York Way and 4th Street Intersection
    • Prater Way and Pyramid Way Intersection

Occasional lane and shoulder closures expected.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/2 – 3/13
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and I-580 southbound on-ramp at Damonte Ranch Pkwy.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

3/2 – 3/6
Underground construction will begin at 7th St and Keystone Ave. Occasional lane and shoulder closures expected.

3/2 – 3/20
Underground construction will begin at McCarran Blvd and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
  • Plumb Ln to Vassar St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Vassar St: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.
Center Street and Mary Street at Virginia Street:
  • Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St. Mary St and Center St remain open to traffic away from Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

February 20, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/18 – 2/28
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and I580 southbound on-ramp at Damonte.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/19 – 2/21
Underground construction will begin at 7th St. and Keystone Ave. Occasional lane and shoulder closures expected.

2/24 – 3/6
Underground construction will begin at McCarran Blvd. and Neil Rd. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Plumb Ln to Pueblo St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Pueblo St: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St. Center Street and Mary Street at Virginia Street:
  • Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St. Mary St and Center St remain open to traffic away from Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

February 14, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/14 – 2/28
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and I580 southbound on-ramp at Damonte.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/4 – 2/14
Underground construction continues at Mill St and Kirman Ave. Occasional lane and shoulder closures expected.

2/17 – 2/21
Underground construction will begin at 7th St. and Keystone Ave.. Occasional lane and shoulder closures expected.

2/24 – 3/6
Underground construction will begin at McCarran Blvd. and Neil Rd. Occasional lane and shoulder closures expected.
TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
• Plumb Ln to Vassar St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
• Liberty St to Vassar St: traffic is reduced to southbound direction only.
• Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St.
• Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
o Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:
• Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St. Mary St and Center St remain open to traffic away from Virginia St.
• Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

February 7, 2020

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/30 – 2/14 
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr, and on Disc Dr from Sparks Blvd to Vista Blvd.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/4 – 2/21
Underground construction will begin at Mill St and Kirman Ave. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
  • Plumb Ln to Vassar St: two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
  • Liberty St to Vassar St: traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose St to northbound Plumas St to Liberty St. Two-way traffic is available north of Stewart St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.
Center Street and Mary Street at Virginia Street:
  • Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St.  Mary St and Center St remain open to traffic away from Virginia St.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 31, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

No work currently scheduled.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Thursday 2/6
The Keystone on ramp from California Ave will be closed for fence repair.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/22 – 1/31
Shoulder and lane closures along Sparks Blvd from Baring Blvd to Disc Dr.

1/30 – 2/7
Shoulder closures along Sparks Blvd from Baring Blvd to Disc Dr., Disc from Sparks to Vista and Vista from Disc to Los Altos.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Project complete.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

2/3 – 2/14
Underground construction will begin at Mill St and Kirman Ave. Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Virginia Street:
    • Plumb Ln to Vassar St – two-way traffic with isolated shoulder and street parking closures to install project appurtenances.
    • Vassar St to Stewart St – traffic is reduced to southbound direction only.
    • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Plumas St to Liberty Street. Two-way traffic is available north of Stewart St.
    • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
      • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St. Center Street and Mary Street at Virginia Street:
    • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time. Through traffic will remain open on Virginia St.
    • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 24, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

No work currently scheduled.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Thursday 1/30
The Foster Drive on ramp from Booth St to Keystone Ave will be closed for pedestrian rail installation.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/22 – 1/31
Shoulder and lane closures along Sparks Blvd from Baring Blvd to Disc Dr.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Project complete.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/27 – 1/31
No work scheduled for this week.

2/3 – 2/14
Underground construction will begin at Mill St and Kirman Ave.  Occasional lane and shoulder closures expected.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Vassar St to Stewart St – traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St.  Drivers can also use
  • Mt Rose Street to northbound Plumas St to Liberty Street.  Two-way traffic is available north of Stewart St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St.  During limited instances, both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 17, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 1/20
Pavement Crack Sealing
Locust Street: Casazza Drive to Ryland Street
Kirman Avenue: Ryland Street to Plumb Lane

Tuesday 1/21
Pavement Crack Sealing
Locust Street: Casazza Drive to Ryland Street
Kirman Avenue: Ryland Street to Plumb Lane

Wednesday 1/22
NO WORK SCHEDULED

Thursday 1/23/2020
NO WORK SCHEDULED

Friday 1/24
NO WORK SCHEDULED

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday 1/20
The Foster Drive on ramp from Booth to Keystone will be closed for pedestrian rail installation.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/13 – 1/21
Work will continue along Baring Blvd. Intermittent lane and shoulder closures should be expected. Pull boxes and a 55’ pole for a traffic camera will be installed at Baring Blvd and N Truckee Ln.

1/22 – 1/31
Shoulder and lane closures along Sparks Blvd from Baring Blvd to Disc Dr

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work activity currently scheduled. Traffic signal is in operation.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/7 – 1/24
Traffic signal construction at the intersection of Evans Ave and Enterprise Rd with shoulder and lane closures.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
• Vassar St to Stewart St – traffic is reduced to southbound direction only.
• Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Plumas St to Liberty Street. Two-way traffic is available north of Stewart St.
• Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, Plumas St, or Haskell St; which include:
o Pueblo St, Arroyo St, Vassar St, La Rue Ave, Martin St, Taylor St, Cheney St, St Lawrence Ave, Thoma St, California St, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:
• ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia Street. During limited instances, both streets may be closed at the same time.
• Detours will be in place.
For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 10, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 1/13/2020
Pavement Crack Sealing
Avenida De Landa: Sharlands Avenue to Robb Drive

Tuesday 1/14/2020
Pavement Crack Sealing
Avenida De Landa: Sharlands Avenue to Robb Drive

Wednesday 1/15/2020
Pavement Crack Sealing
Avenida De Landa: Sharlands Avenue to Robb Drive

Thursday 1/16/2020
NO WORK SCHEDULED

Friday 1/17/2020
NO WORK SCHEDULED

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday 1/20
The Foster Drive on ramp from Booth to Keystone will be closed for pedestrian rail installation.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/6 – 1/21
Work will continue along Baring Blvd.  Intermittent lane and shoulder closures should be expected.  Pull boxes and a 55’ pole for a traffic camera will be installed at Baring Blvd and N Truckee Ln.  

1/22 – 1/31
Shoulder and lane closures along Sparks Blvd from Baring Blvd to Disc Dr.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work currently scheduled.  Traffic signal is in operation.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

1/7 – 1/24
Construction will begin at the intersection of Evans Ave and Enterprise Rd with shoulder and lane closures.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Vassar St to Stewart St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St.  Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Stewart St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, or Haskell St; which include:
    • Pueblo St, Arroyo St, Caliente St, Vassar St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

January 2, 2020

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

No work currently scheduled.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

No work currently scheduled.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Jan. 6th – Jan. 10th
Work will continue along Bearing Blvd. Intermittent lane and shoulder closures should be expected. Electrical pull boxes will be installed at Bearing and Truckee.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work currently scheduled.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

No work currently scheduled.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

No work currently scheduled.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:
• Mt Rose St/Holcomb Ave to Cheney St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
• Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Cheney St.
• Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Center St, or Haskell St; which include:

    • Pueblo St, Arroyo St, Caliente St, Vassar St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:
• ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances, both streets may be closed at the same time.
• Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

December 26, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 12/30  –  Friday 1/3
No work is scheduled.  Work will resume on Monday 1/6.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday December 30
Lane Closures on California and Foster to facilitate some corrective work and pedestrian railing installation.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Monday 12/23 – Friday 12/27
No work during holidays

Monday 12/30 – Tuesday 12/31
Pullbox replacement on Baring Boulevard and Truckee Lane with occasional lane and shoulder closures

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Friday 12/13 – Monday 12/23
Occasional lane closure for signal equipment installation for a new traffic signal at the intersection of N Virginia Street and Lemmon Drive.

Traffic signal activation tentatively scheduled for 12/30/19.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Thursday 1/2
Construction of new traffic signal at Evans Avenue and Enterprise Road, possible lane and shoulder closures.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Red Rock Road at Silver Lake Boulevard Traffic Signal Installation
• Traffic Control in effect weekdays from 7 a.m. to 5 p.m. throughout December.
• Eastbound, westbound, southbound traffic lanes will be reduced to one lane for underground utility work.
• Expect flagger operation through the project for equipment and materials moving throughout the project.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Mt Rose St/Holcomb Ave to Martin St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Martin St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave or Haskell St, which include:
    • Pueblo St, Arroyo St, Caliente St, Vassar St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Starting in early 2020, traffic control will extend northward from Martin St towards Liberty St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

December 20, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 12/20
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane
Plumas Street: Plumb Lane to Marsh Avenue
Mt. Rose Street: Arlington Avenue to Plumas Street
Lakeside Drive: McCarran Boulevard to Plumb Lane

Monday 12/23  –  Friday 12/27
No work is scheduled.  Work will resume on Monday 12/30.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Lane closures with traffic control will be in effect to allow installation of pedestrian railing and curb modification.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Friday 12/20
Pullbox replacement on Baring Boulevard and Truckee Lane with occasional lane and shoulder closures.

Monday 12/23  –  Friday 12/27
No work during the holiday.

Monday 12/30  –  Tuesday 12/31
Pullbox replacement on Baring Boulevard and Truckee Lane with occasional lane and shoulder closures.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Friday 12/13  –  Monday 12/23
Occasional lane closure for signal equipment installation for a new traffic signal at the intersection of N Virginia Street and Lemmon Drive.

Traffic signal activation tentatively scheduled for 12/23.

 

TE SPOT 8 – PACKAGE 1
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Thursday 1/2
Construction of new traffic signal at Evans Avenue and Enterprise Road, possible lane and shoulder closures.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Red Rock Road at Silver Lake Boulevard Traffic Signal Installation
• Traffic Control in effect weekdays from 7 a.m. to 5 p.m. throughout December.
• Eastbound, westbound, southbound traffic lanes will be reduced to one lane for underground utility work.
• Expect flagger operation through the project for equipment and materials moving throughout the project.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Virginia Street:

  • Mt Rose St/Holcomb Ave to Martin St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Martin St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave or Haskell St, which include:
    • Pueblo St, Arroyo St, Caliente St, Vassar St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Starting in early 2020, traffic control will extend northward from Martin St towards Liberty St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

December 13, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 12/16
NO WORK SCHEDULED

Tuesday 12/17
Pavement Crack Sealing
Mayberry Drive: Fourth Street to Hunter Lake Drive
Caughlin Parkway: McCarran Boulevard (North) to McCarran Boulevard (South)
Plumb Lane: McCarran Boulevard to Ferris Lane
Hunter Lake Drive: Plumb Lane to California Avenue

Wednesday 12/18
Pavement Crack Sealing
Mayberry Drive: Fourth Street to Hunter Lake Drive
Caughlin Parkway: McCarran Boulevard (North) to McCarran Boulevard (South)
Plumb Lane: McCarran Boulevard to Ferris Lane
Hunter Lake Drive: Plumb Lane to California Avenue
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane
Plumas Street: Plumb Lane to Marsh Avenue
Mt. Rose Street: Arlington Avenue to Plumas Street
Lakeside Drive: McCarran Boulevard to Plumb Lane

Thursday 12/19
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane
Plumas Street: Plumb Lane to Marsh Avenue
Mt. Rose Street: Arlington Avenue to Plumas Street
Lakeside Drive: McCarran Boulevard to Plumb Lane

Friday 12/20
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane
Plumas Street: Plumb Lane to Marsh Avenue
Mt. Rose Street: Arlington Avenue to Plumas Street
Lakeside Drive: McCarran Boulevard to Plumb Lane

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

California Avenue will be closed between Newlands Circle and Booth Street to install a new signal pole at Keystone Avenue. Detours will be in place.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

12/13 – 12/19
Pullbox replacement on Vista Boulevard with occasional lane and shoulder closures.
Shoulder closures on SR431 S Virginia Street; I-80 at McCarran Boulevard and I-80 at Robb Drive.

12/20
Pullbox replacement on Baring Boulevard and Truckee Lane with occasional lane and shoulder closures.

12/23 – 12/27
No work during holidays

12/30 – 12/31
Pullbox replacement on Baring Boulevard and Truckee Lane with occasional lane and shoulder closures.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

12/13 – 12/23
Occasional lane closure for signal equipment installation for a new traffic signal at the intersection of N Virginia Street and Lemmon Drive.

Traffic signal activation tentatively scheduled for 12/23.

 

TE SPOT 8 – PACKAGE 2
RTC Project Manager, Andrew Jayankura, P.E., PTOE. – (775) 332-2139

Red Rock Road at Silver Lake Boulevard Traffic Signal Installation
• Traffic Control in effect weekdays from 7 a.m. to 5 p.m. throughout December.
• Eastbound, westbound, southbound traffic lanes will be reduced to one lane for underground utility work.
• Expect flagger operation through the project for equipment and materials moving throughout the project.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street. Businesses will always remain accessible.

Virginia Street:

  • Mt Rose St/Holcomb Ave to Martin St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Martin St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave or Haskell St, which include:
    • Pueblo St, Arroyo St, Caliente St, Vassar St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

December 6, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 12/6
Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Double Diamond Parkway: Double R Boulevard to Double R Boulevard

Monday 12/9
Pavement Striping
Plumb Lane: Sharon Way to Arlington Avenue

Tuesday 12/10
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Wells Avenue: Virginia Street to Kuenzli Street
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road
Vista Boulevard: Brierley Way to Wingfield Parkway
Los Altos Parkway: Vista Boulevard to Promedio Parkway
Eagle Canyon Drive: Pyramid Highway to West Calle De La Plata

Wednesday 12/11
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Wells Avenue: Virginia Street to Kuenzli Street
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road
Vista Boulevard: Brierley Way to Wingfield Parkway
Los Altos Parkway: Vista Boulevard to Promedio Parkway
Eagle Canyon Drive: Pyramid Highway to West Calle De La Plata

Thursday 12/12
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Wells Avenue: Virginia Street to Kuenzli Street
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane

Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Double Diamond Parkway: Double R Boulevard to Double R Boulevard

Friday 12/13
Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Double Diamond Parkway: Double R Boulevard to Double R Boulevard

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

12/3  –  12/13
Conduit installation on Disc Dr between Sparks Blvd and Vista Blvd.  WB lane closures and driveway closures.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

12/6/19 – 1/3/20
Occasional lane closure for signal equipment installation for a new traffic signal at the intersection of N Virginia Street and Lemmon Drive.

 

RENO CONSOLIDATED 19-03 – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE
RTC Project Manager, Warren Call, P.E. – (775) 335-1881

Road work on Sierra Highlands Drive, Colbert Drive, Hammill Lane, Ralston Street, and Ohm Place is complete.  The roads are open with no restrictions.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street. Businesses will always remain accessible.

Virginia Street:

  • Mt Rose St/Holcomb Ave to Martin St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Martin St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave or Haskell St, which include:
    • Pueblo St, Arroyo St, Caliente St, Vassar St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

November 27, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 12/02
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Wells Avenue: Virginia Street to Kuenzli Street
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road
Vista Boulevard: Brierley Way to Wingfield Parkway
Los Altos Parkway: Vista Boulevard to Promedio Parkway
Eagle Canyon Drive: Pyramid Highway to West Calle De La Plata

Tuesday 12/3
Pavement Crack SealingFourth Street:
Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Wells Avenue: Virginia Street to Kuenzli Street
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane

Utility AdjustmentsLos Altos Parkway:
Vista Boulevard (South) to Goodwin Road
Vista Boulevard: Brierley Way to Wingfield Parkway
Los Altos Parkway: Vista Boulevard to Promedio Parkway
Eagle Canyon Drive: Pyramid Highway to West Calle De La Plata

Wednesday 12/4
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Wells Avenue: Virginia Street to Kuenzli Street
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane

Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Thursday 12/5
Pavement Crack Sealing
Fourth Street: Keystone Avenue to West Street
Kuenzli Street: Kietzke Avenue to Girioux Street
Lake Street: Second Street to Plaza Street
Liberty Street: Center Street to Holcomb Avenue
Wells Avenue: Virginia Street to Kuenzli Street
Locust Street: Casazza Drive to Ryland Street
Ryland Street: Kirman Avenue to Mill Street
Kirman Avenue: Ryland Street to Plumb Lane
Second Street: Girioux Street to Kietzke Lane

Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Double Diamond Parkway: Double R Boulevard to Double R Boulevard

Friday 12/6
Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Double Diamond Parkway: Double R Boulevard to Double R Boulevard

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

ITS PHASE 2B PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

  • Conduit installation on Disc between Sparks and Vista. WB lane closures and driveway closures.

 

LEMMON DRIVE CAPACITY IMPROVEMENT
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

  • Exploratory work under the roadway in preparation for potential future roadway construction that will improve safety and mobility on Lemmon Drive.
  • Monday 11/18 – Early December (8:30am to 4:00 pm): Intermittent lane closures on Lemmon drive between Fleetwood Drive and Chickadee Drive. Flaggers will direct two-way traffic.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • 12/6/19 – 1/3/20: occasional lane closure for signal equipment installation.

 

RENO CONSOLIDATED 19-02 – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Road work on North Hills Boulevard and Hunter Lake/Foster Drive is complete.  The roads are open with no restrictions.

 

RENO CONSOLIDATED 19-03 – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE
RTC Project Manager, Warren Call, P.E. – (775) 335-1881

Ohm Place: roadwork is complete. Intermittent traffic controls will be in place for punch list work. Flaggers may be present.

Ralston Street: roadwork is complete.

Sierra Highlands: roadwork is substantially complete. Intermittent traffic controls will be in place for utility adjustment and punch list work. Flaggers may be present.

Hammil Lane and Colbert Drive: roadwork is complete.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street. Businesses will always remain accessible.

Virginia Street:

  • Mt Rose St/Holcomb Ave to Center St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Center St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Lake St, or Haskell St, which include:
    • Continental Dr, Regency Wy, Walts Ln, Mt Rose St, Pueblo St, Arroyo St, Caliente St, Vassar St, Martin St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

November 22, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 11/22
Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Monday 11/25
Pavement Crack Sealing
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Silverada Boulevard: Ninth Street to Oddie Boulevard
Victorian Avenue: El Rancho to Pyramid Way
Nugget Avenue: East Victorian Plaza Circle to West Victorian Plaza Circle
South Rock Boulevard: Hymer Avenue to Glendale Avenue
Galletti Way: Glendale Avenue to Fourth Street

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road
Vista Boulevard: Brierley Way to Wingfield Parkway
Los Altos Parkway: Vista Boulevard to Promedio Parkway
Eagle Canyon Drive: Pyramid Highway to West Calle De La Plata

Tuesday 11/26
Pavement Crack Sealing
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Silverada Boulevard: Ninth Street to Oddie Boulevard
Victorian Avenue: El Rancho to Pyramid Way
Nugget Avenue: East Victorian Plaza Circle to West Victorian Plaza Circle
South Rock Boulevard: Hymer Avenue to Glendale Avenue
Galletti Way: Glendale Avenue to Fourth Street

Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Double Diamond Parkway: Double R Boulevard to Double R Boulevard

Wednesday 11/27
Pavement Crack Sealing
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Silverada Boulevard: Ninth Street to Oddie Boulevard
Victorian Avenue: El Rancho to Pyramid Way
Nugget Avenue: East Victorian Plaza Circle to West Victorian Plaza Circle
South Rock Boulevard: Hymer Avenue to Glendale Avenue
Galletti Way: Glendale Avenue to Fourth Street

Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Thursday 11/28 – Friday 11/29
No work scheduled

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

LEMMON DRIVE CAPACITY IMPROVEMENT
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Exploratory work under the roadway in preparation for potential future roadway construction that will improve safety and mobility on Lemmon Drive.

  • Tuesday 11/12 – Friday 11/22 (8:30 am to 4:00 pm): Intermittent lane closures on Lemmon Drive between US 395 and Military Road. Two-way traffic will remain in place.
  • Monday 11/18 – Early December (8:30am to 4:00 pm): Intermittent lane closures on Lemmon drive between Fleetwood Drive and Chickadee Drive. Flaggers will direct two-way traffic.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • 11/25 – 12/6: occasional lane closure for signal equipment installation

 

RENO CONSOLIDATED 19-02 – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Road work on North Hills Boulevard and Hunter Lake/Foster Drive is complete.  The roads are open with no restrictions.

 

RENO CONSOLIDATED 19-03 – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE
RTC Project Manager, Warren Call, P.E. – (775) 335-1881

Ohm Place: roadwork is complete. Intermittent traffic controls will be in place for punch list work. Flaggers may be present.

Ralston Street: roadwork is complete.

Sierra Highlands: roadwork is substantially complete. Intermittent traffic controls will be in place for utility adjustment and punch list work. Flaggers may be present.

Hammil Lane and Colbert Drive: roadwork is complete.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street. Businesses will always remain accessible.

Virginia Street:

  • Mt Rose St/Holcomb Ave to Center St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughout this section of Virginia St.
  • Northbound through traffic is detoured at Holcomb Ave to Center St to Liberty St. Drivers can also use Mt Rose Street to northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Center St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Lake St, or Haskell St, which include:
    • Continental Dr, Regency Wy, Walts Ln, Mt Rose St, Pueblo St, Arroyo St, Caliente St, Vassar St, Martin St, Taylor St, Cheney St, St Lawrence Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

November 15, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Monday 11/18/2019
Utility Adjustments
Plumb Lane: Upson Lane to Phillips Street

Pavement Crack Sealing
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Silverada Boulevard: Ninth Street to Oddie Boulevard
Victorian Avenue: El Rancho to Pyramid Way
Nugget Avenue: East Victorian Plaza Circle to West Victorian Plaza Circle
South Rock Boulevard: Hymer Avenue to Glendale Avenue
Galletti Way: Glendale Avenue to Fourth Street

 

Tuesday 11/19/2019
Pavement Crack Sealing
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Silverada Boulevard: Ninth Street to Oddie Boulevard
Victorian Avenue: El Rancho to Pyramid Way
Nugget Avenue: East Victorian Plaza Circle to West Victorian Plaza Circle
South Rock Boulevard: Hymer Avenue to Glendale Avenue
Galletti Way: Glendale Avenue to Fourth Street

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

Pavement Striping (NIGHTWORK-7:00 PM to 5:00 AM)
Sun Valley Boulevard: Seventh Avenue Intersection
McCarran Boulevard: Mayberry Drive Intersection

Wednesday 11/20/2019
Pavement Crack Sealing
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Silverada Boulevard: Ninth Street to Oddie Boulevard
Victorian Avenue: El Rancho to Pyramid Way
Nugget Avenue: East Victorian Plaza Circle to West Victorian Plaza Circle
South Rock Boulevard: Hymer Avenue to Glendale Avenue
Galletti Way: Glendale Avenue to Fourth Street

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road
Vista Boulevard: Brierley Way to Wingfield Parkway
Los Altos Parkway: Vista Boulevard to Promedio Parkway
Eagle Canyon Drive: Pyramid Highway to West Calle De La Plata

Thursday 11/21/2019
Pavement Crack Sealing
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Silverada Boulevard: Ninth Street to Oddie Boulevard
Victorian Avenue: El Rancho to Pyramid Way
Nugget Avenue: East Victorian Plaza Circle to West Victorian Plaza Circle
South Rock Boulevard: Hymer Avenue to Glendale Avenue
Galletti Way: Glendale Avenue to Fourth Street

Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Double Diamond Parkway: Double R Boulevard to Double R Boulevard

Friday 11/22/2019
Utility Adjustments
Mira Loma Drive: McCarran Boulevard to Veterans Parkway
Maestro Drive: Colbert Drive to Double R Boulevard
Sierra Center Parkway: Virginia Street to Maestro Drive
South Meadows Parkway: Gateway Drive to Veterans Parkway
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

LEMMON DRIVE CAPACITY IMPROVEMENT
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

  • Exploratory work under the roadway in preparation for potential future roadway construction that will improve safety and mobility on Lemmon Drive.
  • Tuesday 11/12 – Friday 11/22 (8:30 am to 4:00 pm): Intermittent lane closures on Lemmon Drive between US 395 and Military Road. Two-way traffic will remain in place.
  • Monday 11/18 – Early December (8:30am to 4:00 pm): Intermittent lane closures on Lemmon drive between Fleetwood Drive and Chickadee Drive. Flaggers will direct two-way traffic.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • 11/25 – 12/6: occasional lane closure for signal equipment installation

 

RENO CONSOLIDATED 19-02 – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

North Hills Boulevard:

  • Between Golden Valley Road and Beckwourth Drive:
    • Construction is substantially complete with minor traffic controls.
    • Some sidewalk work/bus stop amenities is being finished.
  • Between Beckwourth Drive and Buck Drive:
    • Road is open to two-way traffic with minor traffic controls.

Hunter Lake/Foster Drive: construction is substantially complete and traffic control has been removed.

 

RENO CONSOLIDATED 19-03 – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE
RTC Project Manager, Warren Call, P.E. – (775) 335-1881

Ohm Place: – roadwork is complete. Intermittent traffic controls will be in place for punch list work. Flaggers may be present.

Ralston Street: between University Terrace and 11th Street – roadwork is complete. Intermittent traffic controls will be in place for punch list work. Flaggers may be present.

Sierra Highlands: roadwork is substantially complete. Intermittent traffic controls will be in place for utility adjustment and punch list work. Flaggers may be present.

Hammil Lane and Colbert Drive: roadwork is substanilly complete. Intermitten traffic controls will be in place for punch list work. Flaggers may be present.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street. Businesses will always remain accessible.

Virginia Street:

  • Regency Wy to Center St – traffic is reduced to southbound direction only. Traffic control will shift lanes throughouth Virginia Street.
  • Northbound through traffic is detoured from Regency Wy to Holcomb Ave to Center St to Liberty St. Drivers can also use northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Center St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many sidestreets from Holcomb Ave, Lake St, or Haskell St, which include:
    • Continental Dr, Regency Wy, Walts Ln, Mt Rose St, Pueblo St, Arroyo St, Caliente St, Vassar St, Martin St, Taylor St, Cheney St, St Lawerance Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

Plumb Lane at Virginia Street

  • The outside lane of west bound Plumb Lane in the vicinity of Virginia Street will be closed on Monday November 18 from approximately 8:30 am through 4:00 pm.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

November 8, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 11/8
Pavement Crack Sealing
Disc Drive: Vista Boulevard to Sparks Boulevard
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Baring Boulevard: McCarran Boulevard to Vista Boulevard
Greenbrae Drive: 4th Street to Stanford Way
Prater Way: Pyramid Highway to Northern Nevada Medical Center

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

Monday 11/11
Pavement Crack Sealing
Disc Drive: Vista Boulevard to Sparks Boulevard
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Baring Boulevard: McCarran Boulevard to Vista Boulevard
Greenbrae Drive: 4th Street to Stanford Way
Prater Way: Pyramid Highway to Northern Nevada Medical Center

Tuesday 11/12
Pavement Crack Sealing
Disc Drive: Vista Boulevard to Sparks Boulevard
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Baring Boulevard: McCarran Boulevard to Vista Boulevard
Greenbrae Drive: 4th Street to Stanford Way
Prater Way: Pyramid Highway to Northern Nevada Medical Center

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

Wednesday 11/13
Pavement Crack Sealing
Disc Drive: Vista Boulevard to Sparks Boulevard
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Baring Boulevard: McCarran Boulevard to Vista Boulevard
Greenbrae Drive: 4th Street to Stanford Way
Prater Way: Pyramid Highway to Northern Nevada Medical Center

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

Thursday 11/14
Pavement Crack Sealing
Disc Drive: Vista Boulevard to Sparks Boulevard
Sullivan Lane: Prater Way to El Rancho Boulevard
Wedekind Road: Sutro Street to El Rancho Drive
Baring Boulevard: McCarran Boulevard to Vista Boulevard
Greenbrae Drive: 4th Street to Stanford Way
Prater Way: Pyramid Highway to Northern Nevada Medical Center

Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

Friday 11/8
Utility Adjustments
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

LEMMON DRIVE CAPACITY IMPROVEMENT
RTC Project Manager, Dale Keller, P.E. – (775) 335-1827

Exploratory work under the roadway will take place in preparation for potential future roadway construction that will improve safety and mobility on Lemmon Drive.

  • Tuesday 11/12  –  Friday 11/22  (8:30 am to 4:00 pm): Intermittent lane closures on Lemmon Drive between US 395 and Military Road.  Two-way traffic will remain in place.
  • Monday 11/18  –  early December (8:30 am to 4:00 pm): Intermittent lane closures on Lemmon Drive between Fleetwood Drive and Chickadee Drive.  Flaggers will direct two-way traffic.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • 11/12 – 11/22: occasional lane closure for signal equipment installation.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

The contractor is finishing up roadway work on Sutro Street from Commercial Row to 4th Street.

  • Sutro Street will be open to traffic in both directions from E. Commercial Row to 4th Street. Lane shifts will be in place as the contractor stripes the roadway and raises uttilites.

This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

 

RENO CONSOLIDATED 19-02 – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

North Hills Boulevard: Monday 11/11 – replacement of loops along Golden Valley Road will take place. Lane closures on Golden Valley Road will be minimized as much as possible. The contractor will schedule operations to avoid working at the school in the afternoon.

The Contractor is finalizing construction activities.

  • Between Golden Valley Road and Beckwourth Drive:
    • Striping operations will be in effect.
    • Sidewalk work is scheduled to take place.
    • Two-way traffic remains in this segment and will be flagger controlled during construction hours.
    • Traffic shifted using the center turn lane as a travel lane.
    • Please use caution and share the road with bicyclists.
  • Between Beckwourth Drive and Buck Drive: Friday evening the road will be open to traffic with minor controls.

Hunter Lake/Foster Drive: construction is substantially complete and traffic control has been removed.

 

RENO CONSOLIDATED 19-03 – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE
RTC Project Manager, Warren Call, P.E. – (775) 335-1881

Ohm Place: roadwork is complete.

Ralston Street: between University Terrace and 11th Street – roadwork is complete.  Intermittent traffic controls will be in place for punch list work.  Flaggers may be present.

Sierra Highlands: roadwork is substantially complete.  Intermittent traffic controls will be in place for utility adjustment and punch list work.  Flaggers may be present.

Hammil Lane and Colbert Drive: roadwork is substantially complete.  Intermittent traffic controls will be in place for punch list work.  Flaggers may be present.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street. Businesses will always remain accessible.

Virginia Street:

  • Regency Wy to Center St – traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured from Regency Wy to Holcomb Ave to Center St to Liberty St. Drivers can also use northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Center St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many sidestreets from Holcomb Ave, Lake St, or Haskell St, which include:
    • Continental Dr, Regency Wy, Walts Ln, Mt Rose St, Pueblo St, Arroyo St, Caliente St, Vassar St, Martin St, Taylor St, Cheney St, St Lawerance Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

October 31, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

 

Monday 11/4/2019

Pavement Crack Sealing

Village Parkway: Cold Springs Drive to Cody Court

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)

Greg Street: Franklin Way to I-80 Right of Way

Seventh Street: Genoa Avenue to Elgin Avenue

 

Tuesday 11/5/2019

Pavement Crack Sealing

Village Parkway: Cold Springs Drive to Cody Court

 

Wednesday 11/6/2019

Pavement Crack Sealing

Ingenuity Avenue: Pyramid Highway to Hawco Court

Hawco Court: Ingenuity Avenue to End of Pavement

Digital Court: Ingenuity Avenue to End of Pavement

Isidor Court: Circuit Court to Academy Way

Distribution Drive: West Calle De La Plata to Isidor Court

Circuit Court: Isidor Court to End of Pavement

Inventors Place: Isidor Court to End of Pavement

Utility Adjustments

Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

 

Thursday 11/7/2019

Pavement Crack Sealing

Ingenuity Avenue: Pyramid Highway to Hawco Court

Hawco Court: Ingenuity Avenue to End of Pavement

Digital Court: Ingenuity Avenue to End of Pavement

Isidor Court: Circuit Court to Academy Way

Distribution Drive: West Calle De La Plata to Isidor Court

Circuit Court: Isidor Court to End of Pavement

Inventors Place: Isidor Court to End of Pavement

Utility Adjustments

Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

 

Friday 11/8/2019

Pavement Crack Sealing

Disc Drive: Vista Boulevard to Sparks Boulevard

Sullivan Lane: Prater Way to El Rancho Boulevard

Wedekind Road: Sutro Street to El Rancho Drive

Baring Boulevard: McCarran Boulevard to Vista Boulevard

Greenbrae Drive: 4th Street to Stanford Way

Prater Way: Pyramid Highway to Northern Nevada Medical Center

Utility Adjustments

Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • Construction is on hold until signal equipment arrives in November.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Monday, Nov. 4 through Friday, Nov. 8:

  • Sutro Street will be closed to northbound traffic from E. Commercial Row to 4th Street. Southbound traffic will remain open. Northbound traffic will be detoured at E. Commercial Row to Sage Street to 4th Street.

Friday, Nov. 8 at 6 p.m. through Monday, Nov. 11 at 5 a.m.:

  • Sutro Street will be closed from Kuenzli Street to 4th Street. Access to the Waste Management Sage Transfer Station will be maintained by detouring from 4th Street to Sage Street to E. Commercial Row. Northbound traffic will be detoured on Kirman Avenue to Kuenzli Street to Wells Avenue. Southbound traffic will be detoured at 6th Street to Wells Avenue.

 

These closures are in place for safety and so that the RTC can remove the existing roadway and repave it.

This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

North Hills Boulevard:

  • Paving operations on Thursday 10/31 thru Saturday 11/02 (Temperature dependent) southbound lane closure between Round Table Pizza driveway and Buck Drive. Only northbound traffic allowed.
  • Paving will start at 8:30 am and will last until 8:00 pm (approximately) each day.

 

  • Lane closures on Golden Valley Road will be minimized as much as possible. The contractor will schedule operations to avoid working at the intersection as school is letting out in the afternoon.
  • Signal timing adjustments have been made to help minimize congestion.
  • Traffic Control will continue as it has been.

 

  • Between Golden Valley Road and Beckwourth Drive:
    • Two-way traffic remains in this segment and will be flagger controlled during construction hours.
    • Traffic is shifted using the center turn lane as a travel lane.
    • Please use caution and share the road with bicyclists.
  • Between Beckwourth Drive and Buck Drive:
    • Detours in place. Southbound lane closure. Only northbound traffic allowed.
    • Northbound traffic is flagger controlled during construction hours approximately 7 am to 5 pm, Monday thru Saturday.
    • Speed limit reduced to 25 MPH and traffic will be allowed on pulverized material (unpaved lane). Watch for construction equipment during construction hours.

Hunter Lake/Foster Drive:

  • Construction is substantially complete.
  • Traffic Control has been removed.

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

RTC Project Manager, Warren Call, P.E. – (775) 335-1881

Ralston Street:

  • Between University Terrace and 11th Street – roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for punch list work.

Ohm Place:

  • Roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for punch list work.

Sierra Highlands:

  • Roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for punch list work.

Hammil Lane:

  • Construction is in progress and will continue thru the end of October.  Pavement removal will occur on Wednesday and Thursday.  Watch for flaggers and traffic controls that will be in place throughout construction.

Colbert Drive:

  • Construction is underway on Colbert Drive from Longley Lane to 500 feet north on Colbert Drive.  pavement removal will occur on Monday and Tuesday.  Watch for flaggers and traffic controls that will be in place throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street. Businesses will always remain accessible.

Virginia Street:

  • Regency Wy to Center St – traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured from Regency Wy to Holcomb Ave to Center St to Liberty St. Drivers can also use northbound Haskell St to Martin St to Virginia St. Two-way traffic is available north of Center St.
  • Northbound traffic with the final destination within the construction zone can utilize one of the many sidestreets from Holcomb Ave, Lake St, or Haskell St, which include:
    • Continental Dr, Regency Wy, Walts Ln, Mt Rose St, Pueblo St, Arroyo St, Caliente St, Vassar St, Martin St, Taylor St, Cheney St, St Lawerance Ave, Moran St, and Stewart St.

Center Street and Mary Street at Virginia Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St. During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

October 24, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Thursday 10/24
Slurry Seal
Terminal Way: Plumb Lane to Mill Street
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

Pavement Striping
Various Project Streets: 2nd Coat Paint Application

Friday 10/25
Pavement Striping
Various Project Streets: 2nd Coat Paint Application

Saturday 10/26 thru Sunday 11/3
No work due to weather conditions.  Work will resume the week of November 4th.

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • Construction is on hold until signal equipment arrives in November.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction closures and detours will continue the week of October 27th. The project is expected to be complete by November.

Sutro/Commercial:

  • Construction work from Commercial Row to 4th Street is ongoing.
  • Two-way traffic will be provided at all times.

This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

North Hills Boulevard:

  • Paving operations on Thursday 10/31 thru Saturday 11/02 (Temperature dependent) southbound lane closure between Round Table Pizza driveway and Buck Drive. Only northbound traffic allowed.
  • Paving will start at 8:30 am and will last until 8:00 pm (approximately) each day.
  • Lane closures on Golden Valley Road will be minimized as much as possible. The contractor will schedule operations to avoid working at the intersection as school is letting out in the afternoon.
  • Signal timing adjustments have been made to help minimize congestion.
  • Traffic Control will continue as it has been.
  • Between Golden Valley Road and Beckwourth Drive:
    • Two-way traffic remains in this segment and will be flagger controlled during construction hours.
    • Traffic is shifted using the center turn lane as a travel lane.
    • Please use caution and share the road with bicyclists.
  • Between Beckwourth Drive and Buck Drive:
    • Detours in place. Southbound lane closure. Only northbound traffic allowed.
    • Northbound traffic is flagger controlled during construction hours approximately 7 am to 5 pm, Monday thru Saturday.
    • Speed limit reduced to 25 MPH and traffic will be allowed on pulverized material (unpaved lane). Watch for construction equipment during construction hours.

Hunter Lake/Foster Drive:

  • Construction is substantially complete.
  • Traffic Control has been removed.

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

RTC Project Manager, Warren Call, P.E. – (775) 335-1881

Ralston Street:

  • Between University Terrace and 11th Street – roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for punch list work.

Ohm Place:

  • Roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for punch list work.

Sierra Highlands:

  • Roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for punch list work.

Hammil Lane:

  • Construction is in progress and will continue thru the end of October.  Pavement removal will occur on Wednesday and Thursday.  Watch for flaggers and traffic controls that will be in place throughout construction.

Colbert Drive:

  • Construction is underway on Colbert Drive from Longley Lane to 500 feet north on Colbert Drive.  pavement removal will occur on Monday and Tuesday.  Watch for flaggers and traffic controls that will be in place throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street.  Businesses will always remain accessible.

Virginia Street:

  • Regency Wy to Center St – traffic is reduced to southbound direction only.
  • Northbound through traffic is detoured from Regency Wy to Holcomb Ave to Center St to Liberty St. Drivers can also use northbound Haskell St to Martin St to Virginia St.  Two-way traffic is available north of Center St.
  • Northbound traffic with final destination within the construction zone can utilize one of the many side streets from Holcomb Ave, Lake St, or Haskell St, which include:
    • Continental Dr, W Regency Wy, Walts Ln, Mt Rose St, Pueblo St, Arroyo St, Caliente St, Vassar St, Martin St, Taylor St, Cheney St, St Lawerance Ave, Moran St, and Stewart St.

Center Street and Mary Street:

  • ROAD CLOSURE: Work in this area will require closure of either Center St or Mary St at Virginia St.  During limited instances both streets may be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

October 18, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Sunday 10/20/2019

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd Coat Paint Application

Monday 10/21/2019

NO WORK SCHEDULED

Tuesday 10/22/2019

Pavement Striping
Various Project Streets: 2nd Coat Paint Application

Wednesday 10/23/2019

Pavement Striping
Various Project Streets: 2nd Coat Paint Application

Thursday 10/24/2019

Slurry Seal
Terminal Way: Plumb Lane to Mill Street
Los Altos Parkway: Vista Boulevard (South) to Goodwin Road

Pavement Striping
Various Project Streets: 2nd Coat Paint Application

Friday 10/25/2019

Pavement Striping
Various Project Streets: 2nd Coat Paint Application

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • Construction is on hold until signal equipment arrives in November.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction closures and detours will continue the week of October 20th. The project is expected to be complete by November.

Sutro/Commercial:

  • Construction work from Commercial Row to 4th Street is ongoing.
  • Two-way traffic will be provided at all times.

This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

North Hills Boulevard:

  • Paving operations (demolition and repave) began Thursday 10/10.
  • Lane closures on Golden Valley Road will be minimized as much as possible.  The contractor will schedule operations to avoid working at the intersection as school is letting out in the afternoon. Two-way traffic remains in this segment.
  • Signal timing adjustments have been made to help minimize congestion.
  • Between Golden Valley Road and Beckwourth Drive:
    • Two-way traffic remains in this segment.
    • Will be flagger controlled during construction hours.
    • Traffic is shifted using the center turn lane as a travel lane.
    • Please use caution and share the road with bicyclists.
  • Between Beckwourth Drive and Buck Drive:
    • DETOUR: Southbound lane closure, only northbound traffic allowed.
    • Northbound traffic is flagger controlled during construction hours approximately 7 am to 5 pm, Monday thru Saturday.
    • Speed limit reduced to 25 MPH and traffic will be allowed on pulverized material (unpaved lane).  Watch for construction equipment during construction hours.

Hunter Lake/Foster Drive:

    • Paving operations (demolition and repave) began Monday 10/7.
    • One lane closure at intersection.
    • Two-way traffic maintained at all times.

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

RTC Project Manager, Warren Call, P.E. – (775) 335-1881

Ralston Street:

  • Between University Terrace and 11th Street – roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for minor utility work.

Ohm Place:

  • Roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for minor utility work.

Sierra Highlands:

  • Construction is on going and anticipated to continue thru the end of October.  Watch for flaggers and traffic controls that will be in place throughout construction on Sierra Highlands.

Hammil Lane:

  • Construction has begun  and will continue thru the end of October.  Watch for flaggers and traffic controls that will be in place throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street.  Businesses will always remain accessible.

Virginia Street:

  • Traffic is reduced to southbound direction only from Regency Way to Center Street.
  • Northbound through traffic will be detoured from Regency Way to Holcomb Avenue to Center Street to Liberty Street. Drivers can also use northbound Haskell Street to Martin Street to Virginia Street. Two-way traffic is available north of Center Street..
  • Side streets, including Tayler Street, Cheney Street, Moran Street, and Stewart Street, are also open for Midtown-business access.

Center Street and Mary Street:

  • ROAD CLOSURE: Work in this area requires either Center Street or Mary Street may be closed at Virginia Street. The Streets will never both be closed at the same time.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

October 11, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are

Friday 10/11
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd coat paint application

Sunday 10/13
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd coat paint application
Greg Street: Franklin Way to I-80

Monday 10/14
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd coat paint application
Greg Street: Franklin Way to I-80

Tuesday 10/15
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd coat paint application
Greg Street: Franklin Way to I-80

Wednesday 10/16
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd coat paint application

Thursday 10/17
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd coatpPaint application

Friday 10/18
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd coat paint application

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • Construction is on hold until signal equipment arrives mid-November.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

Construction closures and detours will continue the week of October 13th. The project is expected to be complete by November.

Sutro Street:

  • Constuction work from McCarran to the northern terminus is ongoing.
  • Paving operations begin on Wednesday, 10/16.
  • Two-way traffic will be provided and flaggers will assist motorisits through the construction zone.  All detours will be marked.
  • Bus service is being detoured off of Selmi Drive.  Check the RTC Public Transportation webpage for more details.

Sutro/Commercial:

  • Construction work from Commercial Row to 4th Street begins on Monday, 10/14.
  • Two-way traffic maintained at all times.

This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

North Hills Boulevard:

  • Paving operations (demolition and repave) began Thursday 10/10.
  • Between Golden Valley Road and Beckwourth Drive:
    • Two-way traffic remains in this segment.
    • Traffic is shifted using the center turn lane as a travel lane.
    • Please use caution and share the road with bicyclists.
  • Between Beckwourth Drive and Buck Drive:
    • DETOUR: Northbound lane closure, only southbound traffic allowed.
    • Southbound traffic is flagger controlled during construction hours approximately 7 am to 5 pm, Monday thru Saturday.
    • Speed limit reduced to 25 MPH and traffic will be allowed on pulverized material (unpaved lane).  Watch for construction equipment during construction hours.

Hunter Lake/Foster Drive:

    • Paving operations (demolition and repave) began Monday 10/7.
    • One lane closure at intersection.
    • Two-way traffic maintained at all times.

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

Ralston Street:

  • Between University Terrace and 11th Street – roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for minor utility work.

Ohm Place:

  • Roadwork is substantially complete.  Watch for flaggers and traffic controls that may be used for minor utility work.

Sierra Highlands:

  • Construction is on going and anticipated to continue thru the end of October.  Watch for flaggers and traffic controls that will be in place throughout construction on Sierra Highlands.

Hammil Lane:

  • Construction has begun and will continue thru the end of October.  Watch for flaggers and traffic controls that will be in place throughout construction.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Starting Monday, October 14 road closures will be in place for construction of the roundabout at the intersections of Virginia Street and Center Street/Mary Street. Businesses will always remain accessible.

Virginia Street:

  • Traffic is reduced to southbound direction only.
  • Northbound through traffic will be detoured from Holcomb Avenue to Center Street to Liberty Street. Drivers can also use northbound Haskell Street to Martin Street to Virginia Street.
  • Side streets, including Cheney Street, Moran Street, and Stewart Street, are also open for Midtown-business access.

Center Street:

  • Starting Monday, 10/14
  • ROAD CLOSURE: Center Street at Virginia Street.
  • Detours will be in place.

Mary Street:

  • Starting Monday, 10/14
  • Intermittent road closures: Mary Street at Virginia Street.
  • Detours will be in place.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

October 4, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are

Sunday 10/6/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd Coat Paint Application

Monday 10/7/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd Coat Paint Application
Greg Street: Franklin Way to I-80 Right of Way

Tuesday 10/8/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd Coat Paint Application
Greg Street: Franklin Way to I-80 Right of Way

Wednesday 10/9/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd Coat Paint Application
Greg Street: Franklin Way to I-80 Right of Way

Thursday 10/10/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd Coat Paint Application

Friday 10/11/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Various Project Streets: 2nd Coat Paint Application

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • Construction is on hold until signal equipment arrives mid-November.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

Construction closures and detours for the project will continue the week of October 7th. The project is expected to be complete by November.

Constuction on Sutro Street from McCarran to the northern terminus is underway.  Two-way traffic will be provided and flaggers will assist motorisits through the construction zone.
All detours will be marked.
This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

North Hills Blvd:

  • Possible construction work Saturday 10/5.
  • Two-way traffic maintained at all times.
  • Please share the road with bicyclists.
  • Paving operations (demolition and repave) starting on Thursday 10/10.
  • Between Golden Valley Rd and Beckwourth Dr:
    •  Traffic is shifted using the center turn lane as a travel lane
  • Between Beckwourth Dr and Buck Dr:
    • One lane-two way traffic with flaggers.
    • The night of wednesday 10/9 – Northbound lane closure, only southbound traffic allowed.
    •  Speed limit reduced to 25 MPH and traffic will be allowed on pulverized material (unpaved lane).

Hunter Lake/Foster Dr:

  • ROAD CLOSURE: Foster Dr (eastbound/westbound access) at Hunter Lake closed.  Detours in place.
  • Paving operations (demolition and repave) starting on Monday 10/7.
  • One lane closure at intersection.
  • Two-way traffic maintained at all times.
  • Traffic will be allowed on base material (unpaved lane).

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

Ralston St:

  • Between University Terrace and 11th St:
    • Striping Crews will be out the week of October 7th.  Traffic controls are in place along Ralston St.
  • Parking is prohibited within the Ralston St construction zones 7 am – 7 pm, Monday through Friday 10/7 thru 10/11.
  • During construction, access for trash pickup is provided on Tuesdays – place Green Waste cans out for pickup.  For street parking use nearby side streets; please adhere to the “no parking” restrictions.

Ohm Place:

  • Construction is in progress.
  • Full closure of Ohm Place the week of October 7th . Traffic controls will be in place with business detours for NV Energy offices.

Sierra Highlands:

  • Construction will begin the week of September 30 thru the end of October.  Traffic controls and flagger control will be in place on Sierra Highlands

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Construction is occurring within the Midtown areas.

  • Construction is occurring on South Virginia St between Plumb Ln and Mary St/Center St:
    • Traffic will be reduced to southbound only, northbound traffic will be detoured at Regency Wy to Center St.

For the most up to date information on traffic control, please visit the Virginia Street Website.  

September 26, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are

Saturday 9/28/2019
Traffic Signal Loop Replacement
Plumb Lane: Daniel Webster Drive to Arlington Avenue

Sunday 9/29/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Plumb Lane: Daniel Webster Drive to Arlington Avenue

Monday 9/30/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Tuesday 10/1/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Wednesday 10/2/2019
Slurry Seal
Eastlake Boulevard: US 395 Alternate to Little Washoe Lake Park

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Eastlake Boulevard: US 395 Alternate to Little Washoe Lake Park

Thursday 10/3/2019

NO WORK SCHEDULED

Friday 10/4/2019

NO WORK SCHEDULED

 

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

  • New traffic signal at the intersection of N Virginia Street and Lemmon Drive.
  • Construction is on hold until signal equipment arrives mid-November.

 

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

Construction closures and detours for the project will continue the week of September 30. The project is expected to be complete by November.
Lake Street will be closed to through traffic from Mill Street to the Truckee River bridge.  Northbound traffic will be detoured at Mill Street to Wells Avenue to Kuenzli Street.
1st Street open to westbound traffic only from Center Street to Lake Street.  Businesses within the construction zone will be provided southbound access at 2nd Street to westbound 1st Street.
Constuction on Sutro Street from McCarran to the northern terminus is underway.  Two-way traffic will be provided and flaggers will assist motorisits through the construction zone.
All detours will be marked.
This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

 

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

North Hills Blvd:

  • Demolition, sidewalk and drainage work with one lane closure.
  • Two-way traffic maintained at all times.
  • Please share the road with bicyclists.
  • Between Golden Valley Rd and Beckwourth Dr:
    • Traffic is shifted using the center turn lane as a travel lane.
  • Between Beckwourth Dr and Buck Dr:
    • One lane-two way traffic with flaggers.
    • TBA – Northbound lane closure, only southbound traffic allowed.

Hunter Lake/Foster Dr:

  • Demolition, sidewalk and drainage work with one lane closure at intersection.
  • Two-way traffic maintained at all times.

 

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

Ralston St:

  • Between University Terrace and 11th St:
    • Striping Crews will be out the week of September 30th.  Traffic controls are in place along Ralston St.
  • Parking is prohibited within the Ralston St construction zones 7 am – 7 pm, Monday through Friday 8/5 thru 10/1.
  • During construction, access for trash pickup is provided on Tuesdays – place Green Waste cans out for pickup.  For street parking use nearby side streets; please adhere to the “no parking” restrictions.

Ohm Place:

  • Construction is in progress.
  • Full closure of Ohm Place is in effect through the beginning of October. Traffic controls will be in place with business detours for NV Energy offices.

Sierra Highlands:

  • Construction will begin the week of September 30 thru the end of October.  Traffic control will be in place on Sierra Highlands.

 

 

SPARKS CONSOLIDATED 19-01 – 15TH STREET, FRANKLIN WAY, HULDA COURT, AND EL RANCHO DRIVE

Starting September 30, 2019, at 7:00 a.m. through Saturday October 5, 2019:
Drivers can expect the following road and lane closures. All detours will be marked.

Franklin Way Greg Street to Spice Island Drive:

  • Street will be closed to northbound traffic from Greg Street to Spice Island Drive while utilites are raised.  Nouthbound traffic will be detoured at Spice Island Drive to Purina Way to Greg Street.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Construction is occurring within the Midtown areas.

  • Construction is occurring between Plumb Ln and Mary St/Center St:
    • Traffic will be reduced to southbound only, northbound traffic will be detoured at Regency Wy to Center St.
  • The following side streets are also under construction and closed to through traffic, local access is provided:
    • Cheney St- between Virginia St and Center St
    • Caliente St – between Virginia St and Haskell St

For the most up to date information on traffic control, please visit the Virginia Street Website.  

September 19, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are

Friday 9/20
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Mesa Park Drive: Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Drive to Leroy Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Mesa Park Drive: Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Drive to Leroy Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Saturday 9/21
NO WORK SCHEDULED

Sunday 9/22
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Mesa Park Drive: Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Drive to Leroy Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Monday 9/23
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Beaumont Parkway: Avenida De Landa to Clubhouse Drive
Mesa Park Drive: Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Drive to Leroy Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Tuesday 9/24
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Wednesday 9/25
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Thursday 9/26
Slurry Seal
Plumb Lane: Daniel Webster Drive to Arlington Avenue

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Plumb Lane: Daniel Webster Drive to Arlington Avenue
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Friday 9/27
Slurry Seal
Plumb Lane: Daniel Webster Drive to Arlington Avenue

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Plumb Lane: Daniel Webster Drive to Arlington Avenue
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

  • New traffic signal at the intersection of N Virginia and Lemmon Drive.
  • Construction is on hold until signal equipment arrives mid-November.

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

Construction closures and detours for the project will continue the week of September 16. The project is expected to be complete by September 30.
Lake Street will be closed to through traffic from the Truckee River bridge to Second Street. Northbound traffic will be detoured at Mill Street to Wells Avenue to Kuenzli Street and at Liberty Street to Center Street. Southbound traffic will be detoured at Second Street to Virginia Street to Liberty Street to Sinclair Street. Businesses within the closure will be provided southbound access at 2nd Street to westbound 1st Street.
1st Street will be closed to through traffic from Center Street to Lake Street. Businesses within the closure will be provided southbound access at 2nd Street to westbound at 1st Street. Drivers will be able to access the Cal Neva parking garage using Second Street to Lover’s Lane Alley.
All detours will be marked.
This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

To learn more, please visit detours map.

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

North Hills Blvd:

  • Demolition, sidewalk and drainage work with one lane closure.
  • Two-way traffic maintained at all times.
  • Please share the road with bicyclists.
  • Between Golden Valley Rd and Beckwourth Dr:
    • Traffic is shifted using the center turn lane as a travel lane.
  • Between Beckwourth Dr and Buck Dr:
    • One lane-two way traffic with flaggers.
    • Starting Monday September 30 – northbound lane closure, only southbound traffic allowed.

Hunter Lake/Foster Dr:

  • Demolition, sidewalk and drainage work with one lane closure at intersection.
  • Two-way traffic maintained at all times.

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

Ralston St:

  • Between University Terrace and 11th St:
    • Construction is in progress through October 3, with concrete removal and replacement of sidewalk, curb/gutters, and roadway reconstruction. Traffic controls are in place along Ralston St.
  • Parking is prohibited within the Ralston St construction zones 7 am – 7 pm, Monday through Friday 8/5 thru 10/1.
  • During construction, access for trash pickup is provided on Tuesdays – place Green Waste cans out for pickup. For street parking use nearby side streets; please adhere to the “no parking” restrictions.

Ohm Place:

  • Construction is in progress.
  • Full closure of Ohm Place is in effect through the beginning of October. Traffic controls will be in place with business detours for NV Energy offices.

 

SPARKS CONSOLIDATED 19-01 – 15TH STREET, FRANKLIN WAY, HULDA COURT, AND EL RANCHO DRIVE

Starting September 16, 2019, at 7:00 a.m. through Saturday September 21, 2019:
Drivers can expect the following road and lane closures. All detours will be marked.

15th Street C Street to Prater Way:

  • Street will be closed to through traffic from C Street to Prater Way during raising utilities and striping. Northbound traffic will be detoured at C Street to 16th Street to Prater Way, or to at Victorian Avenue to Pyramid Way to Prater Way. Southbound traffic will be detoured at Prater Way to 16th Street to C Street or to Pyramid Way to Victorian Avenue. Businesses and residences within the closure will be provided southbound access from Prater Way and Northbound access from Victorian Avenue.
  • Franklin Way 15th Street C Street to Prater Way:
    Street will be closed to northbound traffic from Greg Street to Spice Island Drive during roadway removal.  Nouthbound traffic will be detoured at Spice Island Drive to Purina Way to Greg Street.

To learn more, please visit detours map.

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Construction is occurring within the Midtown areas.

  • Starting September 23, 2019 construction will continue northward on the western side of Virginia St to Mary St/Center St from Plumb Ln.
  • Between Plumb Ln and Mary St/Center St:
    • Traffic will be reduced to southbound only, northbound traffic will be detoured at Regency Wy to Center St.
  • The following side streets are also under construction and closed to through traffic, local access is provided:
    • Cheney St- between Virginia St and Center St
    • Stewart St – between Virginia St and Center St
    • Caliente St – between Virginia St and Haskell St

For the most up to date information on traffic control, please visit the Virginia Street Website.  

 

For the most up to date information on traffic control, please visit the Virginia Street Website.  

September 13, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Friday 9/13/2019
Slurry Seal
Ninth Street: Virginia Street to Evans Avenue
Ninth Street: Evans Avenue to Valley Road
Ninth Street: Wells Avenue to Shoshone Drive
Cabela Drive: Round-A-Bout to South Verdi Road
South Verdi Road: Verdi Court to Bridge Street
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Ninth Street: Virginia Street to Evans Avenue
Ninth Street: Evans Avenue to Valley Road
Ninth Street: Wells Avenue to Shoshone Drive
Cabela Drive: Round-A-Bout to South Verdi Road
South Verdi Road: Verdi Court to Bridge Street
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps
Lakeside Drive: Huffaker Lane to Bartley Ranch Regional Park Entrance
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)

Saturday 9/14/2019
Slurry Seal
Fifth Street: Ferrari Street to Cul-De-Sac
Depaoli Street: Fifth Street to Tacchino Street
Ferrari Street: Fourth Street to Fifth Street
Tacchino Street: Depaoli Street to Fourth Street
Ralston Street: Fifth Street to University Terrace
Ryland Street: Holcomb Avenue to Kirman Avenue

Sunday 9/15/2019
Slurry Seal
Vista Boulevard: Brierley Way to Prater Way

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Vista Boulevard: Brierley Way to Prater Way
Fifth Street: Ferrari Street to Cul-De-Sac
Depaoli Street: Fifth Street to Tacchino Street
Ferrari Street: Fourth Street to Fifth Street
Tacchino Street: Depaoli Street to Fourth Street
Ralston Street: Fifth Street to University Terrace
Ryland Street: Holcomb Avenue to Kirman Avenue
Ninth Street: Virginia Street to Evans Avenue
Ninth Street: Evans Avenue to Valley Road
Ninth Street: Wells Avenue to Shoshone Drive
Cabela Drive: Round-A-Bout to South Verdi Road
South Verdi Road: Verdi Court to Bridge Street
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps

Monday 9/16/2019

Slurry Seal
South Verdi Road: Verdi Court to Bridge Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
South Verdi Road: Verdi Court to Bridge Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Cabela Drive: Round-A-Bout to South Verdi Road
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps

 

Tuesday 9/17/2019

Slurry Seal
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway
Fifth Street: Ferrari Street to Cul-De-Sac
Depaoli Street: Fifth Street to Tacchino Street
Ferrari Street: Fourth Street to Fifth Street
Tacchino Street: Depaoli Street to Fourth Street
Ralston Street: Fifth Street to University Terrace
Ryland Street: Holcomb Avenue to Kirman Avenue
Cabela Drive: Round-A-Bout to South Verdi Road
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps

 

Wednesday 9/18/2019

Pavement Patching
Sky Vista Parkway: Trading Post Road to Vista Knoll Parkway

Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street+

Thursday 9/19/2019

Pavement Patching
Sky Vista Parkway: Trading Post Road to Vista Knoll Parkway

Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

 

Friday 9/20/2019
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Double R Boulevard: Damonte Ranch Parkway to South Meadows Parkway

 

Saturday 9/21/2019
Slurry Seal
Mesa Park Road: West Fourth Street to Mae Anne Avenue
Mae Anne Avenue: Mesa Park Road to La Salle Heights

 

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

The road is open with no controls.  Signal work that remains will occur later this year and may require traffic control for a short period of time.

 

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

New traffic signal at the intersection of N. Virginia and Lemmon Drive
Construction on hold until signal equipment arrives mid-November.

 

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

Construction closures and detours for the project will continue the week of September 16. The project is expected to be complete by September 30.
Lake Street will be closed to through traffic from the Truckee River bridge to Second Street. Northbound traffic will be detoured at Mill Street to Wells Avenue to Kuenzli Street and at Liberty Street to Center Street. Southbound traffic will be detoured at Second Street to Virginia Street to Liberty Street to Sinclair Street. Businesses within the closure will be provided southbound access at 2nd Street to westbound 1st Street.
1st Street will be closed to through traffic from Center Street to Lake Street. Businesses within the closure will be provided southbound access at 2nd Street to westbound at 1st Street. Drivers will be able to access the Cal Neva parking garage using Second Street to Lover’s Lane Alley.
All detours will be marked.
This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

To learn more, please visit detours map.

 

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

North Hills Blvd:

  • Demolition, sidewalk and drainage work with one lane closure.
  • Two-way traffic maintained at all times.
  • Please share the road to bicyclists.
  • One lane-two way traffic with flaggers between Buck Dr. and Beckwourth Dr.
  • Between Beckwourth Dr. and Golden Valley Rd. traffic is shifted using the center turn lane as a travel lane.
  • Access to the mail drop boxes may be closed for pipe work across the driveways.

Hunter Lake/Foster Dr:

  • Construction to start on Monday September 9th.

 

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

Ralston Street between University Terrace and 11th Street; Starting August 5th at 7:00 am thru October 3rd construction will be in progress with concrete removal and replacement for sidewalk and curb/gutters; roadway reconstruction. Traffic controls in place along Ralston Street.

For the safety of you and your vehicle, parking on the street will be prohibited within the Ralston Street construction zones from 7am-7pm, Monday through Friday from August 5th to the first of October. During construction, we will also provide access for trash pickup on Tuesdays – please place your Green Waste cans out on Tuesday for pickup. For additional street parking, a nearby side street must be used; please adhere to the “no parking” restrictions.

Ohm Place construction is schedule to begin Monday, 09/09, with partial cloure. Beginning the week of 09/16 full closure of Ohm Place will be in effect through the beginning of October.  Traffic controls will be in place with business detours for NV Energy offices.

 

 

SPARKS CONSOLIDATED 19-01 – 15TH STREET, FRANKLIN WAY, HULDA COURT, AND EL RANCHO DRIVE

Starting September 16, 2019, at 7:00 a.m. through Saturday September 21, 2019:
Drivers can expect the following road and lane closures. All detours will be marked.

15th Street C Street to Prater Way:

  • Street will be closed to through traffic from C Street to Prater Way during raising utilities and striping. Northbound traffic will be detoured at C Street to 16th Street to Prater Way, or to at Victorian Avenue to Pyramid Way to Prater Way. Southbound traffic will be detoured at Prater Way to 16th Street to C Street or to Pyramid Way to Victorian Avenue. Businesses and residences within the closure will be provided southbound access from Prater Way and Northbound access from Victorian Avenue.
  • Franklin Way 15th Street C Street to Prater Way:
    Street will be closed to northbound traffic from Greg Street to Spice Island Drive during roadway removal.  Nouthbound traffic will be detoured at Spice Island Drive to Purina Way to Greg Street.

To learn more, please visit detours map.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Construction is occurring from Plumb Ln through Mt Rose St and on select side streets within the Midtown areas.

  • Starting September 16, 2019 construction will continue northward on the western side of Virginia Street to Vassar St from Plumb Ln
    • Between Plumb Ln and Stewart St traffic will be reduced to southbound only, northbound traffic will be detoured at Regency Way to Vassar St.
        • Martin (between Virginia St and Haskell St)
        • Arroyo (between Virginia St and Haskell St)
        • Cheney (between Virginia St and Center St)
        • Stewart Street (between Virginia St and Center St)
        • Caliente Street (between Virginia St and Haskell St)The following side streets are also under construction and closed to through traffic, local access is provided:

For the most up to date information on traffic control, please visit the Virginia Street Website.  

September 5, 2019

2019 PREVENTIVE MAINTENANCE PROGRAM

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Saturday 9/7/2019
Slurry Seal
Vista Boulevard: Los Altos Parkway to Wingfield Parkway
Bible Way: Vassar Street to Mill Street
Mill Street: Kietzke Lane to I-580 On/Off Ramps
Third Street: Sierra Street to Vine Street
University Terrace: Vine Street to Sierra Street

Sunday 9/8/2019
Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Vista Boulevard: Los Altos Parkway to Wingfield Parkway
Bible Way: Vassar Street to Mill Street
Mill Street: Wells Avenue to I-580 On/Off Ramps
Third Street: Sierra Street to Vine Street
University Terrace: Vine Street to Sierra Street
Neil Road: Delucchi Lane to Marvel Way
Mira Loma Drive: McCarran Boulevard to Herons Landing
Greenbrae Drive: McCarran Boulevard to Howard Drive
Marietta Way: Glendale Avenue to End of Pavement

Monday 9/9/2019
Slurry Seal
Del Monte Lane: Bonde Lane to Viewcrest Drive
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Del Monte Lane: Bonde Lane to Viewcrest Drive
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)
Vista Boulevard: Los Altos Parkway to Wingfield Parkway

Tuesday 9/10/2019
Slurry Seal
Veterans Parkway: Truckee River Bridge to Clean Water Bridge
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Veterans Parkway: Truckee River Bridge to Clean Water Bridge
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)
Vista Boulevard: Los Altos Parkway to Wingfield Parkway
Bible Way: Vassar Street to Mill Street
Mill Street: Wells Avenue to I-580 On/Off Ramps
Third Street: Sierra Street to Vine Street
University Terrace: Vine Street to Sierra Street

Wednesday 9/11/2019
Slurry Seal
Lakeside Drive: Huffaker Lane to Bartley Ranch Regional Park Entrance
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Lakeside Drive: Huffaker Lane to Bartley Ranch Regional Park Entrance
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)
Del Monte Lane: Bonde Lane to Viewcrest Drive
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)
Vista Boulevard: Los Altos Parkway to Wingfield Parkway

Thursday 9/12/2019
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Cabela Drive: Round-A-Bout to South Verdi Road
South Verdi Road: Verdi Court to Bridge Street
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Cabela Drive: Round-A-Bout to South Verdi Road
South Verdi Road: Verdi Court to Bridge Street
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)

Friday 9/13/2019
Slurry Seal
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Cabela Drive: Round-A-Bout to South Verdi Road
South Verdi Road: Verdi Court to Bridge Street
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Seventh Street: Robb Drive to Washington Street
Seventh Street: Sierra Street to Virginia Street
Cabela Drive: Round-A-Bout to South Verdi Road
South Verdi Road: Verdi Court to Bridge Street
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps
Lakeside Drive: Huffaker Lane to Bartley Ranch Regional Park Entrance
Double Diamond Parkway: Double R Boulevard (North) to Double R Boulevard (South)

Saturday 9/14/2019
Slurry Seal
Fifth Street: Ferrari Street to Cul-De-Sac
Depaoli Street: Fifth Street to Tacchino Street
Ferrari Street: Fourth Street to Fifth Street
Tacchino Street: Depaoli Street to Fourth Street
Ralston Street: Fifth Street to University Terrace
Ryland Street: Holcomb Avenue to Kirman Avenue

Sunday 9/15/2019
Slurry Seal
Vista Boulevard: Brierley Way to Prater Way

Pavement Striping (Nightwork 7:00 PM to 5:00 AM)
Vista Boulevard: Brierley Way to Prater Way
Fifth Street: Ferrari Street to Cul-De-Sac
Depaoli Street: Fifth Street to Tacchino Street
Ferrari Street: Fourth Street to Fifth Street
Tacchino Street: Depaoli Street to Fourth Street
Ralston Street: Fifth Street to University Terrace
Ryland Street: Holcomb Avenue to Kirman Avenue
Seventh Street: Sierra Street to Virginia Street
Cabela Drive: Round-A-Bout to South Verdi Road
South Verdi Road: Verdi Court to Bridge Street
Boomtown-Garson Road: Cabela Drive to I-80 On/Off Ramps

 

 

CALIFORNIA AVENUE AND KEYSTONE AVENUE INTERSECTION ENHANCEMENT

The project is now substantially complete. Minor utility work is scheduled for the morning of Saturday September 7th. The road will remain open however the contractor may require a lane closure for a short period of time.

 

 

NORTH VALLEYS 3 INTERSECTION IMPROVEMENT PROJECT

New traffic signal at the intersection of N. Virginia and Lemmon Drive

Construction on hold until signal equipment arrives mid-November.

 

 

RENO CONSOLIDATED 19-01 – SUTRO STREET, LAKE STREET, FIRST STREET AND STATE STREET

Construction closures and detours for the project will continue Monday, September 9th. The project is expected to be complete by September 30.

Lake Street will be closed to through traffic from the Truckee River bridge to Second Street. Northbound traffic will be detoured at Mill Street to Wells Avenue to Kuenzli Street and at Liberty Street to Center Street. Southbound traffic will be detoured at Second Street to Virginia Street to Liberty Street to Sinclair Street. Businesses within the closure will be provided southbound access at 2nd Street to westbound 1st Street.

1st Street will be closed to through traffic from Center Street to Lake Street. Businesses within the closure will be provided southbound access at 2nd Street to westbound at 1st Street. Drivers will be able to access the Cal Neva parking garage using Second Street to Lover’s Lane Alley.

All detours will be marked.

This project is part of a larger project called Reno Consolidated 19-01, which will reconstruct and rehabilitate select Reno roadways identified for improvement or maintenance.

To learn more, please visit detours map.

 

 

RENO CONSOLIDATED 19-02 PROJECT – NORTH HILLS BOULEVARD FROM GOLDEN VALLEY ROAD TO BUCK DRIVE AND THE INTERSECTION OF HUNTER LAKE DRIVE AT FOSTER DRIVE

North Hills Blvd:

  • Demolition, sidewalk and drainage work with one lane closure.
  • Two-way traffic maintained at all times.
  • Please share the road to bicyclists.
  • One lane-two way traffic with flaggers between Buck Dr. and Beckwourth Dr.
  • Between Beckwourth Dr. and Golden Valley Rd. traffic is shifted using the center turn lane as a travel lane.
  • Access to the mail drop boxes may be closed for pipe work across the driveways.

Hunter Lake/Foster Dr:

  • Construction to start on Monday September 9th.

 

 

RENO CONSOLIDATED 19-03 PROJECT – SIERRA HIGHLANDS DRIVE, COLBERT DRIVE, HAMMILL LANE, RALSTON STREET, AND OHM PLACE

Ralston Street between University Terrace and 11th Street; Starting August 5th at 7:00 am thru October 3rd construction will be in progress with concrete removal and replacement for sidewalk and curb/gutters; roadway reconstruction. Traffic controls in place along Ralston Street.

For the safety of you and your vehicle, parking on the street will be prohibited within the Ralston Street construction zones from 7am-7pm, Monday through Friday from August 5th to the first of October. During construction, we will also provide access for trash pickup on Tuesdays – please place your Green Waste cans out on Tuesday for pickup. For additional street parking, a nearby side street must be used; please adhere to the “no parking” restrictions.

Ohm Place construction is schedule to begin Monday, 09/09, with partial cloure. Beginning the week of 09/16 full closure of Ohm Place will be in effect through the beginning of October.

 

 

SPARKS CONSOLIDATED 19-01 – 15TH STREET, FRANKLIN WAY, HULDA COURT, AND EL RANCHO DRIVE

Starting September 9, 2019, at 7:00 a.m. through Saturday September 14, 2019:

Drivers can expect the following road and lane closures. All detours will be marked.

15th Street closed Victorian Avenue to Prater Way:

  • Street will be closed to through traffic from Victorian Avenue to Prater Way during roadway removal and paving. Northbound traffic will be detoured at C Street to 16th Street to Prater Way, or at Victorian Avenue to Pyramid Way to Prater Way. Southbound traffic will be detoured at Prater Way to 16th Street to C Street or to Pyramid Way to Victorian Avenue. Businesses and residences within the closure will be provided southbound access from Prater Way and Northbound access from Victorian Avenue.
  • Saturday, September 14: Closed to all traffic from 7 a.m. – 7 p.m. for final paving operations.

 

To learn more, please visit detours map.

 

 

VIRGINIA STREET BUS RAPID TRANSIT EXTENSION

Construction is occurring from Plumb Ln through Mt Rose St and on select side streets within the Midtown areas.

  • Construction is occurring from Plumb Ln through Mt Rose St and on select side streets within the Midtown areas.
    • Between Plumb Ln and Mt Rose St traffic will be reduced to southbound only, northbound traffic will be detoured at Regency Way to Vassar St.
    • The following side streets are also under construction and closed to through traffic, local access is provided:
        • Martin (between Virginia St and Haskell St)
        • Arroyo (between Virginia St and Haskell St)
        • Cheney (between Virginia St and Center St)
        • Stewart Street (between Virginia St and Center St)
        • Caliente Street (between Virginia St and Haskell St)

      For the most up to date information on traffic control, please visit the Virginia Street Website.  

       

August 29, 2019

August 22, 2019

August 15, 2019

August 8, 2019

August 2, 2019

July 26, 2019

July 18, 2019

July 12, 2019

July 5, 2019

June 28, 2019

June 14, 2019

June 6, 2019

May 30, 2019

May 24, 2019

May 21, 2019

May 9, 2019

May 2, 2019

April 25, 2019

April 18, 2019

April 11, 2019

April 4, 2019

March 29, 2019

March 21, 2019

March 14, 2019

March 7, 2019

March 1, 2019

February 22, 2019

February 15, 2019

February 7, 2019

February 2, 2019

January 24, 2019

January 18, 2019

January 10, 2019

January 3, 2019

December 27, 2018

December 20, 2018

December 14, 2018

December 7, 2018

November 29, 2018

November 21, 2018

November 16, 2018

November 8, 2018

November 1, 2018

October 25, 2018

October 19, 2018

October 12, 2018

October 5, 2018

October 3, 2018

September 20, 2018

September 14, 2018

September 10, 2018

August 30, 2018