March 17, 2023

BUS STOP IMPROVEMENT & CONNECTIVITY PROGRAM – PHASE 4
RTC Project Manager, Kimberly Diegle, P.E.– (775) 335-1844

Weather permiting, lane and shoulder closures may be in place on North Virginia Street at Talus Way and Parr Boulevard; and on Glendale Avenue at Marietta Way.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Remaining construction will resume in April/May timeframe.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Construction crews working on installing steel tube fence, signal work and grade planters (weather permitting).

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours.
  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Construction crews are continuing to work on installing underground light conduit, retaining wall, signals and fence removals. Starting March 20th, additional construction crews will begin working on storm drain installation.
  • Mall Drive access closed until June. Detours to shopping center through Silverada and El Rancho accesses partially open (right-in/right-out) when feasible.
  • Starting Friday, March 17th (weather permitting) – new traffic pattern – travel lanes (one in each direction) shifted to the south side of Oddie Boulevard from Suillivan Road to east of US-395 ramps.
  • Northbound and southbound Silverada Boulevard at Oddie Boulevard will be closed two (2) days each from Monday, March 20th through Friday, March 24th. Oddie Boulevard will remain open with 2-way traffic. Detours in place along Silverada Boulevard.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Installation of illuminated street signs will resume in April.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

This project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Due to continued winter weather conditions, the underground utility relocation work and the construction of a retaining wall below Mesa Park Road will now resume in late March, weather permitting. The construction of the roundabout will begin this spring. Please observe all traffic controls, work zone speed limits and flaggers when construction is occurring.

 

March 10, 2023

BUS STOP IMPROVEMENT & CONNECTIVITY PROGRAM – PHASE 4
RTC Project Manager, Kimberly Diegle, P.E.– (775) 335-1844

Weather permiting, lane and shoulder closures may be in place on North Virginia Street at Talus Way and Parr Boulevard; and on Glendale Avenue at Marietta Way.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Remaining construction will resume in April/May timeframe.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing steel tube fence, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing underground light conduit, retaining wall, signals and fence removals (weather permitting)
  • Mall Drive access closed until June – Detours to shopping center through Silverada and El Rancho accesses partially open (right-in/right-out) when feasible
  • Starting Friday, March 17, 2023 (weather permitting) – new traffic pattern – travel lanes (one in each direction) shifted to the south side of Oddie Boulevard from Suillivan Road to east of US-395 ramps

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Installation of illuminated street signs will resume in April.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

This project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Due to continued winter weather conditions, the underground utility relocation work and the construction of a retaining wall below Mesa Park Road will now resume in late March, weather permitting. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Traffic Signal at Mill Street and Telegraph Street – signal is active. Please use caution driving through the intersection.

March 3, 2023

BUS STOP IMPROVEMENT & CONNECTIVITY PROGRAM – PHASE 4
RTC Project Manager, Kimberly Diegle, P.E.– (775) 335-1844

Lane and shoulder closures may be in place on North Virginia Street at Talus Way and Parr Boulevard; and on Glendale Avenue at Marietta Way.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Remaining construction will resume in April/May timeframe.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing steel tube fence, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing underground light conduit, retaining wall, signals and fence removals (weather permitting)
  • Mall Drive access closed until June – Detours to shopping center through Silverada and El Rancho accesses partially open (right-in/right-out) when feasible
  • Starting March 10, 2023 (weather permitting) – new traffic pattern – travel lanes (in each direction) shifted to the south side of the road from Sullivan to Silverada

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Installation of illuminated street signs will resume in March.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

This project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work and the construction of a retaining wall below Mesa Park Road will resume late February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Traffic Signal at Mill Street and Telegraph Street – signal is active. Please use caution driving through the intersection.

February 24, 2023

BUS STOP IMPROVEMENT & CONNECTIVITY PROGRAM – PHASE 4
RTC Project Manager, Kimberly Diegle, P.E.,– (775) 335-1844

Lane and shoulder closures will be in place on North Virginia Street at Talus Way and Parr Boulevard; and on Glendale Avenue at Marietta Way.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Remaining construction will resume in April/May timeframe.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing steel tube fence, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing underground light conduit, retaining wall, signals and fence removals (weather permitting)
  • Mall Drive access closed until June – Detours to shopping center through Silverada and El Rancho accesses partially open (right-in/right-out) when feasible

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Installation of illuminated street signs will resume in March.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

This project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work and the construction of a retaining wall below Mesa Park Road will resume late February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Traffic Signal at Mill Street and Telegraph Street – Signal is active. Please use caution driving through the intersection.

February 17, 2023

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout February.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing steel tube fence, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing underground light conduit, retaining wall, signals and fence removals (weather permitting)
  • Mall Drive access closed until June – Detours to shopping center through Silverada and El Rancho accesses

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company will have traffic control in place on Sparks Boulevard in the northbound and southbound directions between I80 and Greg Street for the installation of signal heads and traffic cameras.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

This project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work and the construction of a retaining wall below Mesa Park Road will resume late February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Traffic Signal at Mill Street and Telegraph Street – Signal will be active on Thursday, February 16th. Please use caution driving through the newly configured intersection.

February 10, 2023

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout February.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing steel tube fence, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing underground light conduit, retaining wall and signals and fence removals (weather permitting)
  • Mall Drive access closed until June – Detours to shopping center thru Silverada and El Rancho accesses

Pedestrian Bridge removal during the weekends of February 11th and 18th  –  Detours in place

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company will have traffic control in place on Sparks Boulevard in the northbound and southbound directions between I80 and Greg Street for the installation of signal heads and traffic cameras.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work will resume late February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Work resumes at the intersection of South Meadows Parkway and Wilbur May Parkway. Traffic signal will be active on Thursday, January 26, 2023. Drivers should anticipate lane and shoulder closures.

Traffic Signal at Mill Street and Telegraph Street – construction resumes at the intersection. Be advised for lane closures. Traffic signal expected to be ctive by the end of February.

February 3, 2023

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout February.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing steel tube fence, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing underground light conduit, retaining wall and signals (weather permitting)
  • Mall Drive access closed until June – Detours to shopping center thru Silverada and El Rancho accesses

Pedestrian Bridge removal during the weekends of February 11th and 18th  –  Detours in place

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company will have traffic control in place on Sparks Boulevard in the northbound direction just south of Greg Street until installation of signal heads is complete.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work will resume late February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Work resumes at the intersection of South Meadows Parkway and Wilbur May Parkway. Traffic signal will be active on Thursday, January 26, 2023. Drivers should anticipate lane and shoulder closures.

Traffic Signal at Mill Street and Telegraph Street – construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

January 27, 2023

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout January.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing privacy walls, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing underground light conduit, retaining wall and signals (weather permitting)

Pedestrian Bridge removal during the weekends of February 11th and 18th  –  Detours in place

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company will have traffic control in place on Sparks Boulevard in the northbound direction just south of Greg Street until installation of signal heads is complete.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work will resume later this month or early February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Work resumes at the intersection of South Meadows Parkway and Wilbur May. Traffic signal will be active on Thursday, January 26, 2023. Drivers should anticipate lane and shoulder closures.

Traffic Signal at Mill Street and Telegraph Street – construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

January 20, 2023

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout January.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing privacy walls, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on underground light conduit and signals (weather permitting)

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company will have traffic control in place on Sparks Boulevard in the northbound direction just south of Greg Street until installation of signal heads is complete.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVENUE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work will resume later this month or early February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Work resumes at the intersection of South Meadows at Wilbur May. Traffic signal will be active on Thursday, January 26, 2023. Drivers should anticipate lane and shoulder closures.

Traffic Signal at Mill Street and Telegraph Street, construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

January 13, 2023

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout January.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing privacy walls, signal work and grade planters (weather permitting)

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on underground light conduit and signals (weather permitting)

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company will have traffic control in place on Sparks Boulevard in the northbound direction just south of Greg Street until installation of signal heads is complete.

TE SPOT 10 – SOUTH PROJECT (ROUNDABOUT INSTALLATION AT WOODLAND AVE/4TH STREET)
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue began last fall. There is no construction occurring at this time. Weather permitting, underground utility relocation work will resume later this month or early February. The construction of the roundabout will begin this spring. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time. Work resumes in January. Drivers should anticipate lane and shoulder closures.

January 6, 2023

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout January.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on installing privacy walls, signal work and grade planters.

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on underground light conduit and signals

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company will have traffic control in place on Sparks Boulevard in the northbound direction just south of Greg Street until installation of signal head is complete.

TE SPOT 10 – SOUTH PROJECT (ROUNDAVOUT INSTALLATION AT WOODLAND AVE/4TH STREET
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is underway. Traffic lane shoulder closures and detours will occur at various times throughout the project. Please observe all traffic controls, work zone speed limits and flaggers when construction is occurring. Weather permitting, underground utility relocation work will occur during the winter. There is no work anticipated for the rest of the year. The construction of the roundabout will begin in the spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time. Work resumes in January. Drivers should anticipate lane and shoulder closures.

December 30, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout December.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Drive Safe!

Construction activities will resume January 3, 2023.

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on placing concrete sidewalk, installing privacy walls, signal work and grade planters.

Phase 2 & 3 – Sullivan Lane (Sparks) to Sutro Street (Reno):

  • Shoulder and lane closures during construction working hours
  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Construction crews working on underground light conduit and signals

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes along Sparks Boulevard between Lincoln Way and Greg Street. Daytime single-lane closures will be in place in both the northbound and southbound directions between Greg Street and the I-80 eastbound off-ramp. These closures and associated work are weather dependent.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT (ROUNDAVOUT INSTALLATION AT WOODLAND AVE/4TH STREET
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is underway. Traffic lane shoulder closures and detours will occur at various times throughout the project. Please observe all traffic controls, work zone speed limits and flaggers when construction is occurring. Weather permitting, underground utility relocation work will occur during the winter. There is no work anticipated for the rest of the year. The construction of the roundabout will begin in the spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time. Work resumes in January. Drivers should anticipate lane and shoulder closures.

December 23, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout December.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Happy Holidays! Drive Safe!

Construction activities will resume January 3, 2023.

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes along Sparks Boulevard between Lincoln Way and Greg Street. Daytime single-lane closures will be in place in both the northbound and southbound directions between Greg Street and the I-80 eastbound off-ramp. These closures and associated work are weather dependent.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT (ROUNDAVOUT INSTALLATION AT WOODLAND AVE/4TH STREET
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is underway. Traffic lane shoulder closures and detours will occur at various times throughout the project. Please observe all traffic controls, work zone speed limits and flaggers when construction is occurring. Weather permitting, underground utility relocation work will occur during the winter. There is no work anticipated for the rest of the year. The construction of the roundabout will begin in the spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time. Work resumes in January. Drivers should anticipate lane and shoulder closures.

December 16, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout December.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Paving operations: cycle track (weather permitting) with detours and half intersection closures at 12th Street and Rock Boulevard

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes along Sparks Boulevard between Lincoln Way and Greg Street. Daytime single-lane closures will be in place in both the northbound and southbound directions between Greg Street and the I-80 eastbound off-ramp. These closures and associated work are weather dependent.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT (ROUNDAVOUT INSTALLATION AT WOODLAND AVE/4TH STREET
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is underway. Traffic lane shoulder closures and detours will occur at various times throughout the project. Please observe all traffic controls, work zone speed limits and flaggers when construction is occurring. Weather permitting, underground utility relocation work will occur during the winter. There is no work anticipated this week. The construction of the roundabout will begin in the spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

December 9, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout December.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard
  • Paving operations (weather permitting) with detours and half intersection closures at 12th Street and Rock Boulevard

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes along Sparks Boulevard between Lincoln Way and Greg Street. Daytime single-lane closures will be in place in both the northbound and southbound directions between Greg Street and the I-80 eastbound off-ramp. These closures and associated work are weather dependent.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT (ROUNDAVOUT INSTALLATION AT WOODLAND AVE/4TH STREET
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is underway. Traffic lane shoulder closures and detours will occur at various times throughout the project. Please observe all traffic controls, work zone speed limits and flaggers when construction is occurring. Weather permitting, underground utility relocation work will occur during the winter. There is no work anticipated this week. The construction of the roundabout will begin in the spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

December 2, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout December.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Paving operations (weather permitting):
    • Detours – half intersection closures (south side) at Rock Boulevard and 12th Street from November 28th through December 9th

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes along Sparks Boulevard between Lincoln Way and Greg Street. Daytime and nighttime single-lane closures will be in place in both the northbound and southbound directions between Greg Street and the I-80 eastbound off-ramp. These closures and associated work are weather dependent.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT (ROUNDAVOUT INSTALLATION AT WOODLAND AVE/4TH STREET
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

The project that includes the construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is underway. Traffic lane shoulder closures and detours will occur at various times throughout the project. Please observe all traffic controls, work zone speed limits and flaggers when construction is occurring. Weather permitting, underground utility relocation work will occur during the winter. There is no work anticipated this week. The construction of the roundabout will begin in the spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

November 23, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout November.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction crews will be working on Saturdays through the end of November 2022.
  • Traffic changeover to new pavement, north side of Oddie Boulevard.
  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Milling and paving operations:
    • Intersections open during Thanksgiving Holiday
    • Detours – half intersection closures (south side) at Rock Boulevard and 12th Street from November 28th through December 9th

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes along Sparks Boulevard between Lincoln Way and Greg Street. Daytime and nighttime single-lane closures will be in place in both the northbound and southbound directions between Greg Street and the I-80 eastbound off-ramp.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT (ROUNDAVOUT INSTALLATION AT WOODLAND AVE/4TH STREET
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Traffic lane shoulder closures and detours will occur at various times throughout the project. Please observe all traffic control, work zone speed limits and flaggers when construction is occurring. There is no work anticipated this week. The construction of the roundabout will begin in the Spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

November 18, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout November.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction crews will be working on Saturdays through the end of November 2022.
  • Traffic changeover to new pavement, north side of Oddie Boulevard.
  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Milling and paving operations:
    • Detours – half intersection closures (south side) at Rock Boulevard and 12th Street from November 10th through December 2nd
    • Intersections open during Thanksgiving Holiday

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Project is completed.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes along Sparks Boulevard between Lincoln Way and Greg Street. Daytime and nighttime single-lane closures will be in place in both the northbound and southbound directions between Greg Street and the I-80 eastbound off-ramp.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Traffic lane shoulder closures and detours will occur at various times throughout the project. Currently, work includes relocation of overhead utilities to underground. Please observe all traffic control, work zone speed limits and flaggers. The construction of the roundabout will begin in the Spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

November 10, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway work will continue on Prater Way between Pyramid Way and 4th Street. Drivers should anticipate lane and shoulder closures throughout November.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction crews will be working on Saturdays through the end of November 2022.
  • Traffic changeover to new pavement, north side of Oddie Boulevard.
  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Milling and paving operations to start by mid-November:
    • Detours – half intersection closures at Rock Boulevard and 12th Street from November 10th thru December 2nd

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

On and off lane and shoulder closures are still in effect as the project is almost complete. The roadway will be fully open by end of November.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as the median along Sparks Boulevard between Lincoln Way and Greg Street. Daytime single-lane closures will be in place in the northbound direction between Greg Street and the I-80 eastbound off-ramp from 5:00 a.m. – 2:00 p.m. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Traffic lane shoulder closures and detours will occur at various times throughout the project. Currently, work includes relocation of overhead utilities to underground. Please observe all traffic control, work zone speed limits and flaggers. The construction of the roundabout will begin in the Spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment. No traffic control in place at this time.

November 4, 2022

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Beginning the week of September 26, 2022, Q&D will begin patching roadway and sidewalk at the following locations:

  • Sharlands Avenue from Robb Drive to Mae Anne Avenue.
  • Double R Boulevard from Sandhill Road to South Meadows Parkway.
  • Lane and shoulder closures will be in place for this work.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction crews will be working on Saturdays through the end of November 2022.
  • Underground work includes lighting conduits, planter and irrigation installation, form and pour sidewalk concrete and privacy wall installation (post and panels).
  • Traffic changeover to new pavement, north side of Oddie Boulevard.
  • One traffic lane in each direction will be maintained along Oddie Boulevard.
  • Milling and paving operations to start by mid-November:
    • Detours – half intersection closures at Rock Boulevard and 12th Street.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane will continue through November 2022. Detours will be in place around the vicinity of the project.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as the median along Sparks Boulevard between Lincoln Way and Greg Street. Daytime single-lane closures will be in place in the northbound direction between Greg Street and the I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

Drivers should expect delays during the morning commute, look for signs and traffic control devices; please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Traffic lane shoulder closures and detours will occur at various times throughout the project. Currently, work includes relocation of overhead utilities to underground. Utility work requiring some traffic control will be occurring during the week. Please observe all traffic control, work zone speed limits and flaggers. The construction of the roundabout will begin in the Spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is on hold for procurement of traffic signal equipment.  No traffic control in place at this time.

October 28, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This project is substantially complete.

2022 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

This project is substantially complete.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Beginning the week of September 26th Q&D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Q&D will also be patching roadway and small sections of sidewalk along Double R Boulevard from Sandhill Road to South Meadows Parkway. Lane and shoulder closures will be in place for this work.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction crews will work on Saturdays through the end of November 2022.
  • Underground work will include lighting conduits, planter and install irrigation, form and pour sidewalk concrete and install privacy wall (post and panels).
  • Traffic swap (to new pavement) north side of Oddie Boulevard
  • One lane in each direction will be maintained along Oddie Boulevard.
  • Milling and paving operations to start by mid-November:
    • Detours – Half intersection closures at Rock Boulevard and 12th Street

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.

Roadway pavement operations will begin on October 17th and end on October 28th. Peckham Lane, between S. Virginia Street and Baker Lane, will be closed. Business access to the Atlantis and Old Town Mall will be via S. Virginia Street. The intersection of Peckham Lane and Baker Lane will be intermittently closed.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

The free right turn lane from southbound Sparks Boulevard to westbound Greg Street is closed for the curing of concrete pavement. Trucks will be restricted from making this right turn movement and will be detoured to Greg Street via Vista Boulevard.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Lane, shoulder closures and detours will occur at various times throughout the project. Currently, work includes relocation of overhead utilities to underground. That work will continue through the end of October. Please observe all traffic control, work zone speed limits and flaggers. The construction of the roundabout will begin in the Spring of 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022. Lane and shoulder closures will be in place during work hours.

October 21, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The contractor has completed resurfacing operations and will be finalizing striping and utility raising activities. Traffic control will vary throughout the corridor. Slow down and expect delays.

PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday (10/24/2022)
No Work

Tuesday (10/25/2022)
No work

Wednesday (10/26/2022)
No Work

Thursday (10/27/2022)
No Work

Friday (10/28/2022)
No work

Note:  This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Beginning the week of September 26th Q&D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Q&D will also be patching roadway and small sections of sidewalk along Double R Boulevard from Sanhill to South Meadows. Lane and shoulder closures will be in place for this work.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures:
    • Pyramid Way – between 9:00 a.m. – 2:00 p.m.
    • Sullivan Lane and Rock Boulevard – during working hours
  • Rock Boulevard and 12th Street might have some intersection closures with detours.
    • 12th Street (southside) closure on Monday and Tuesday October 24th and October 25th
  • Construction crews working on Saturdays through the end of November 2022.
  • Underground work including underground lighting conduits, planter and install irrigation, form and pour sidewalk concrete and install privacy wall (post and panels)
  • Traffic Swap (to new pavement) north side of Oddie Boulevard
  • One lane in each direction will be maintained along Oddie Boulevard.
  • Milling and paving operations to start by mid-November.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.

Roadway pavement operations will begin on October 17th and end on October 28th. Peckham Lane between S. Virginia Street and Baker Lane will be closed. Business access to Atlantis and Old Town Mall will be via. S. Virginia Street. The intersection of Peckham Lane and Baker Lane will be intermittently closed.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

The free right turn lane from southbound Sparks Boulevard to westbound Greg Street is closed for the curing of concrete pavement. Trucks will be restricted from making this right turn movement and will be detoured to Greg Street via Vista Boulevard.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Lane, shoulder closures and detours will be in place. The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting spring 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022. Lane and shoulder closures will be in place during work hours.

October 14, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The contractor has completed resurfacing operations and will be finalizing striping and utility raising activities. Traffic control will vary throughout the corridor. Slow down and expect delays.

PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday (10/10/2022)
No Work

Tuesday (10/11/2022)
No work

Wednesday (10/12/2022)
No Work

Thursday (10/13/2022)
No Work

Friday (10/14/2022)
No work

Note:  This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Beginning the week of September 26th Q&D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Q&D will also be patching roadway and small sections of sidewalk along Double R Boulevard from Sanhill to South Meadows. Lane and shoulder closures will be in place for this work.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures:
    • Pyramid Way – between 9:00 a.m. – 2:00 p.m.
    • Sullivan Lane and Rock Boulevard – during working hours
  • Rock Boulevard and 12th Street might have some intersection closures with detours.
  • Construction crews working on Saturdays through the end of November 2022.
  • Underground work including underground lighting conduits, planter and install irrigation, form and pour sidewalk concrete and install privacy wall (post and panels)
  • Traffic Swap (to new pavement) north side of Oddie Boulevard.
  • One lane in each direction will be maintained along Oddie Boulevard.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.

Roadway pavement operations will begin on October 12th and end on October 21st. Peckham Lane between S. Virginia Street and Baker Lane will be closed. Business access to Atlantis and Old Town Mall will be via. S. Virginia Street. The intersection of Peckham Lane and Baker Lane will be intermittently closed.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

The free right turn lane from southbound Sparks Boulevard to westbound Greg Street will be closed for the placement and curing of concrete pavement. Trucks will be restricted from making this right turn movement and will be detoured to Greg Street via Vista Boulevard.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Engineering Manager, Doug Maloy, P.E. – (775) 335-1865

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Lane, shoulder closures and detours will be in place. The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting spring 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022. Lane and shoulder closures will be in place during work hours.

October 7, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The contractor has completed resurfacing operations and will be finalizing striping and utility raising activities. Traffic control will vary throughout the corridor. Slow down and expect delays.

PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday (10/10/2022)
No Work

Tuesday (10/11/2022)
No work

Wednesday (10/12/2022)
No Work

Thursday (10/13/2022)
No Work

Friday (10/14/2022)
No work

Note:  This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Beginning the week of September 26th Q&D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Q&D will also be patching roadway and small sections of sidewalk along Double R Boulevard from Sanhill to South Meadows. Lane and shoulder closures will be in place for this work.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures:
    • Pyramid Way – between 9:00 a.m. – 2:00 p.m.
    • Sullivan Lane and Rock Boulevard – during working hours
  • Rock Boulevard and 12th Street might have some intersection closures with detours.
  • Construction crews working on Saturdays from September 24th through November 26th.
  • Underground work including lighting conduits, storm drain, and install privacy wall (post and panels)
  • Traffic Swap (to new pavement) north side of Oddie Boulevard.
  • One lane in each direction will be maintained along Oddie Boulevard.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Lane, shoulder closures and detours will be in place. The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting spring 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022. Lane and shoulder closures will be in place during work hours.

September 30, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The contractor has completed resurfacing operations and will be finalizing striping and utility raising activities. Traffic control will vary throughout the corridor. Slow down and expect delays.

PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Monday (10/3/2022)
Utility Adjustments
– Northwood Boulevard: Tahoe Boulevard to Village Boulevard
– Incline Way: Country Club Drive to Southwood Boulevard
– Country Club Drive: Tahoe Boulevard to Mt. Rose Highway

Tuesday (10/4/2022)
No work

Wednesday (10/5/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Various project streets thermos punch list

Thursday (10/6/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Various project streets thermos punch list

Friday (10/7/2022)
No work

Note:  This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Beginning the week of September 26th Q&D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Lane closures will be in place for this work.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures:
    • Pyramid Way – between 9:00 a.m. – 2:00 p.m.
    • Sullivan Lane and Rock Boulevard – during working hours
  • Rock Boulevard and 12th Street might have some intersection closures with detours
  • Construction crews working on Saturdays from September 24th through November 26th
  • Underground work including lighting conduits, storm drain, and install privacy wall (post and panels)
  • Traffic Swap (to new pavement) north side of Oddie Boulevard
  • One lane in each direction will be maintained along Oddie Boulevard

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.

Peckham Lane between South Virginia Street and Baker Lane will be closed from 9/26 to 9/30 for emergency work on the Cochran Ditch. Business access to Atlantis and Old Town Mall will be provided via. South Virginia Street.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

Crews will be working Friday night (September 30) starting at 4:00 p.m. through Saturday morning at 6:00 a.m. During this time, single lane closures will occur on Sparks Boulevard between Lincoln Way and I-80. Drivers can expect slow moving traffic and delays through the work zone. Use of alternative routes are encouraged.

Starting Friday at 9:00 p.m. the I-80 eastbound and westbound ramps from Sparks Boulevard will be closed. Eastbound traffic will be detoured to Vista Boulevard. The northbound ramp will remain open. All ramps will be reopened by 6:00 a.m. Saturday.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Lane, shoulder closures and detours will be in place. The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting spring 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022. Lane and shoulder closures will be in place during work hours.

September 23, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The contractor has completed resurfacing operations and will be finalizing striping and utility raising activities. Traffic control will vary throughout the corridor. Slow down and expect delays.

PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Sunday (9/25/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Hunter Lake Drive:  Rodney Drive to Idlewild Drive

Monday (9/26/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Hunter Lake Drive:  Rodney Drive to Idlewild Drive
– Various project streets second coat

Tuesday (9/27/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
Various project streets second coat

Wednesday (9/28/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Various project streets second coat

Thursday (9/29/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Various project streets second coat

Friday (9/30/2022)
Utility Adjustments
Northwood Boulevard:  Tahoe Boulevard to Village Boulevard
Incline Way:  Country Club Drive to Southwood Boulevard
Country Club Drive:  Tahoe Boulevard to Mt. Rose Highway
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Various project streets second coat

Note:  This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is on temporary hold.

Beginning the week of September 26th Q& D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Lane closures will be in place for this work.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures:
    • Pyramid Way – between 9:00 a.m. – 2:00 p.m. and night work from 9:00 p.m. – 5:00 a.m.
    • Sullivan Lane and Rock Boulevard – during working hours
  • Rock Boulevard and 12th Street might have some intersection closures with detours
  • Construction crews working on Saturdays from September 24th through November 26th
  • Underground work including lighting conduits, storm drain, sidewalk subgrade and base grade, install privacy wall (post and panels)
  • Traffic Swap (to new pavement) north side of Oddie Boulevard
  • One lane in each direction will be maintained along Oddie Boulevard

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue has begun. Lane, shoulder closures and detours will be in place. The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting spring 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022.

September 16, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The contractor has completed resurfacing operations and will be finalizing striping and utility raising activities. Traffic control will vary throughout the corridor. Slow down and expect delays.

PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Sunday (9/18/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Mayberry Drive:  Fourth Street to Hunter Lake Drive
– Thomas Creek Road:  Holcomb Lane to Foothill Road

Monday (9/19/2022)
Micro-Surfacing
– Hunter Lake Drive:  Rodney Drive to Idlewild Drive
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Mayberry Drive:  Fourth Street to Hunter Lake Drive
– Hunter Lake Drive:  Rodney Drive to Idlewild Drive

Tuesday (9/20/2022)
Micro-Surfacing
-Hunter Lake Drive: Rodney Drive to Idlewild Drive
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
Hunter Lake Drive: Rodney Drive to Idlewild Drive

Wednesday (9/21/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
-Various project streets second coat

Thursday (9/22/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
-Various project streets second coat

Friday (9/23/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
-Various project streets second coat

Note:  This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction has moved to Gieger Grade from South Virginia to Veterans Parkway. Work is off the shoulder with no traffic control needed. The next portion will be on Veterans Parkway from Gieger Grade to Curti Ranch Road. Traffic control will be shoulder and lane closures for this portion.

Beginning the week of September 19th Q& D will begin patching roadway and sidewalk along Sharlands Avenue from Robb Drive to Mae Anne Avenue. Lane closures will be in place for this work.

MILL STREET COMPLETE PROJECT – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The project is substantially complete.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Pyramid Way Intermittent lane closure between 9:00 a.m. – 2:00 p.m.
    •  NVE will be doing night work from 9:00 pm until 5:30 am.
  • Traffic swap (to new pavement) north side of Oddie Boulevard starting Saturday, September 17.
  • One lane in each direction will be maintained along Oddie Boulevard.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022. Detours will be in place around the vicinity of the project.

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The project is substantially complete.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street. Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I-80 eastbound off-ramp. Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m. The Sparks Boulevard westbound off-ramp thru/left turn lane to southbound Sparks Boulevard will be closed until Monday, September 19, 2022, at 6:00 a.m.

Upcoming Marathon Shift Work:
Weekend Closure:  Friday, September 16, 2022, at 8:00 p.m. through Monday, September 19, 2022, at 6:00 a.m. Sparks Boulevard will be closed in the southbound direction from Lincoln Way to Greg Street and northbound from Greg Street to the I-80 westbound off-ramp. All on-ramps and off-ramps at Sparks Boulevard interchange (with the exception of the I-80 eastbound off-ramp, right turn) will be closed and traffic will be detoured to Vista Boulevard.

Drivers should expect delays during the morning commute, look for signs and traffic control devices. Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will commence September 14th. Lane, shoulder closures and detours will be in place. The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting spring 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022.

September 9, 2022

2022 CORRECTIVE MAINTENANCE PROJECT – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The contractor will continue Mill Street and fill operations, then transition to micro-surfacing.  Traffic will be reduced to one lane each direction and work area will be congested.  Slow down and expect delays.

2022 PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Friday (9/9/2022)
Micro-Surfacing
– Caughlin Parkway:  Sourdough Circle to Sawbuck Road
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– El Rancho Boulevard:  Victorian Avenue to Sullivan Lane
– Carville Drive:  Silverada Boulevard to Paradise Drive

Saturday (9/10/2022)
   No work

Sunday (9/11/2022)
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– First Street:  Center Street to Lake Street
– Fourth Street: Virginia Street to Evans Avenue
Carville Drive:  Silverada Boulevard to Paradise Drive
– Ralston Street:  University Terrace to Eleventh Street
– North Hills Boulevard:  Golden Valley Road to Buck Drive

Monday (9/12/2022)
Micro-Surfacing
– Mayberry Drive:  Fourth Street to Hunter Lake Drive
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– North Hills Boulevard:  Golden Valley Road to Buck Drive
– Caughlin Parkway:  Sourdough Circle to Sawbuck Road
– Mayberry Drive:  Fourth Street to Hunter Lake Drive

Tuesday (9/13/2022)
Micro-Surfacing
– Mayberry Drive:  Fourth Street to Hunter Lake Drive
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Caughlin Parkway:  Sourdough Circle to Sawbuck Road
– Mayberry Drive:  Fourth Street to Hunter Lake Drive

Wednesday (9/14/2022)
Micro-Surfacing
– Mayberry Drive:  Fourth Street to Hunter Lake Drive
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Mayberry Drive:  Fourth Street to Hunter Lake Drive

Thursday (9/15/2022)
Micro-Surfacing
– Mayberry Drive:  Fourth Street to Hunter Lake Drive
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Mayberry Drive:  Fourth Street to Hunter Lake Drive

Friday (9/16/2022)
Micro-Surfacing
– Hunter Lake Drive:  Rodney Drive to Idlewild Drive
– Somersett Ridge Parkway:  US Hwy 40 to Del Webb Parkway
Pavement Striping (night work – 7:00 p.m. – 7:00 a.m.)
– Hunter Lake Drive:  Rodney Drive to Idlewild Drive
– Somersett Ridge Parkway:  US Hwy 40 to Del Webb Parkway

Note:  This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will continue on Double R Boulevard between South Meadows Parkway and Sandhill Drive.  Lane closures are in place during this phase of the project.

MILL STREET COMPLETE PROJECT – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The project is substantially complete.

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Pyramid Way:  Intermittent lane closures between 9:00 a.m. – 2:00 p.m.
  • Paving operations are ongoing until Friday, September 16.
    – Rock Boulevard intersection (north side) closure with detour.
    – 12th Street intersection (north side) closure with detour.
    – Sullivan Lane:  Lane closures during construction hours.
  • Traffic swap (to new pavement) north side of Oddie Boulevard starting Saturday, September 17.
  • One lane in each direction will be maintained along Oddie Boulevard.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue through October 2022.  Detours will be in place around the vicinity of the project.

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The project is substantially complete.

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Lane and shoulder closures will be in place.

SPARKS BOULEVARD IMPROVEMENT PROJECT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes, as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street.  Nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street, and in the northbound direction between Greg Street and I-80 eastbound off-ramp.  Daytime single-lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

Upcoming Marathon Shift Work:

Weekend Closure 1:  Friday, September 9, 2022, 8:00 p.m. through Monday, September 12, 2022,  6:00 a.m. – Sparks Boulevard will be closed in the southbound direction from Lincoln Way to the I-80 eastbound off-ramp.  All northbound traffic will remain open.  Traffic will be detoured to and from Sparks Boulevard through Lincoln Way to Lillard Drive/Brierley Way to Vista Boulevard.

Weekend Closure 2:  Friday, September 16, 2022, 8:00 p.m. through Monday, September 19, 2022, 6:00 a.m. – Sparks Boulevard will be closed in the southbound direction from Lincoln Way to Greg Street and northbound from Greg Street to the I-80 westbound off-ramp.  All on-ramps and off-ramps at Sparks Boulevard interchange (with the exception of the I-80 eastbound off-ramp, right turn) will be closed and traffic will be detoured to Vista Boulevard.

Drivers should expect delays during the morning commute.  Look for signs and traffic control devices.  Please drive with caution.

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is delayed until September 12, 2022.  Lane closures and detours will be in place.  The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting spring 2023.

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through October 2022.

September 2, 2022

2022 CORRECTIVE MAINTENANCE – ROCK BOULEVARD FROM MCCARRAN TO THE TRUCKEE RIVER BRIDGE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

The contractor will begin mill and fill operations on Tuesday, September 6, 2022, working from the Truckee River bridge.  Traffic will be reduced to one lane each direction.  Expect delays.

 

2022 PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Friday 9/2/2022

Micro-Surfacing
El Rancho Boulevard: Victorian Avenue to Sullivan Lane
Carville Drive: Silverada Boulevard to Paradise Drive

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
El Rancho Boulevard Victorian Avenue to Sullivan Lane
Carville Drive: Silverada Boulevard to Paradise Drive

Saturday 9/3/2022

No Work

Sunday 9/4/2022

No Work

Monday 9/5/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Southeast Connector: Pembroke Drive to Clean Water Way
El Rancho Boulevard: Victorian Avenue to Sullivan Lane

Tuesday 9/6/2022

Micro-Surfacing
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street
Third Street: Sierra Street to Vine Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
El Rancho Boulevard: Victorian Avenue to Sullivan Lane
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street
Third Street: Sierra Street to Vine Street

Wednesday 9/7/2022

Micro-Surfacing
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Carville Drive: Silverada Boulevard to Paradise Drive
Ralston Street: University Terrace to Eleventh Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
El Rancho Boulevard: Victorian Avenue to Sullivan Lane
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Carville Drive: Silverada Boulevard to Paradise Drive
Ralston Street: University Terrace to Eleventh Street

Thursday 9/8/2022

Micro-Surfacing
North Hills Boulevard: Golden Valley Road to Buck Drive

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
North Hills Boulevard: Golden Valley Road to Buck Drive

Friday 9/9/2022

Micro-Surfacing
Caughlin Parkway: Sourdough Circle to Sawbuck Road

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
El Rancho Boulevard: Victorian Avenue to Sullivan Lane
Carville Drive: Silverada Boulevard to Paradise Drive

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PHASE 4 
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will continue on Double R Boulevard between South Meadows Parkway and Sandhilll Drive. Lane closures are in place during this phase of the project.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

The project is substantially complete.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Pyramid Way: intermittent lane closures between 9:00 a.m. – 2:00 p.m.
  • Paving Operations are ongoing until Friday, September 16, 2022.
    • Rock Boulevard Intersection (north side) closure with detour
    • 12th Street Intersection (north side) closure with detour
    • Sullivan Lane: lane closures during construction hours

One lane in each direction will be maintained along Oddie Boulevard.

For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

PECKHAM LANE REHABILITATION
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway Rehabilitation of Peckham Lane between South Virginia Street and Baker Lane have begun and will continue till Mid-October 2022. Detours will be in place around the vicinity of the project.

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022, for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

The project is substantially complete.

 

SKY VISTA WIDENING AND REHABILITATION
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

Construction Sky Vista project will begin August 15, 2022.  Lane and shoulder closures will be in place.

 

SPARKS BOULEVARD IMPROVEMENT – SOUTH PHASE
RTC Project Manager, Amanda Callegari, P.E. – (775) 335-1881

Granite Construction Company is working in both the southbound and northbound lanes as well as outside shoulders along Sparks Boulevard between Lincoln Way and Greg Street nightly lane closures will reduce traffic to one lane in the southbound direction between Lincoln Way and Greg Street and in the northbound direction between Greg Street and I80 eastbound off-ramp. Daytime single lane closures will also be in place on Sparks Boulevard in the southbound direction between Kleppe Lane and Greg Street from 10:00 a.m. to 6:00 p.m.

Upcoming marathon shift work:
Weekend Closure 1: Friday, September 9, 2022, at 8:00 p.m. through Monday, September 12, 2022, at 6:00 a.m.

Sparks Boulevard will be closed in the southbound direction from Lincoln Way to the I-80 eastbound off-ramp. All northbound traffic will remain open. Traffic will be detoured to and from Sparks Boulevard through Lincoln Way to Lillard Drive/Brierley Way to Vista Boulevard.

Weekend Closure 2: Friday, September 16, 2022, at 8:00 p.m. through Monday, September 19, 2022, at 6:00 a.m. Sparks Boulevard will be closed in the southbound direction from Lincoln Way to Greg Street and northbound from Greg Street to the I-80 westbound off-ramp. All on-ramps and off-ramps at Sparks Boulevard Interchange (with the exception of the I80 eastbound off-ramp right turn) will be closed and traffic will be detoured to Vista Boulevard.

Drivers should expect delays during the morning commute, look for signs and traffic control devices; please drive with caution.

 

TE SPOT 10 – SOUTH
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue is delayed until September 12, 2022.  Lane closures and detours will be in place.  The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting Spring 2023.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction continues through September 2022.

August 19, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Sunday 8/21/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Mill Street: Terminal Way to McCarran Boulevard

Monday 8/22/2022

Micro-Surfacing
Mill Street: Terminal Way to McCarran Boulevard
E Prater Way: Vista Boulevard to City Limits
Boxington Way: Lincoln Way to Lillard Drive
Purina Way: Spice Islands Drive to Greg Street
Snider Way: Stanford Way to Steneri Way
Spice Islands Court: Spice Islands Drive to Cul De Sac

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Mill Street: Terminal Way to McCarran Boulevard
E Greenbrae Drive: Stanford Way to McCarran Boulevard
Franklin Way: Spice Islands Drive to Kleppe Lane
Boxington Way: Lincoln Way to Lillard Drive
Purina Way: Spice Islands Drive to Greg Street
Snider Way: Stanford Way to Steneri Way
Spice Islands Court: Spice Islands Drive to Cul De Sac

Tuesday 8/23/2022

Micro-Surfacing
15th Street: C Street to Prater Way
Deming Way: Spice Islands Drive to End
Dermody Way: Glendale Avenue to End
Hulda Court: Hulda Way to End

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Mill Street: Terminal Way to McCarran Boulevard
E Greenbrae Drive: Stanford Way to McCarran Boulevard
Franklin Way: Spice Islands Drive to Kleppe Lane
15th Street: C Street to Prater Way
Deming Way: Spice Islands Drive to End
Dermody Way: Glendale Avenue to End
Hulda Court: Hulda Way to End

Wednesday 8/24/2022

Micro-Surfacing
Southeast Connector: Pembroke Drive to Clean Water Way

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Southeast Connector: Pembroke Drive to Clean Water Way
Mill Street: Terminal Way to McCarran Boulevard
15th Street: C Street to Prater Way
Deming Way: Spice Islands Drive to End
Dermody Way: Glendale Avenue to End
Hulda Court: Hulda Way to End

Thursday 8/25/2022

Micro-Surfacing
Southeast Connector: Pembroke Drive to Clean Water Way

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Southeast Connector: Pembroke Drive to Clean Water Way
Boxington Way: Lincoln Way to Lillard Drive
Purina Way: Spice Islands Drive to Greg Street
Snider Way: Stanford Way to Steneri Way
Spice Islands Court: Spice Islands Drive to Cul De Sac

Friday 8/26/2022

Micro-Surfacing
Southeast Connector: Pembroke Drive to Clean Water Way

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Southeast Connector: Pembroke Drive to Clean Water Way
15th Street: C Street to Prater Way
Deming Way: Spice Islands Drive to End
Dermody Way: Glendale Avenue to End
Hulda Court: Hulda Way to End

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will continue on Geiger Grade from S. Virginia to Veteran’s Parkway. Shoulder closures are possible during this phase of the project.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Wyoming Avenue. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction is nearing completion on this project and will address final cleanup and landscape issues throughout the project limits from Terminal Way to McCarran Boulevard. There will be isolated closures in the outside lanes. The southbound to westbound turnpocket at McCarran Boulevard will be closed for paving.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews constructing sidewalk, curb and gutter, grade planter/landscape and road median.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Pyramid Way: intermittent lane closures between 9:00 a.m. – 2:00 p.m.
    • Paving Operations starting Monday, August 29, 2022  until Friday, Septemeber 16, 2022.
      • Rock Intersection (north side) closure with detour
      • 12th Intersection (north side) closure with detour
      • Sullivan: lane closures during construction hours

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway Rehabilitation of Peckham Lane between S. Vriginia Street and Baker Lane have begun and will continue till Mid-October 2022. Detours will be in place around the vicinity of the project.

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Two way traffic is back!
Paving and striping have been completed. The contractor will be making some repairs in various locations so continue to expect some traffic control activities throughout the project.

 

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction Sky Vista project will begin August 15, 2022.  Lane and shoulder closures will be in place.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin August 22, 2022. Lane closures and detours will be in place. The first phase of this project will be relocation of overhead utilities to underground with the roundabout construction starting Spring 2023.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street is on-going with other construction on the Mill Street project. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin August 2022.

August 12, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Sunday 8/14/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Terminal Way: Plumb Lane to Mill Street

Monday 8/15/2022

Pavement Patching
Mill Street: Terminal Way to McCarran Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Terminal Way: Plumb Lane to Mill Street
E Lincoln Way: Stanford Way to McCarran Boulevard
E Lincoln Way: Sparks Boulevard to Lillard Drive

Tuesday 8/16/2022

Pavement Patching
Mill Street: Terminal Way to McCarran Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Terminal Way: Plumb Lane to Mill Street
E Lincoln Way: Stanford Way to McCarran Boulevard
E Lincoln Way: Sparks Boulevard to Lillard Drive
Lillard Drive: Brierley Way to Prater Way

Wednesday 8/17/2022

Micro-Surfacing
E Prater Way: Sparks Boulevard to City Limits

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
E Prater Way: Sparks Boulevard to City Limits
Lillard Drive: Brierley Way to Prater Way

Thursday 8/18/2022

Micro-Surfacing
Mill Street: Terminal Way to McCarran Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Mill Street: Terminal Way to McCarran Boulevard
Lillard Drive: Brierley Way to Prater Way

Friday 8/19/2022

Micro-Surfacing
Mill Street: Terminal Way to McCarran Boulevard
E Greenbrae Drive: Stanford Way to McCarran Boulevard
Franklin Way: Spice Islands Drive to Kleppe Lane

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Mill Street: Terminal Way to McCarran Boulevard
E Greenbrae Drive: Stanford Way to McCarran Boulevard
Franklin Way: Spice Islands Drive to Kleppe Lane

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to began July 25, 2022 on Sharlands Avenue from Robb Drive to Mae Anne Avenue. Shoulder or lane closures are possible.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Wyoming Avenue. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction is nearing completion on this project and will address final cleanup and landscape issues throughout the project limits from Terminal Way to McCarran Boulevard. There will be isolated closures in the outside lanes. The southbound to westbound turnpocket at McCarran Boulevard will be closed for paving.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are installing light pole bases, constructing sidewalk, curb and gutter, grade planter/landscape and road median.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Pyramid Way: Lane closure between 9:00 a.m. – 2:00 p.m.
    • Paving Operations starting Monday, August 29, 2022  until Friday, Septemeber 16, 2022.
      • Rock Intersection closure with detour
      • 12th Intersection closure with detour
      • Sullivan lane closure

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

PECKHAM LANE REHABILITATION PROJECT
RTC Project Manager, Andrew Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Roadway Rehabilitation of Peckham Lane between S. Vriginia Street and Baker Lane will begin on August 15th, 2022. Detours will be in place around the vicinity of the project.

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Two way traffic is back!
Paving and striping have been completed. The contractor will be making some repairs in various locations so continue to expect some traffic control activities throughout the project.

 

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction Sky Vista project will begin August 15, 2022.  Lane and shoulder closures will be in place.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin August 15, 2022. Lane closures and detours will be in place.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street is on-going with other construction on the Mill Street project. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin August 2022.

August 5, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Sunday 8/7/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Incline Way: Country Club Drive to Southwood Boulevard
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Monday 8/8/2022

Micro-Surfacing
Terminal Way: Plumb Lane to Mill Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Terminal Way: Plumb Lane to Mill Street
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Tuesday 8/9/2022

Micro-Surfacing
E Prater Way: Sparks Boulevard to City Limits

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
E Prater Way: Sparks Boulevard to City Limits
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Wednesday 8/10/2022

Micro-Surfacing
E Greenbrae Drive: Stanford Way to McCarran Boulevard
Franklin Way: Spice Islands Drive to Kleppe Lane

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
E Greenbrae Drive: Stanford Way to McCarran Boulevard
Franklin Way: Spice Islands Drive to Kleppe Lane
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Thursday 8/11/2022

Micro-Surfacing
E Lincoln Way: Stanford Way to McCarran Boulevard
E Lincoln Way: Sparks Boulevard to Lillard Drive

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
E Lincoln Way: Stanford Way to McCarran Boulevard
E Lincoln Way: Sparks Boulevard to Lillard Drive
Terminal Way: Plumb Lane to Mill Street

Friday 8/12/2022

Micro-Surfacing
Lillard Drive: Brierley Way to Prater Way

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
E Lincoln Way: Stanford Way to McCarran Boulevard
E Lincoln Way: Sparks Boulevard to Lillard Drive
Lillard Drive: Brierley Way to Prater Way

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to began July 25, 2022 on Sharlands Avenue from Robb Drive to Mae Anne Avenue. Shoulder or lane closures are possible.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Wyoming Avenue. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Between Rock and McCarran there is work happening at the Edison intersection and the outside southbound lane will be closed.  Expect delays during the morning and afternoon rush and consider alternate routes.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing  privacy screens’, panels installation, retaining curb, installing light pole bases, constructing sidewalk, curb and gutter and grade planter/landscape.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Paving Operations starting Monday August 22, 2022.

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Two way traffic is back!
Paving and striping have been completed. The contractor will be making some repairs in various locations so continue to expect some traffic control activities throughout the project.

 

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction Sky Vista project will begin August 15, 2022.  Lane and shoulder closures will be in place.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin August 15, 2022. Lane closures and detours will be in place.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street is on-going with other construction on the Mill Street project. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin August 2022.

July 29, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Sunday 7/31/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Incline Way: Country Club Drive to Southwood Boulevard
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Monday 8/1/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Incline Way: Country Club Drive to Southwood Boulevard
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Tuesday 8/2/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Incline Way: Country Club Drive to Southwood Boulevard
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Wednesday 8/3/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Incline Way: Country Club Drive to Southwood Boulevard
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Thursday 8/4/2022

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Incline Way: Country Club Drive to Southwood Boulevard
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to began July 25, 2022 on Sharlands Avenue from Robb Drive to Mae Anne Avenue. Shoulder or lane closures are possible.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Wyoming Avenue. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Between Rock and McCarran there is work happening at the Edison intersection and the outside southbound lane will be closed.  Expect delays during the morning and afternoon rush and consider alternate routes.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing  privacy screens’ footing excavation, posts/panels installation, retaining curb, installing light pole bases, constructing curb and gutter and grade planter/landscape.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Two way traffic is back!  Paving and striping have been completed.  The contractor will be making some repairs in various locations so continue to expect some traffic control activities throughout the project.

 

SKY VISTA WIDENING AND REHABILITATION PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction Sky Vista project will begin August 15, 2022.  Lane and shoulder closures will be in place.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin August 15, 2022. Lane closures and detours will be in place.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street is on-going with other construction on the Mill Street project. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin August 2022.

July 22, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Sunday 7/24

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
La Posada Drive: Cordoba Boulevard to End of Curb
Greenbrae Drive: El Rancho Boulevard to Rock Boulevard

Monday 7/25

Micro-Surfacing
Northwood Boulevard: Tahoe Boulevard to Village Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Peckham Lane: Virginia Street to Longley Lane

Tuesday 7/26

Micro-Surfacing
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Chip Sealing
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Peckham Lane: Virginia Street to Longley Lane
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Wednesday 7/27

Pavement Patching
Terminal Way: Plumb Lane to Mill Street

Micro-Surfacing
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Thursday 7/28

Pavement Crack Sealing
Terminal Way: Plumb Lane to Mill Street

Micro-Surfacing
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Friday 7/29

Micro-Surfacing
Incline Way: Country Club Drive to Southwood Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Terminal Way: Plumb Lane to Mill Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Incline Way: Country Club Drive to Southwood Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Terminal Way: Plumb Lane to Mill Street

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin July 25, 2022 on Sharlands Avenue from Robb Drive to Mae Anne Avenue. Shoulder or lane closures are possible.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row between Apollo Way and Wyoming Avenue is closed to through traffic. Downhill traffic is detoured at Apollo Way back to Wyoming Avenue.
  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Apollo Way. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Expect delays during the morning and afternoon rush and consider alternate routes. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Intermittent lane closures on Pyramid Way.

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway. This week the contractor continues removing drives and sidewalk to be improved. Forming and pouring new sidewalk, curb and gutter will begin.

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin August 15, 2022. Lane closures and detours will be in place.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street is on-going with other construction on the Mill Street project. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin July 2022.

July 15, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Sunday 7/17

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Clean Water Way: McCarran Boulevard to Cor Soi
Mill Street: Rock Boulevard to McCarran Boulevard
Terminal Way: Mill Street to Plumb Lane
Peckham Lane: Virginia Street to Longley Lane

Monday 7/18

Micro-Surfacing
La Posada Drive: Cordoba Boulevard to End of Curb

Micro-Milling
Incline Way: Country Club Drive to Southwood Boulevard

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Mayberry Drive: Fourth Street to Hunter Lake Drive
Third Street: Sierra Street to Vine Street
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Ralston Street: University Terrace to Eleventh Street
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street

Tuesday 7/19

Micro-Surfacing
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Micro-Milling
Incline Way: Country Club Drive to Southwood Boulevard
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Mayberry Drive: Fourth Street to Hunter Lake Drive
Third Street: Sierra Street to Vine Street
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Ralston Street: University Terrace to Eleventh Street
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Circuit Court: Isidor Court. to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Wednesday 7/20

Micro-Surfacing
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Micro-Milling
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Mayberry Drive: Fourth Street to Hunter Lake Drive
Third Street: Sierra Street to Vine Street
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Ralston Street: University Terrace to Eleventh Street
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Thursday 7/21

Micro-Surfacing
La Posada Drive: Cordoba Boulevard to End of Curb
Peckham Lane: Virginia Street to Longley Lane

Micro-Milling
Terminal Way: Plumb Lane to Mill Street

Chip Sealing
Incline Way: Country Club Drive to Southwood Boulevard

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Robb Drive: Sharlands Avenue to Las Brisas Boulevard
Mayberry Drive: Fourth Street to Hunter Lake Drive
Third Street: Sierra Street to Vine Street
First Street: Center Street to Lake Street
Fourth Street: Virginia Street to Evans Avenue
Ralston Street: University Terrace to Eleventh Street
State Street: Virginia Street to Holcomb Avenue
Sutro Street: Commercial Row to Fourth Street

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
La Posada Drive: Cordoba Boulevard to End of Curb
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way
Peckham Lane: Virginia Street to Longley Lane

Friday 7/22

Micro-Surfacing
Greenbrae Drive: El Rancho Boulevard to Rock Boulevard
Victorian Ave: Prater Way to El Rancho Boulevard
Peckham Lane: Virginia Street to Longley Lane

Micro-Milling
Terminal Way: Plumb Lane to Mill Street

Chip Sealing
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
La Posada Drive: Cordoba Boulevard to End of Curb
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Ct. to Academy Way
Greenbrae Drive: El Rancho Boulevard to Rock Boulevard
Victorian Avenue: Prater Way to El Rancho Boulevard
Peckham Lane: Virginia Street to Longley Lane

Saturday 7/23

Micro-Milling
Terminal Way: Plumb Lane to Mill Street

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin July 18, 2022 on Sharlands Avenue from Robb Drive to Mae Anne Avenue. Shoulder or lane closures are possible.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row between Apollo Way and Wyoming Avenue is closed to through traffic. Downhill traffic is detoured at Apollo Way back to Wyoming Avenue.
  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Apollo Way. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – MILL STREET FROM TERMINAL WAY TO MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Expect delays during the morning and afternoon rush and consider alternate routes. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Intermittent lane closures on Pyramid Way.

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway. This week the contractor continues removing drives and sidewalk to be improved. Forming and pouring new sidewalk, curb and gutter will begin.

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 25, 2022.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street is on-going with other construction on the Mill Street project. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin July 2022.

July 8, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Monday 7/11

Micro-Surfacing
Veterans Parkway Multi-Use Path

Pavement Patching – Grinder Patch
Peckham Lane: Virginia Street to Longley Lane
Terminal Way: Plumb Lane to Mill Street

Pavement Striping
Eastlake Boulevard: Cattleguard to Coyote Drive

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Boxington Way: Lincoln Way to Lillard Drive
Deming Way: Spice Islands Drive to End
E Lincoln Way: Stanford Way to McCarran Boulevard
E Lincoln Way: Sparks Boulevard  to Lillard Drive
E Prater Way: Sparks Boulevard to City Limits
Franklin Way: Spice Islands Drive to Kleppe Lane
Hulda Court: Hulda Way to End
Lillard Drive: Brierley Way to Prater Way
Purina Way: Spice Islands Drive to Greg Street
United Circle: Spice Islands Drive to Spice Islands Drive

Tuesday 7/12

Micro-Surfacing
Veterans Parkway Multi-Use Path

Pavement Patching – Grinder Patch
Fourth Street: Virginia Street to Evans Avenue
State Street: Virginia Street to Holcomb Avenue

Pavement Striping
Veterans Parkway Multi-Use Path

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
15th Street: C Street to Prater Way
Boxington Way: Lincoln Way to Lillard Drive
Deming Way: Spice Islands Drive to End
Dermody Way: Glendale Avenue to End
E Lincoln Way: Stanford Way to McCarran Boulevard
E Lincoln Way: Sparks Boulevard to Lillard Drive
E Prater Way: Sparks Boulevard to City Limits
Franklin Way: Spice Islands Drive to Kleppe Lane
Greenbrae Drive: El Rancho Boulevard to Rock Boulevard
Hulda Court: Hulda Way to End
Lillard Drive: Brierley Way to Prater Way
Purina Way: Spice Islands Drive to Greg Street
Snider Way: Stanford Way to Steneri Way
Spice Islands Court: Spice Islands Drive to Cul De Sac
United Circle: Spice Islands Drive to Spice Islands Drive

Wednesday 7/13

Micro-Surfacing
Veterans Parkway Multi-Use Path

Pavement Patching – Grinder Patch
La Posada Drive: Cordoba Boulevard to End of Curb

Pavement Patching – Hand Patch
Isidor Court: Circuit Court to Academy Way
Distribution Drive: Calle De La Plata to Isidor Court

Pavement Striping
Veterans Parkway Multi-Use Path

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
15th Street: C Street to Prater Way
Deming Way: Spice Islands Drive to End
Dermody Way: Glendale Avenue to End
Franklin Way: Spice Islands Drive to Kleppe Lane
Hulda Court: Hulda Way to End
Lillard Drive: Brierley Way to Prater Way
Purina Way: Spice Islands Drive to Greg Street
Snider Way: Stanford Way to Steneri Way
Spice Islands Court: Spice Islands Drive to Cul De Sac
United Circle: Spice Islands Drive to Spice Islands Drive
Clean Water Way: McCarran Boulevard to Cor Soi
Mill Street: Rock Boulevard to McCarran Boulevard
Terminal Way: Mill Street to Plumb Lane
Peckham Lane: Virginia Street to Longley Lane
Thomas Creek Road: Holcomb Lane to Foothill Road

Thursday 7/14

Micro-Surfacing
Wingfield Hills Road: David Allen Parkway to Rolling Meadows Drive

Pavement Striping
Veterans Parkway Multi-Use Path

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Wingfield Hills Road: David Allen Parkway to Rolling Meadows Drive

Pavement Crack Sealing (Night Work – 7:00 p.m. – 7:00 a.m.)
Clean Water Way: McCarran Boulevard to Cor Soi
Mill Street: Rock Boulevard to McCarran Boulevard
Terminal Way: Mill Street to Plumb Lane
Peckham Lane: Virginia Street to Longley Lane
Thomas Creek Road: Holcomb Lane to Foothill Road

Friday 7/15

Micro-Surfacing
Wingfield Hills Road: David Allen Parkway to Rolling Meadows Drive

Pavement Striping (Night Work – 7:00 p.m. – 7:00 a.m.)
Wingfield Hills Road: David Allen Parkway to Rolling Meadows Drive

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin July 11, 2022 on Sharlands Avenue from Robb Drive to Mae Anne Avenue. Shoulder or lane closures are possible.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row between Apollo Way and Wyoming Avenue is closed to through traffic. Traffic is detoured at Apollo Way back to Wyoming Avenue.
  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Apollo Way. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Expect delays during the morning and afternoon rush and consider alternate routes. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Intermittent lane closures on Pyramid Way.

Phase 4: Sutro Street to I-80 ramps (Reno): 

  • Utility exploration (potholing).

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway. This week the contractor continues removing drives and sidewalk to be improved. Forming and pouring new sidewalk, curb and gutter will begin.

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

 

TE SPOT 10 – FUEL TAX PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor will be completing signal work within the intersection at Victorian & 16th Street in Downtown Sparks throughout the week of July 11-15th. Travelers should expect temporary lane reductions and minor delays during daytime hours.

Bus stops located to the east and west of the intersection will be temporarily relocated during the week, but will remain open to transit riders.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 25, 2022.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street is on-going with other construction on the Mill Street project. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin in mid-July.

July 1, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Monday 7/4

No Work – Independence Day

Tuesday 7/5

Pavement Crack Sealing (Night Work  7:00 p.m. – 7:00 a.m.)
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Hawco Court: Ingenuity Avenue to End
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way

Wednesday 7/6

Pavement Crack Sealing (Night Work  7:00 p.m. – 7:00 a.m.)
Circuit Court: Isidor Court to End
Digital Court: Ingenuity Avenue to End
Distribution Drive: Calle De La Plata to Isidor Court
Hawco Court: Ingenuity Avenue to End
Ingenuity Avenue: Pyramid Hwy to Hawco Court
Inventors Place: Isidor Court to End
Isidor Court: Circuit Court to Academy Way
La Posada Drive: Cordoba Boulevard to End Of Curb
Wingfield Hills Road: David Allen Parkway to Rolling Meadows Drive

Thursday 7/7

Pavement Crack Sealing (Night Work  7:00 p.m. – 7:00 a.m.)
La Posada Drive: Cordoba Boulevard to End Of Curb
Wingfield Hills Road: David Allen Parkway to Rolling Meadows Drive
Boxington Way: Lincoln Way to Lillard Drive
Deming Way: Spice Islands Drive to End
E Lincoln Way: Stanford Way to McCarran Boulevard
E Lincoln Way: Sparks Boulevard to Lillard Drive
E Prater Way: Sparks Boulevard to City Limits
Franklin Way: Spice Islands Drive to Kleppe Lane
Hulda Court: Hulda Way to End
Lillard Drive: Brierley Way to Prater Way
Purina Way: Spice Islands Drive to Greg Street
United Circle: Spice Islands Drive to Spice Islands Drive

Pavement Patching
Somersett Ridge Parkway: Us Hwy 40 to Del Webb Parkway
Mayberry Drive: Fourth Street to Hunter Lake Drive

Friday 7/8

Pavement Patching – Grinder Patch
Mayberry Drive: Fourth Street to Hunter Lake Drive
Hunter Lake Drive: Rodney Drive to Idlewild Drive

Slurry Seal
Eastlake Boulevard: Cattleguard to Coyote Drive

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin June 27, 2022.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row between Apollo Way and Wyoming Avenue is closed to through traffic. Traffic is detoured at Apollo Way back to Wyoming Avenue.
  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Apollo Way. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Expect delays during the morning and afternoon rush and consider alternate routes. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Intermittent lane closures on Pyramid Way.

Phase 4: Sutro Street to I-80 ramps (Reno): 

  • Utility exploration (potholing).

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway. This week the contractor continues removing drives and sidewalk to be improved. Forming and pouring new sidewalk, curb and gutter will begin.

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 2022.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street to begin June 27, 2022. Traffic signal at South Meadows Boulevard and Wilbur May Boulevard construction to begin in mid-July.

June 24, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Monday 6/27

Pavement Crack Sealing
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Incline Way: Country Club Drive to Southwood Boulevard
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Patching
El Rancho Boulevard: Victorian Avenue to Sullivan Lane

Tuesday 6/28

Pavement Crack Sealing
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Incline Way: Country Club Drive to Southwood Boulevard
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Patching
Robb Drive: Sharlands Avenue to Las Brisas Boulevard

Wednesday 6/29

Pavement Crack Sealing
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Northwood Boulevard: Tahoe Boulevard to Village Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Incline Way: Country Club Drive to Southwood Boulevard
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Pavement Patching
Somersett Ridge Parkway: Us Hwy 40 to Del Webb Parkway
Mayberry Drive: Fourth Street to Hunter Lake Drive

Thursday 6/30

Pavement Patching – Grinder Patch
Mayberry Drive: Fourth Street to Hunter Lake Drive
Hunter Lake Drive: Rodney Drive to Idlewild Drive

Friday 7/1

Pavement Patching – Grinder Patch
Peckham Lane: Virginia Street to Longley Lane
Terminal Way: Plumb Lane to Mill Street

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Travelers should expect temporary lane and shoulder closures at the following locations while crews install pedestrian rail at RTC Bus Stops:

  • Neil Road and Nutmeg Place
  • Double Diamond Parkway and Technology Way
  • S. Virginia Street and Kietzke Lane

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Project is complete.

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin June 27, 2022.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row between Apollo Way and Wyoming Avenue is closed to through traffic. Traffic is detoured at Apollo Way back to Wyoming Avenue.
  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Apollo Way. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Expect delays during the morning and afternoon rush and consider alternate routes. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Intermitten lane closures on Pyramid  June 27 – July 22, 2022.

Phase 2: Sullivan Lane (Sparks) to Silverada Boulveard (Reno): 

  • Preliminary construction exploration (potholing).

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – westbound traffic will be closed on California Avenue at Booth Street beginning on Wednesday, June 22, 2022 for roadway reconstruction. The detour is anticipated to be in effect for approximately six weeks. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to Mayberry Drive to California Avenue. Eastbound traffic will not be affected.

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway. This week the contractor continues removing drives and sidewalk to be improved. Forming and pouring new sidewalk and curb and gutter will begin.

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 2022.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street and South Meadows Boulevard and Wilbur May Boulevard to begin June 27, 2022.

June 17, 2022

2022 RTC Preventive Maintenance Project
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Monday 6/20

Utility Adjustments
Hunter Lake Drive: Rodney Drive to Idlewild Drive
Somersett Ridge Parkway: Highway 40 to Del Webb Parkway

Tuesday 6/21

Pavement Patching
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Northwood Boulevard: Tahoe Boulevard to Village Boulevard

Wednesday 6/22

Pavement Crack Sealing
Thomas Creek Road: Holcomb Lane to Foothill Road
Eastlake Boulevard: North End Cattleguard to Coyote Drive

Pavement Patching
Tanager Street: Village Boulevard to Southwood Boulevard
Incline Way: Country Club Drive to Southwood Boulevard
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard

Thursday 6/23

Pavement Crack Sealing
Somersett Ridge Parkway: Highway 40 to Del Webb Parkway
Hunter Lake Drive: Rodney Drive to Idlewild Drive
Ralstong Street: University Terrace to Eleventh Street

Pavement Patching – Grinder Patch
Franklin Way: Spice Islands Drive to Kleppe Lane
E Lincoln Way: Sparks Boulevard to Lillard Drive
Lillard Drive: Brierley Way to Prater Way
E Prater Way: Sparks Boulevard to City Limits

Pavement Patching – Hand Patch
Eastlake Boulevard: North End Cattleguard to Coyote Drive
Thomas Creek Road: Holcomb Lane to Foothill Road

Friday 6/24

Pavement Crack Sealing
Country Club Drive: Tahoe Boulevard to Mt. Rose Highway
Incline Way: Country Club Drive to Southwood Boulevard
Lakeshore Boulevard: Village Boulevard to Tahoe Boulevard
Tanager Street: Village Boulevard to Southwood Boulevard
Northwood Boulevard: Tahoe Boulevard to Village Boulevard

Pavement Patching – Grinder Patch
E Greenbrae Drive: Stanford Way to McCarran Boulevard
Carville Drive: Silverada Boulevard to Paradise Drive

Pavement Patching – Hand Patch
La Posada Drive: Cordoba Boulevard to End of Curb
Hawco Court: Ingenuity Avenue to NE of Ingenuity Avenue
Ingenuity Avenue: SR 445 to NW of Hawco Court
Isidor Court: W of Circuit Court to W of Academy Way
Distribution Drive: Calle De La Plata to Isidor Court

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Project is complete.

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin June 27, 2022.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row between Apollo Way and Wyoming Avenue is closed to through traffic. Traffic is detoured at Apollo Way back to Wyoming Avenue.
  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Apollo Way. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly.
  • Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Expect delays during the morning and afternoon rush and consider alternate routes. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Intermitten daily lane closures on Pyramid starting June 20 – June 30, 2022.

Phase 2: Sullivan Lane (Sparks) to Silverada Boulveard (Reno): 

  • Preliminary construction exploration (potholing).

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Mayberry Drive

California Avenue is closed to through traffic. Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway. This week the contractor continues removing drives and sidewalk to be improved. Forming and pouring new sidewalk and curb and gutter will begin.

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 2022.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street and Telegraph Street and South Meadows Boulevard and Wilbur May Boulevard to begin June 27, 2022.

June 10, 2022

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Installation is complete and the traffic signal is active. Final paving and striping will occur June 27, 2022.

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin June 27, 2022.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Kings Row between Apollo Way and Wyoming Avenue is closed to through traffic. Traffic is detoured at Apollo Way back to Wyoming Avenue.
  • Kings Row is closed to northbound (uphill) traffic between McCarran Boulevard and Apollo Way. Traffic accessing Kings Row is encouraged to use the residential side streets and access the Kings Row area via McCarran Boulevard to Kings Row southbound or Wyoming Avenue and Conway Lane to the neighborhood streets.
  • Drivers should expect delays and rerouting when looking to access Kings Row neighborhood, look for signs and traffic control devices; please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction has begun work on the NORTH side of Mill Street between Rock Boulevard and Terminal Way. The two right westbound lanes will be closed and westbound traffic will be reduced to one lane. Expect delays during the morning and afternoon rush and consider alternate routes. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Sullivan Lane – Northside instersection closure – until Friday June 17, 2022.

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Mayberry Drive

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

California Avenue and Mayberry Drive – Memory Lane to Booth Street

One lane in each direction is open to traffic.  Please slow down through construction zones for the safety of the community and workers.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway.  This week the contractor continues removing drives and sidewalk to be improved. Concrete work will begin.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 2022.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street/Telegraph Street and South Meadows Boulevard/Wilbur May Boulevard to begin June 27, 2022.

June 2, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on the pedestrian crossing flasher at the following location:

  • Mill Street and Kirman Avenue (near Renown)

Drivers should expect lane and shoulder closures. Pedestrian detours will be provided.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Installation is complete and the traffic signal is active. Final paving and striping will occur June 13, 2022.

 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) Phase 4 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction to begin June 2022.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.
  • Starting June 13, Kings Row will be one-way (traveling down hill) between McCarran Boulevard and Wyoming Avenue. Detours will be in place for vehicles traveling through this area.
  • In addition, the section of Kings Row between Apollo Way and Wyoming Avenue will be closed to through traffic, vehicles will detour at Apollo Way with routing back to Wyoming Avenue and Kings Row.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Traffic Control Changes!
Spanish Springs Construction will begin work on the NORTH side of Mill Street between McCarran Boulevard and Terminal Way.   The two right westbound lanes will be closed and westbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Sullivan Lane – Northside instersection closure – Monday June 6 – Friday June 17, 2022.

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue is closed to through traffic.  Local traffic may access properties along California Avenue and Westfield Avenue from Hunter Lake Drive.

Mayberry Drive – Memory Lane to California Avenue

One lane in each direction is open to traffic.  Please slow down through construction zones for the safety of the community and workers.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

Traffic is now reversed to the counterclockwise direction allowing work on the other half of the roadway.  This week the contractor will begin removing the old pavement.

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this project.

 

TE SPOT 10 – SOUTH PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of a new roundabout at the intersection of 4th Street and Woodland Avenue will begin July 2022.

 

TRAFFIC SIGNAL INSTALLATION (TSI) 22-01 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of traffic signal at Mill Street/Telegraph Street and South Meadows Boulevard/Wilbur May Boulevard to begin June 2022.

May 27, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Mill Street and Kirman Avenue (near Renown)
  • Lakeside Drive and Robinhood Drive
  • 2nd Street and Gould Street
  • 7th Street and Washington Street

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Installation is complete and the traffic signal is active. Final paving and striping will occur June/July 2022.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Terminal Way. The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • 12th St Closure – May 23 – June 3, 2022.

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Scott Gibson, P.E. – 775-335-1874

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • This week the contractor will be paving driveways, raising utilities on the newly paved road, installing signs, and continuing with the concrete work. 

Traffic is schedued to be reversed to the counterclockwise direction to begin working on the other half of the road starting on Thursday, June 2, 2022.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this project.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Project is completed.

May 20, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Mill Street and Kirman Avenue (near Renown)
  • Lakeside Drive and Robinhood Drive
  • 2nd Street and Gould Street
  • 7th Street and Washington Street

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Installation is complete and the traffic signal is active. Final paving and striping will occur June/July 2022.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Terminal Way. The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and installing light pole bases.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Roy Flores, PE, M.P.A. – 775-335-1881

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • This week the contractor will be paving driveways, raising utilities on the newly paved road, installing signs, and continuing with the concrete work. 

Traffic is schedued to be reversed to the counterclockwise direction to begin working on the other half of the road starting on Thursday, June 2, 2022.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this project.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume week of May 19th – May 23rd, 2022 for roadway slurry seal and striping. Please use caution driving through the intersection. Traffic control will be in effect.

May 13, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Mill Street and Kirman Avenue (near Renown)
  • Lakeside Drive and Robinhood Drive
  • 2nd Street and Gould Street
  • 7th Street and Washington Street

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Installation is complete and the traffic signal is active. Final paving and striping will occur June/July 2022.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Terminal Way. The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane. Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, privacy screens’ footing excavation, posts/panels installation, removing backyard fences and finishing electrical underground work.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)

One lane in each direction will be maintained along Oddie Boulevard. For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Roy Flores, PE, M.P.A. – 775-335-1881

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • This week the contractor will be installing the new modified road subgrade and paving on Thursday (5/19) and Friday (5/20).

Traffic is schedued to be reversed to the counterclockwise direction to begin working on the other half of the road starting on Tuesday, May 31, 2022.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this project.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume week of May 16, 2022 for roadway slurry seal and striping.

The intersection is open for normal operations. New roadway configuration in place. Please use caution driving through the intersection.

May 6, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Double Diamond and Trademark Drive
  • Prater Way and E. I Street
  • Lakeside Drive and Robinhood Drive
  • 2nd Street and Gould Drive
  • 7th Street and Washington Street

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Installation is complete and the traffic signal is active.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Terminal Way.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see daily intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are performing drainage work, median patching, privacy screens’ footing excavation, posts/panels installation.
  • Roadwork activities:
    • Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Roy Flores, PE, M.P.A. – 775-335-1881

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • April 4 through the end of May, weather permitting: Traffic will flow in a one-way, clockwise direction. Drivers will enter at Sky Mountain Drive/Summit Ridge Drive intersection and exit at Sky Valley Drive/Summit Ridge Drive intersection.
  • End of May through July, weather permitting: Traffic will flow in a one-way, counterclockwise direction. Drivers will enter at Sky Valley Drive/Summit Ridge Drive intersection and exit at Sky Mountain Drive/Summit Ridge Drive intersection.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this project.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume week of May 16, 2022 for roadway slurry seal and striping.

The intersection is open for normal operations. New roadway configuration in place.  Please use caution driving through the intersection.

April 29, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Greg Street and McCarran Boulevard
  • South Virginia Street and Kietzke Lane
  • Neil Road and Nutmeg Place
  • Bluestone Drive and Huffaker Lane
  • Double Diamond and Technology Way
  • Double Diamond and Trademark Drive
  • Prater Way and E. I Street
  • Lakeside and Robinhood Drive

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Traffic signal is substantially complete.  Activation of signal is scheduled for April 29, 2022.  Please use caution due to changed traffic pattern.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Terminal Way.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent daily shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing drainage work, median patching, privacy screens’ footing excavation, install posts/panels and signal poles.
  • Roadwork activities:
    • NEW TRAFFIC PATTERNTraffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Rock Boulevard/Oddie Boulevard intersection Half Closure (north side) – Detours in place until Friday, May 6, 2022.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Roy Flores, PE, M.P.A. – 775-335-1881

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • April 4 through the end of May, weather permitting: Traffic will flow in a one-way, clockwise direction. Drivers will enter at Sky Mountain Drive/Summit Ridge Drive intersection and exit at Sky Valley Drive/Summit Ridge Drive intersection.
  • End of May through July, weather permitting: Traffic will flow in a one-way, counterclockwise direction. Drivers will enter at Sky Valley Drive/Summit Ridge Drive intersection and exit at Sky Mountain Drive/Summit Ridge Drive intersection.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this project.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume week of May 9, 2022 for roadway slurry seal and striping.

The intersection is open for normal operations. New roadway configuration in place.  Please use caution driving through the intersection.

April 22, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Greg Street and McCarran Boulevard
  • South Virginia Street and Kietzke Lane
  • Neil Road and Nutmeg Place
  • Bluestone Drive and Huffaker Lane
  • Double Diamond and Technology Way
  • Double Diamond and Trademark Drive
  • Prater Way and E. I Street
  • Lakeside and Robinhood Drive

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Work is suspended pending arrival of traffic signal equipment.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Terminal Way.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks):

  • Roadwork construction completed.
  • Road open with no restrictions

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent daily shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing drainage work, median patching, privacy screens’ footing excavation, install posts/panels and signal poles.
  • Roadwork activities:
    • NEW TRAFFIC PATTERNTraffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Rock Boulevard/Oddie Boulevard intersection Half Closure (north side) – Detours in place until Friday, April 29, 2022.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Roy Flores, PE, M.P.A. – 775-335-1881

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • April 4 through the end of May, weather permitting: Traffic will flow in a one-way, clockwise direction. Drivers will enter at Sky Mountain Drive/Summit Ridge Drive intersection and exit at Sky Valley Drive/Summit Ridge Drive intersection.
  • End of May through July, weather permitting: Traffic will flow in a one-way, counterclockwise direction. Drivers will enter at Sky Valley Drive/Summit Ridge Drive intersection and exit at Sky Mountain Drive/Summit Ridge Drive intersection.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this project.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume in early May for roadway slurry seal and striping.

The intersection is open for normal operations. New roadway configuration in place.  Please use caution driving through the intersection.

April 15, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Greg Street and McCarran Boulevard
  • Terminal Way and Vassar Street
  • Kirman Avenue and Capitol Hill
  • Wrondel Way and Grove Street
  • South Virginia Street and Kietzke Lane
  • Neil Road and Nutmeg Place
  • Bluestone Drive and Huffaker Lane

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Work is suspended pending arrival of traffic signal equipment.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue are shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Terminal Way.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks):

  • Roadwork construction completed.
  • Road open with no restrictions

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent daily shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing drainage work, median patching, privacy screens’ footing excavation, install posts/panels and signal poles.
  • Roadwork activities:
    • NEW TRAFFIC PATTERNTraffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Rock Boulevard/Oddie Boulevard intersection Half Closure (north side) – Detours in place – April 11, 2022 – April 29, 2022.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Roy Flores, PE, M.P.A. – 775-335-1881

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • April 4 through the end of May, weather permitting: Traffic will flow in a one-way, clockwise direction. Drivers will enter at Sky Mountain Drive/Summit Ridge Drive intersection and exit at Sky Valley Drive/Summit Ridge Drive intersection.
  • End of May through July, weather permitting: Traffic will flow in a one-way, counterclockwise direction. Drivers will enter at Sky Valley Drive/Summit Ridge Drive intersection and exit at Sky Mountain Drive/Summit Ridge Drive intersection.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Drivers should expect lane and shoulder closures as workers complete roadside trenching and electrification of the new Rectangular Rapid Flashing Beacon (RRFB) pedestrian crossing at Steamboat Parkway and Horse Ranch Road.

Lane closures should also be anticipated at the intersection of Victorian Avenue and 16th Street as workers install detection loops within the intersection.

Both locations will remain open to two-way traffic. Drivers should slow down and use extra caution when passing through these work zones.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume in early May for roadway slurry seal and striping.

The intersection is open for normal operations. New roadway configuration in place.  Please use caution driving through the intersection.

April 8, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Greg Street and Linda Way
  • Greg Street and Marietta Way
  • Greg Street and McCarran Boulevard
  • Rock Boulevard and Freeport Boulevard
  • Terminal Way and Vassar Street
  • Kirman and Capitol Hill
  • Wrondel Way and Grove Street
  • South Virginia Street and Kietzke Lane

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Work is suspended pending arrival of traffic signal equipment.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue is shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts. Look for signs and traffic control devices, please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Terminal Way.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks):

  • Roadwork construction completed.
  • Road open with no restrictions

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent daily shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing drainage work, median patching, privacy screens’ footing excavation, install posts/panels and signal poles.
  • Roadwork activities:
    • NEW TRAFFIC PATTERNTraffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Rock Boulevard/Oddie Boulevard intersection Half Closure (north side) – Detours in place – April 11, 2022 – April 29, 2022.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Roy Flores, PE, M.P.A. – 775-335-1881

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • April 4 through the end of May, weather permitting: Traffic will flow in a one-way, clockwise direction. Drivers will enter at Sky Mountain Drive/Summit Ridge Drive intersection and exit at Sky Valley Drive/Summit Ridge Drive intersection.
  • End of May through July, weather permitting: Traffic will flow in a one-way, counterclockwise direction. Drivers will enter at Sky Valley Drive/Summit Ridge Drive intersection and exit at Sky Mountain Drive/Summit Ridge Drive intersection.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this week.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume in early May for roadway slurry seal and striping.

The intersection is open for normal operations. New roadway configuration in place.  Please use caution driving through the intersection.

April 1, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Greg Street and Linda Way
  • Greg Street and Marietta Way
  • Greg Street and McCarran Boulevard
  • Rock Boulevard and Freeport Boulevard
  • Terminal Way and Vassar Street

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Work is suspended pending arrival of traffic signal equipment.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • The travel lanes of Kings Row between McCarran Boulevard and Wyoming Avenue is shifted to provide a safe work zone for the contractor. On street parking is not allowed along Kings Row during construction working hours (7:00 a.m. to 5:00 p.m.); however, overnight parking within the work zone is permitted.
  • Drivers should expect lane shifts, look for signs and traffic control devices; please drive slowly. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Telegraph Street.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks):

  • Construction work is in progress and expected to continue until mid-April.
  • Access will be maintained, but alternate routes are recommended.
  • Detours in place until Friday April 8, 2022 (to finalize roadwork: paving/patching, utility adjustments and striping).

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent daily shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing drainage work, median patching, privacy screens’ footing excavation, install posts/panels and signal poles.
  • Roadwork activities:
    • NEW TRAFFIC PATTERNTraffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

RENO CONSOLIDATED 22-01 – SKY MOUNTAIN DRIVE, SKY VALLEY DRIVE
RTC Project Manager, Roy Flores, PE, M.P.A. – 775-335-1881

As part of the project, one-way traffic will be in place for the duration of construction. In addition to improving construction safety and efficiency, one-way traffic will allow vehicles to remain in the traditional right-hand travel lane, retain on-street parking during construction, maintain a bike lane, and allow for continued transit service.

  • April 4 through the end of May, weather permitting: Traffic will flow in a one-way, clockwise direction. Drivers will enter at Sky Mountain Drive/Summit Ridge Drive intersection and exit at Sky Valley Drive/Summit Ridge Drive intersection.
  • End of May through July, weather permitting: Traffic will flow in a one-way, counterclockwise direction. Drivers will enter at Sky Valley Drive/Summit Ridge Drive intersection and exit at Sky Mountain Drive/Summit Ridge Drive intersection.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Work continues on the TE Spot 10 – Fuel Tax Project at the following locations:

Victorian Avenue and 16th Street
Sparks Boulevard and Ion Drive
Steamboat Parkway and Horse Ranch Road

Drivers should expect temporary lane and shoulder closures at these locations. Pedestrian detours may be present as crews complete sidewalk and striping at pedestrian crossings.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume in early May for roadway slurry seal and striping.

The intersection is open for normal operations. New roadway configuration in place.  Please use caution driving through the intersection.

March 25, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • York Way and Rock Boulevard
  • Rock Boulevard and Vance Way
  • York Way and 4th Street
  • Glendale Avenue and Summit Racing
  • Greg Street and Deming Way
  • Greg Street and Linda Way
  • Greg Street and Marietta Way

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

There will be intermittent lane, shoulder and sidewalk closures for signal pole installation.

 

KINGS ROW REHABILITATION PROJECT – PHASE 2 – WYOMING AVENUE TO MCCARRAN BOULVARD
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

  • Message boards and other traffic control equipment will begin mobilizing to the area the week of March 28, 2022.
  • Work activities are planned to start the week of April 4, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Telegraph.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks):

  • Construction work is in progress and expected to continue until mid-April.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.
  • Detours in place starting on March 28 – April 1, 2022 – Roadwork activities.

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent daily shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing drainage work, median patching, privacy screens’ footing excavation and install/pour posts, and panels.
  • Roadwork activities:
    • Temporary striping for “Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
  • Lane closures on Pyramid Way from J Street to I Street starting March 28 – April 8, 2022 from 9:00 a.m. – 4:00 p.m.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Work will resume on the TE Spot 10 – Fuel Tax Project at the following locations:

Steamboat Parkway & Horse Ranch Road
Sparks Boulevard and Ion Drive
Victorian Avenue and 16th Street

Drivers should expect temporary lane and shoulder closures at these locations. Pedestrian detours may be present as crews complete sidewalk and striping at pedestrian crossings.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction to resume in early May for roadway slurry seal and striping.

The intersection is open for normal operations. New roadway configuration in place.  Please use caution driving through the intersection.

March 18, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • Wedekind Road and Community Garden Apartments
  • Silverada Boulevard and Orovada Street
  • Moya Boulevard and 12085 Moya Boulevard
  • York Way and Rock Boulevard
  • Rock Boulevard and Vance Way
  • Glendale Avenue and Summit Racing
  • Greg Street and Deming Way

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical begin installation of traffic signal underground equipment on March 14, 2022. There will be intermittent lane, shoulder and sidewalk closures during Washoe County School District’s spring break, March 14-25, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Telegraph.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks):

  • Construction work is in progress and expected to continue until mid-April.
    • Constructing sidewalk, curb/gutter and driveways.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.
  • Detours in place starting on March 28 – April 1, 2022 – Roadwork activities.

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent daily shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing drainage work, median patching, privacy screens’ footing excavation and install/pour posts, installing pedestrian rail.
  • Roadwork activities:
    • Temporary striping for “Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes.)
    • Traffic Swap scheduled to start on March 21, 2022
  • Lane closures on Pyramid Way from J Street to I Street starting March 28 – April 1, 2022 from 9:00 a.m. – 4:00 p.m.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com. 

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Work will resume on the TE Spot 10 – Fuel Tax Project on Monday, March 14, 2022 at the following locations:

Golden Valley Road & Estates Drive
Western Skies Drive & Brown Elementary School
Steamboat Parkway & Horse Ranch Road
Sparks Boulevard and Ion Drive
Victorian Avenue and 16th Street

Drivers should expect temporary lane and shoulder closures at these locations. Pedestrian detours may be present as crews complete sidewalk and striping at pedestrian crossings.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place.  Please use caution driving through the intersection.

March 11, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • W 4th Street and Keystone Avenue
  • E 2nd Street and Park Street
  • Mill Street and Kirman Avenue (Renown)
  • Valley Road and Highland Avenue
  • Wedekind Road and Community Garden Apartments
  • Silverada Boulevard and Orovada Street
  • Moya Boulevard and 12085 Moya Boulevard
  • York Way and Rock Boulevard
  • Rock Boulevard and Vance Way

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical will begin installation of traffic signal underground equipment on March 14, 2022. There will be intermittent lane, shoulder and sidewalk closures during Washoe County School District’s spring break, March 14-25, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Telegraph.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks)

  • Construction work is in progress and expected to continue until mid-April.
    • removing and replacing median, sidewalk, curb/gutter and driveways.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.
  • Detours in place starting on March 28 – April 1, 2022 – Roadwork activities.

Phase 1: Pyramid Way to Sullivan Lane (Sparks)

  • Drivers may see intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing underground electrical work, excavating/forming/building/backfilling (front and back) retaining walls.
  • Surveying
  • Starting roadwork:
    • Temporary striping for “Traffic Swap” (Oddie Boulevard westbound traffic will be shifted to the eastbound lanes
    • Traffic Swap scheduled to start on March 21, 2022

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at Oddiewellsproject.com.

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

California Avenue to westbound traffic between Booth Street and Mayberry Drive will  be closed. Westbound traffic will be detoured at Booth Street to Foster Drive to Hunter Lake Drive to allow the contractor to complete water line adjustments that must be done prior to the roadway work.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Work will resume on the TE Spot 10 – Fuel Tax Project on Monday, March 14, 2022 at the following locations:

Golden Valley Road & Estates Drive

Western Skies Drive & Brown Elementary School

Steamboat Parkway & Horse Ranch Road

Drivers should expect temporary lane and shoulder closures at these locations. Pedestrian detours may be present as crews complete sidewalk and striping at pedestrian crossings.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place.  Please use caution driving through the intersection.

March 4, 2022

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM  – PHASE 3 PROJECT
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations:

  • W 4th Street and Keystone Avenue
  • E 2nd Street and Park Street
  • Mill Street and Kirman Avenue (Renown)
  • Valley Road and Highland Avenue
  • Wedekind Road and Community Garden Apartments

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and  temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin March 7, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

For additional information on construction status, visit the Project website at http://northvalleysimprovements.com/lemmon-drive/.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Rock Boulevard.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

Electrical work between Telegraph Street and Rock Boulevard is also taking place. The outside eastbound lane will be closed to accommodate that work.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks)

  • Construction work is in progress and expected to continue until mid-March – removing and replacing median.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.

Phase 1: Pyramid Way to Sullivan Lane (Sparks)

  • Drivers may see intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing underground electrical work, excavating/forming/building/backfilling (front and back) retaining walls.
  • Median removal and patching.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at Oddiewellsproject.com.

 

RENO CONSOLIDATED 20-01 – MAYBERRY DRIVE, CALIFORNIA AVENUE, FIRST STREET
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

California Avenue – Hunter Lake Drive to Booth Street

RTC will rehabilitate the roadway, make ADA improvements, create bicycle and pedestrian connectivity, add and maintain sidewalks, and improve safety. At the California Avenue/Mayberry Drive intersection, the RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway and improve ADA access to the Route 16 transit stops on California Avenue near Arbutus Street and Hunter Lake Drive.

Mayberry Drive – Memory Lane to California Avenue

RTC plans to reconfigure it to a four-way intersection with crosswalks, use roadway geometrics to slow traffic entering the neighborhood, and create fewer conflict points between pedestrians, bicycles and cars, creating a safer roadway. Also, rehabilitate the roadway and maintain sidewalk connectivity and existing bike lanes.

Drivers can expect lane closures and detours as the project progresses.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled.  Construction will continue mid-March 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place.  Please use caution driving through the intersection.

February 25, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Monday 2/28

Utility Adjustments

Isidor Court: Calle De La Plata to Circuit Court

Calle De La Plata: Pyramid Highway to Isidor Court

La Posada Drive: Pyramid Highway to Omni Drive

Tuesday 3/1

Utility Adjustments

Calle De La Plata: Pyramid Highway to Isidor Court

La Posada Drive: Pyramid Highway to Omni Drive

Calle De Oro Parkway: Cordoba Boulevard

Wednesday 3/2

Utility Adjustments

La Posada Drive: Pyramid Highway to Omni Drive

Calle De Oro: Cordoba Boulevard

Thursday 3/3

Utility Adjustments

Baring Boulevard: McCarran Boulevard to Vista Boulevard

York Way: Rock Boulevard to McCarran Boulevard

Friday 3/4

Utility Adjustments

Freeport Boulevard: 21st Street to Stanford Way

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM – PHASE 3 PROJECT

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

RTC’s contractor, Sierra Nevada Construction, will be working on sidewalks and bus pads at the following locations starting Monday, February 28, 2022:

  • W 4th Street and Keystone Avenue
  • E 2nd Street and Park Street
  • Mill Street and Kirman Avenue (Renown)

Drivers should expect lane and shoulder closures at these locations. Pedestrian detours will be provided and  temporary alternative bus stops will be available to transit riders.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin March 7, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Rock Boulevard.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

Electrical work between Telegraph Street and Rock Boulevard will take place. The outside eastbound lane will be closed to accommodate that work.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

DUE TO INCLEMENT WEATHER CONSTRUCTION WORK WILL BE RESUMED THIS WEEK!

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks)

  • Construction work is in progress and expected to continue until mid-March.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.

Phase 1: Pyramid Way to Sullivan Lane (Sparks)

  • Drivers may see intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing underground electrical work, excavating/forming/building retaining walls.
  • Nevada Energy crews will be working on Monday, February 28 at 6:00 p.m. until Tuesday, March 1 at 6:00 a.m. (night work). Lane closure only. No detour during night working hours.
  • Sullivan Lane Closure from Monday, February 28 – Friday, March 4. Detour in place with alternative routes taking Prater Way and Greenbrae Drive.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at Oddiewellsproject.com.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled.  Construction will continue mid-March 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place.  Please use caution driving through the intersection.

February 18, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin March 7, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Rock Boulevard.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

Electrical work between Telegraph Street and Rock Boulevard will take place. The outside eastbound lane will be closed to accommodate that work.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks)

  • Construction work is in progress and expected to continue until mid-March.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.

Phase 1: Pyramid Way to Sullivan Lane (Sparks)

  • Drivers may see intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing underground electrical work, excavating/forming/building retaining walls.
  • Sullivan Lane closure from Monday, February 21 – Friday, February 25. Detour in place with alternative routes taking Prater Way and Greenbrae Drive.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at Oddiewellsproject.com .

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled.  Construction will continue in March 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place.  Please use caution driving through the intersection.

February 11, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin March 7, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Spanish Springs Construction continues work on the south side of Mill Street between McCarran Boulevard and Rock Boulevard.  The two right eastbound lanes will be closed and eastbound traffic will be reduced to one lane.  Business and side street access will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks)

  • Construction work is in progress and expected to continue until mid-March.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.

Phase 1: Pyramid Way to Sullivan Lane (Sparks)

  • Drivers may see intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing underground electrical work, excavating/forming/building retaining walls.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at Oddiewellsproject.com .

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled.  Construction will continue in March 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place.  Please use caution driving through the intersection.

February 4, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin March 7, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

MILL STREET COMPLETE STREET – 1-580 to MCCARRAN BOULEVARD
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Construction begins Monday, February 7, 2022.  Work will begin on the south side of Mill Street between McCarran Boulevard and Edison Way.  The two right eastbound lanes will be closed with eastbound traffic reduced to one lane.  Driveway access and access to Financial Boulevard will be maintained.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

El Rancho Drive – Greenbrae Drive to Oddie Boulevard (Sparks)

  • Construction work starting on Monday February 7, 2022 and expected to last until mid-March.
  • One lane in each direction will be maintained.
  • Access will be maintained, but alternate routes are recommended.

Phase 1: Pyramid Way to Sullivan Lane (Sparks)

  • Drivers may see intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Intermittent partial or full closures (detours) at 12th Street and Rock Boulevard intersections during daytime working hours.
  • Construction crews are doing underground work, excavating/forming/building retaining walls.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at Oddiewellsproject.com .

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled.  Construction will continue in March 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place.  Please use caution driving through the intersection.

January 28, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin March 7, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • Intermittent partial or full closures (detours) at 12th and Rock intersections during daytime working hours.
  • Construction crews are doing underground work, excavating/forming/building retaining walls.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com .

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled. Construction will continue in March 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

January 21, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

GOLDEN VALLEY AT BECKWOURTH – TRAFFIC SIGNAL PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction will begin March 7, 2022.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent shoulder and/or lane closures on Oddie Boulevard during daytime working hours.
  • Intermittent partial or full closures (detours) at 12th and Rock intersections.
  • Construction crews are doing underground work, excavating/forming/building retaining walls.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status and time-lapse pictures, visit the Project website at http://Oddiewellsproject.com .

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

January 14, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at Rock Boulevard and Glendale Avenue.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent shoulder and/or lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing underground work, excavating/forming/pouring footings.
  • On Pyramid Way ( between J Street and I Street): intermittent closure of southbound lane from 9:00 AM and 4:00 PM.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com .

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work scheduled.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

January 7, 2022

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at Rock Boulevard at Glendale Avenue.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent shoulder and/or lane closures on Oddie Boulevard during daytime working hours.
  • Construction crews are doing underground work, excavating/forming/pouring footings.
  • On Pyramid Way ( between J Street and I Street): intermittent closure of southbound lane from 9:00 AM and 4:00 PM.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com .

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Activation of the new traffic signal at the intersection of Veterans Parkway and Long Meadow Drive is scheduled for Wednesday, January 12, 2022. Drivers should anticipate the new traffic pattern and expect isolated shoulder and lane closures leading up to the signal activation.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

December 30, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at:

  • Rock Boulevard from Greg Street to Victorian Avenue.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):  Happy New Year! Construction work has resumed.

  • Drivers may see intermittent shoulder and/or lane closures on Oddie Boulevard during daytime working hours.
  • Granite construction crews are doing underground work, excavating/forming/pouring footings.
  • On Pyramid Way ( between J Street and I Street): intermittent closure of southbound lane from 9:00AM and 4:00PM.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this period. Work will resume in 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

December 23, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at:

  • Rock Boulevard from Greg Street to Victorian Avenue.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Happy Holidays!
  • No work this week.
  • Construction will resume after the New Year (weather permitting.)

For additional information on construction status, visit the Project website at http://Oddiewellsproject.com

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

No work is scheduled for this period. Work will resume in 2022.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

December 17, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at:

  • Rock Boulevard from Greg Street to Victorian Avenue.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent shoulder and/or lane closures on Oddie Boulevard during daytime working hours.
  • Granite construction crews are doing underground work, excavating/forming/pouring footings.
  • On Pyramid Way ( between J Street and I Street): intermittent closure of southbound lane from 9:00AM and 4:00PM.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Sparks Boulevard & Ion Drive
  • Veterans Parkway & Long Meadow Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work and construct new pedestrian ramps and sidewalks. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00AM to 3:00PM Monday through Friday.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

December 10, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at:

  • Rock Boulevard from Greg Street to Victorian Avenue.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1: Pyramid Way to Sullivan Lane (Sparks):

  • Drivers may see intermittent shoulder and/or lane closures on Oddie Boulevard during daytime working hours.
  • Granite construction crews are doing underground, excavating/forming/pouring footings.
  • NV Energy crews will continue to remove existing facilities.
  • On Pyramid Way ( between J Street and I Street): intermittent closure of southbound lane from 9:00AM and 4:00PM.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Sparks Boulevard & Ion Drive
  • Vista Boulevard & Iratcabal Drive
  • Victorian Avenue & 16th Street
  • Veterans Parkway & Long Meadow Drive
  • Mayberry Drive & Keele Drive
  • 7th Avenue & McDonald Drive
  • Valley Road & Sadlier Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work and construct new pedestrian ramps and sidewalks. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00AM to 3:00PM Monday through Friday.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place. Please use caution driving through the intersection.

December 3, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Monday 12/6

Utility Adjustment
Red Rock Road: US395 to Moya Boulevard
Village Parkway: Cold Springs Drive to Cody Court

Tuesday 12/7

Utility Adjustment
Isidor Court: Calle De La Plata to Circuit Court
Calle De La Plata: Pyramid Highway to Isidor Court
La Posada Drive: Pyramid Highway to Omni Drive Round-a-bout
Calle De Oro: Cordoba Boulevard to Cordoba Boulevard

Wednesday 12/8

Utility Adjustment
Calle De La Plata: Pyramid Highway to Isidor Court
La Posada Drive: Pyramid Highway to 360’ E of Omni Drive Round-a-bout
Calle De Oro: Cordoba Boulevard to Cordoba Boulevard

Thursday 12/9

Utility Adjustment
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard

Friday 12/10

Utility Adjustment
E Greenbrae Drive: Howard Drive to Prater Way
Freeport Boulevard: 21st Street to Stanford Way

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  Final fiber optic splicing work is in progress at:

  • Lake Street from First Street to Second Street.
  • Rock Boulevard from Greg Street to Victorian Avenue.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work is complete. Isolated lane shifts may be in place to perform final clean up activities.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

 Phase 1: Pyramid Way to Sullivan Lane (Sparks):

Construction begins on Monday November 29, 2021.

  • Drivers may see shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • NV Energy crews will be removing existing facilities.

This week drivers can expect to see crews setting up traffic control to prepare for underground and trenching work on the shoulder.

One lane in each direction will be maintained along Oddie Boulevard.  For additional information on construction status, visit the Project website at http://Oddiewellsproject.com

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Sparks Boulevard & Ion Drive
  • Victorian Avenue & 16th Street
  • Mayberry Drive & Keele Drive
  • 7th Avenue & McDonald Drive
  • Valley Road & Sadlier Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work and construct new pedestrian ramps and sidewalks. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 AM to 3:00 PM Monday through Friday.

Ion Drive will be temporarily closed to traffic from Sparks Boulevard to Luther Pass Court on December 8 and 9, 2021 from 9:00 AM to 5:00 PM. A detour will be provided during this closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

November 26, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 11/26

No Work

Saturday 11/27

No Work

Sunday 11/28

No Work

Monday 11/29

Utility Adjustment
Second Street: Keystone Avenue to Virginia Street
Fourth Street: West Street to Galletti Way

Tuesday 11/30

Utility Adjustment
Second Street: Keystone Avenue to Virginia Street
Fourth Street: West Street to Galletti Way

Wednesday 12/1

Utility Adjustment
Second Street: Keystone Avenue to Virginia Street
Fourth Street: West Street to Galletti Way

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Vista Boulevard & Iratcabal Drive
  • Sparks Boulevard & Ion Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 a.m. to 3:00 p.m. Monday through Friday.

Ion Drive will be temporarily closed to traffic from Sparks Boulevard to Luther Pass Court on December 2 and 3, 2021, from 9:00 a.m. to 5:00 p.m. A detour will be provided during this closure.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Lake Street from First Street to Second Street.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7:00 a.m. to 5:00 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

 Phase 1: Pyramid Way to Sullivan Lane (Sparks):

Construction begins on Monday November 29, 2021.

  • Drivers may see shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • NV Energy crews will be removing existing facilities

This week drivers can expect to see crews setting up traffic control to prepare for underground and trenching work on the shoulder.

One lane on each direction along Oddie Boulevard will be maintained.  For additional information on construction status, visit the Porject website at http://Oddiewellsproject.com

November 19, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 11/19

Utility Adjustment
Moana Lane: Plumas Street to Neil Road
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Saturday 11/20

No Work

Sunday 11/21

No Work

Monday 11/22

Utility Adjustment
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

Tuesday 11/23

Utility Adjustment
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Victorian Avenue & 16th Street
  • Veterans Parkway & Long Meadow Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 a.m. to 3:00 p.m. Monday through Friday.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Lake Street from First Street to Second Street.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7:00 a.m. to 5:00 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)

RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

 Phase 1: Pyramid Way to Sullivan Lane (Sparks):

Construction begins on Monday November 29, 2021.

  • Drivers may see shoulder and lane closures on Oddie Boulevard during daytime working hours.
  • NV Energy crews will be removing existing facilities

This week drivers can expect to see crews setting up traffic control to prepare for underground and trenching work on the shoulder.

One lane on each direction along Oddie Boulevard will be maintained.  For additional information on construction status, visit the Porject website at http://Oddiewellsproject.com

November 12, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Monday 11/15

Utility Adjustment
Arrowcreek Parkway: Thomas Creek to private entrance
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Tuesday 11/16

Utility Adjustment
Redfield Parkway: Kietzke Lane to Virginia Street

Wednesday 11/17

Utility Adjustment
Redfield Parkway: Kietzke Lane to Virginia Street

Thursday 11/18

Utility Adjustment
Plumas Street: Ridgeview Drive to Ridgeview Drive
Moana Lane: Plumas Street to Neil Road
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Friday 11/19

Utility Adjustment
Moana Lane: Plumas Street to Neil Road
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Victorian Avenue & 16th Street
  • Veterans Parkway & Long Meadow Drive

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9:00 a.m. to 3:00 p.m. Monday through Friday.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will be cleaning up the job site and working on punch list items. Drivers should expect intermittent traffic control throughout the project limits.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7:00 a.m. to 5:00 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

November 5, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PHASE 3B, NORTH VIRGINIA STREET & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive. Travelers should expect shoulder closures and isolated lane closures while construction crews complete striping and pedestrian ramp work at the intersection.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following location:

  • Victorian Avenue & 16th Street

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9am to 3pm Monday through Friday.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will be cleaning up the job site and working on punch list items. Drivers should expect intermittent traffic control throughout the project limits.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection is open for normal operations.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 28, 2021

2021 RTC PREVENTIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PHASE 3B, NORTH VIRGINIA STREET & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Monday 11/1 – Tuesday 11/2

To complete paving activities, North Virginia Street will be closed in the southbound direction from 9:00 AM to 5:00 PM from Sunset Mountain Road to the intersection at Panther Drive. The road will remain open to northbound traffic, and a southbound detour will be provided via Golden Valley Road.

Trash pickup will continue as scheduled and access will remain open for mail deliveries.

During construction RTC RIDE bus service may be temporarily impacted within the project area.

Travel lanes will be reopened to two-way traffic after 6pm on Tuesday, November 2.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Veterans Parkway & Long Meadow Drive
  • Steamboat Parkway & Horse Ranch Road
  • Sparks Boulevard & Ion Drive
  • Victorian Avenue & 16th Street

Travelers should expect shoulder closures at all locations while construction crews complete trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced from 9am to 3pm Monday through Friday.

 

ITS PHASE 3
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will be cleaning up the job site and working on punch list items. Drivers should expect intermittent traffic control throughout the project limits.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next spring for pavement slurry seal.  The intersection will be open for normal operations starting October 22, 2021.

New roadway configuration in place, please use caution driving through the intersection.

 

KINGS ROW REHABILITATION – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in final stages, please look for lane shifts.

  • Traffic control includes lane shifts to accommodate final striping and final utility work along all of Kings Row from Keystone Avenue to Wyoming Avenue.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 22, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

TE SPOT 10 – FUEL TAX
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the following locations:

  • Veterans Parkway & Long Meadow Drive
  • Steamboat Parkway & Horse Ranch Road
  • Vista Boulevard & Iratcabal Drive
  • Sparks Boulevard & Ion Drive
  • Victorian Avenue & 16th Street

Travelers should expect shoulder closures at all locations while construction crews complete pole foundation and trenching work. Though roadways will remain open to traffic, the number of travel lanes may be temporarily reduced in from 9am to 3pm Monday through Friday.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of November at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will be cleaning up the job site and working on punchlist items. Drivers should expect intermittent traffic control throughout the project limits.

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction will be postponed until next Spring for pavement slurry seal, however, intersection will open  and allow normal operations by October 22, 2021. New roadway configuration, please use caution driving through intersection.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 15, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of October at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. The contractor will begin utility adjustments this week within the roadway.

Drivers should expect intermittent traffic control throughout the project limits.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

Expect intermittent lane closures around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 8, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

No work scheduled.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be installed through the month of October at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Paving of the roadway is complete. This week the contractor will be installing roadway striping and signage.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closures around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.) – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

October 1, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 10/1

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Saturday 10/2

No Work

Sunday 10/3

No Work

Monday 10/4

Micro Surfacing
Panther Drive: Virginia Street to Western Road

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Tuesday 10/5

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Wednesday 10/6

Traffic Signal Loop Replacement
Moana Lane: Clover Way to Warren Way

Thursday 10/7

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Friday 10/8

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Sky Valley Drive & Mistyridge Lane
  • Virginia Street & Planetarium

Work will include roadside construction of bus stop pads and sidewalk. Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

On Tuesday, September 28, 2021 West Golden Valley Road will be closed to vehicle traffic from 9 AM to 3PM.

Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete roadway striping on Wednesday, September 29, 2021 and Thursday September 30, 2021.

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction of underground infrastructure is complete.  New fiber optic cable will be install through the month of October at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).
  • Lake Street from First Street to Second Street.
  • Lemmon Drive from North Virginia Street to US 395 southbound off-ramp.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Roadway paving will occur on Tuesday (10/5) and Wednesday (10/6) along Newport Lane. Travelers should expect delays and it is recommended to find alternative routes if possible.

On-street parking is closed during daytime working hours on Newport Lane (7 a.m. to 5 p.m. – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

Additionally, contractor will be working on Saturday (10/2) to prepare for paving next week.

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m. – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

September 24, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 9/24

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Saturday 9/25

No Work

Sunday 9/26

No Work

Monday 9/27

Chip Seal
Panther Drive: Virginia Street to Western Road

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Tuesday 9/28

Chip Seal
Panther Drive: Virginia Street to Western Road

 Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Wednesday 9/29

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Thursday 9/30

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

Friday 10/1

Striping (Night Work – 7:00PM – 7:00AM)
(Various project streets second coat)

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Sky Valley Drive & Mistyridge Lane
  • Virginia Street & Planetarium

Work will include roadside construction of bus stop pads and sidewalk. Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

On Tuesday, September 28, 2021, West Golden Valley Road will be closed to vehicle traffic from 9:00 a.m. to 3:00 p.m.

Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete roadway striping on Wednesday, September 29, 2021, and Thursday September 30, 2021.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues at the intersection of North Virginia Street and Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection.  Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Roadway reconstruction work will begin this week along Newport Lane and continue into the following week. Travelers should expect delays and it is recommended to find alternative routes if possible.

On-street parking is closed during daytime working hours on Newport Lane (7 a.m. to 5 p.m. – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.

The contractor will be working the next two (2) Saturdays 9/25 and 10/2

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m. – residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

September 17, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 9/17

Scratch Course
Panther Drive: Virginia Street to Western Road

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Saturday 9/18

No Work

Sunday 9/19

No Work

Monday 9/20

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Tuesday 9/21

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Wednesday 9/22

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Thursday 9/23

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Friday 9/24

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
Battle Born Way: Galletti Way to Victorian Avenue
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • 7th Street and Genoa Avenue
  • Lakeside Drive & Brinkby Avenue
  • Sky Valley Drive & Mistyridge Lane
  • Neil Road and Moana Lane
  • South Virginia Street and Meadowwood Mall
  • Double Diamond & Sandhill Road (DMV)
  • Virginia Street & Planetarium

Work will include roadside construction of bus stop pads and sidewalk. Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete sidewalk and utility work.

 

NORTH VALLEYS IMPROVEMENT PROJECT – PHASE 3B, NORTH VIRGINIA ST. & PANTHER DRIVE

RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction begins Monday, September 20, 2021, at the intersection of North Virginia Street & Panther Drive.

Travelers should expect isolated shoulder and lane closures at the intersection. Bus Stops may be temporarily relocated to accommodate sidewalk work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Construction is in progress along the southside of Newport Lane.

Travelers should expect isolated lane closures and one-way flagging while construction crews complete demolition, driveway, sidewalk, storm drain, and headwall work.

Additionally, in order to complete the removal/replacement of the existing pedestrian ramps and install new storm drain along the southside of Newport Lane, access to Newport Lane from La France Lane and Collins Circle  will be closed during the day while construction activities are ongoing. To maintain resident access, a detour will be provided via Sagehen Lane and Newport Lane for the duration of the side street road closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the north side of Kings Row.
  • On-street parking is closed during daytime working hours on Kings Row (7 a.m. to 5 p.m.). Residents are encouraged to park in driveways or along side streets. Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

September 10, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

 

Friday 9/10

Slurry Seal
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Spice Islands Drive: Greg Street to Franklin Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Prater Way: View Street to Pyramid Way
Moana Lane: US580 to Neil Road
First Street: Arlington Avenue to Sierra Street

Saturday 9/11

Slurry Seal
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard

Sunday 9/12

No Work

Monday 9/13

Slurry Seal
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
(Various project streets second coat)

Tuesday 9/14

Slurry Seal
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
(Various project streets second coat)

Wednesday 9/15

Slurry Seal
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
(Various project streets second coat)

Thursday 9/16

Slurry Seal
Battle Born Way: Galletti Way to Victorian Avenue

Striping (Night Work – 7:00PM – 7:00AM)
Battle Born Way: Galletti Way to Victorian Avenue
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard
(Various project streets second coat)

Friday 9/17

Scratch Course
Panther Drive: Virginia Street to Western Road

Striping (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
(Various project streets second coat)

Saturday 9/18

Slurry Seal
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Meredeth Way & Kleppe Lane
  • 7th Street and Keystone Avenue (Near Raleys)
  • 7th Street and Genoa Avenue
  • Lakeside Drive & Brinkby Avenue
  • Sky Valley Drive & Mistyridge Lane
  • Neil Road and Moana Lane
  • South Virginia Street and Meadowwood Mall
  • Double Diamond & Sandhill Road (DMV)

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete sidewalk and utility work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Construction is in progress along the southside of Newport Lane.

Travelers should expect isolated lane closures and one-way flagging while construction crews complete demolition, driveway, and sidewalk work.

Additionally, in order to complete the removal/replacement of the exisiting pedestrian ramps and install new storm drain along the southside of Newport Lane, access to Newport Lane from La France Lane and Collins Circle  will be closed during the day while construction activies are ongoing.

To maintain resident access, a detour will be provided via Sagehen Lane and Newport Lane for the duration of the side street road closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.

 

  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking will NOT be allowed in the work zone during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

September 3, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

 

Friday 9/3

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
La Posada Drive: RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Saturday 9/4

No work

Sunday 9/5

No Work

Monday 9/6

No Work

Tuesday 9/7

Slurry Seal
Fourth Street: West Street to Galletti Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Moana Lane: US580 to Neil Road
First Street: Arlington Avenue to Sierra Street

Striping (Night Work – 7:00PM – 7:00AM)
Moana Lane: Plumas Street to Neil Road
First Street: Arlington Avenue to Sierra Street

Wednesday 9/8

Slurry Seal
Fourth Street: West Street to Galletti Way
Calle De Oro Parkway: Cordoba Boulevard to Cordoba Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Moana Lane: Plumas Street to US580

Striping (Night Work – 7:00PM – 7:00AM)
Calle De Oro Parkway: Cordoba Boulevard to Cordoba Boulevard
First Street: Arlington Avenue to Sierra Street

Thursday 9/9

Calle De Oro Parkway: Cordoba Boulevard to Cordoba Boulevard
Spice Islands Drive: Greg Street to Franklin Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Calle De Oro Parkway: Cordoba Boulevard to Cordoba Boulevard
Moana Lane: Plumas Street to US580
Prater Way: View Street to Pyramid Way

Friday 9/10

Slurry Seal
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Spice Islands Drive: Greg Street to Franklin Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
Calle De La Plata: Pyramid Highway to Isidor Court
Isidor Court: Calle De La Plata to Circuit Court
Prater Way: View Street to Pyramid Way
Moana Lane: US580 to Neil Road
First Street: Arlington Avenue to Sierra Street

Saturday 9/11

Slurry Seal
Kiley Parkway East: Sparks Boulevard to Windmill Farms Parkway
Kiley Parkway West: Pyramid Highway to Sparks Boulevard

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • 9th Street & Sutro Street
  • 4th Street & Morrill Avenue
  • Locust Street & Crampton Street
  • Locust Street & Capitol Hill Avenue
  • Meredeth Way & Kleppe Lane
  • 7th Street and Keystone Avenue (Near Raleys)
  • Lakeside Drive & Brinkby Avenue

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

The road re-opens to vehicle traffic starting September 3, 2021. Travelers should expect isolated shoulder closures and one-way flagging while construction crews complete sidewalk and utility work.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street.

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Construction is in progress along the southside of Newport Lane.

Travelers should expect isolated lane closures and one-way flagging while construction crews complete demolition, driveway, and sidewalk work.

Additionally, in order to complete the removal/replacement of the exisiting pedestrian ramps and install new storm drain along the southside of Newport Lane, access to Newport Lane from La France Lane and Collins Circle  will be closed during the day while construction activies are ongoing.

To maintain resident access, a detour will be provided via Sagehen Lane and Newport Lane for the duration of the side street road closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.

  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.

 

  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking will NOT be allowed in the work zone during during non-working hours (5 p.m. through 7 a.m.) starting September 7, 2021, at 5 p.m. Vehicles parked in the work zone will be towed.

 

  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

August 30, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Monday 8/30

Slurry Seal
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to E of Veterans Parkway
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Tuesday 8/31

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Wednesday 9/1

Slurry Seal (Night Work – 7:00PM – 7:00AM)
La Posada Drive: RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Thursday 9/2

Slurry Seal (Night Work – 7:00PM – 7:00AM)
La Posada Drive: 360 East of RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
La Posada Drive: RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive

Friday 9/3

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
La Posada Drive: RAB to Pyramid Highway
Cordoba Boulevard: La Posada Drive to La Posada Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Silverada Boulevard & Tybo Avenue
  • 9th Street & Sutro Street
  • 4th Street & Morrill Avenue
  • Locust Street & Crampton Street
  • Locust Street & Capitol Hill Avenue
  • Meredeth Way & Kleppe Lane

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

In order to complete roadway pulverization and paving, West Golden Valley Road remains closed to traffic from Yorkshire Drive to North Virginia Street until September 3rd, 2021.

To maintain resident access, a detour will be provided via Yorkshire Drive and Lancaster Drive for the duration of the road closure.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • North side of Lemmon Drive from North Virginia Street to US 395 southbound off-ramp
  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street

 

NEWPORT LANE
RTC Project Manager, Roy Flores, P.E. – (775) 335-1881

Construction is in progress along the southside of Newport Lane.

Thursday 9/2 and Friday 9/3
In order to complete the removal/replacement of the exisiting pedestrian ramps and install new storm drain along the southside of Newport Lane, access to Newport Lane from La France Lane and Collins Circle  will be closed during the day while construction activies are ongoing. To maintain resident access, a detour will be provided via Sagehen Lane and Newport Lane for the duration of the side street road closure.

 

TE SPOT 10 – NORTH
RTC Project Manager, Andrew Jayankura, P.E., PTOE – (775) 332-2139

  • Construction is in progress at the intersection of Battle Born Way-El Rancho Drive at Victorian Avenue.
  • Expect intermittent lane closes around the intersection as construction progresses. Construction is expected to be completed in Mid-October.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

August 20, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 8/20

Slurry Seal
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way

Slurry Seal (Night Work – 7:00PM – 7:00AM
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Second Street: Keyston Avenue to Virginia Street

Saturday 8/21

Slurry Seal
Sunshine Lane: Mill Street to Second Street
Plumas Street: Ridgeview Drive to Ridgeview Drive

Sunday 8/22

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Sunshine Lane: Mill Street to Second Street
Plumas Street: Ridgeview Drive to Ridgeview Drive
Nugget Avenue: Pyramid Way to Victorian Plaza Circle
Sixth Street: Ralston Street to Virginia Street

Monday 8/23

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way

Tuesday 8/24

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Sunshine Lane: Mill Street to Second Street
Plumas Street: Ridgeview Drive to Ridgeview Drive

Wednesday 8/25

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Thursday 8/26

Slurry Seal
McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to 444’ E of Veterans Parkway
Nugget Avenue: Pyramid Way to Victorian Plaza Circle
Sixth Street: Ralston Street to Virginia Street
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway

Friday 8/27

Slurry Seal
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Prater Way: View Street to Pyramid Way

Striping (Night Work – 7:00PM – 7:00AM)
McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Second Street: Keystone Avenue to Virginia Street

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Neil Road and Catalina Drive
  • Industrial Way & Greg Street
  • ElRancho Drive & Clinton Street
  • Silverada Boulevard & Tybo Avenue
  • 9th Street & Sutro Street
  • 4th Street & Morrill Avenue
  • Locust Street & Crampton Street
  • Locust Street & Capitol Hill Avenue

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

In order to complete roadway pulverization and paving, West Golden Valley Road will be completely closed to traffic from Yorkshire Drive to North Virginia Street starting Monday, August 23 extending through September 3, 2021.

To maintain resident access, a detour will be provided via Yorkshire Drive and Lancaster Drive for the duration of the road closure.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • North side of Lemmon Drive from North Virginia to US 395 southbound off-ramp
  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work)
  • Lake Street from First Street to Second Street

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

August 13, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 8/13

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Steneri Way: Freeport Boulevard to Glendale Avenue

Striping (Night Work – 7:00PM – 7:00AM)
Freeport Boulevard: 21st Street to Stanford Way
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Steneri Way: Freeport Boulevard to Glendale Avenue

Saturday 8/14

No work scheduled.

Sunday 8/15

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Linda Way: Coney Island Drive to Glendale Avenue
Crane Way: 18th Street to Bridge Deck
Icehouse Avenue: end to end
Wolverine Way: Glendale Avenue to Stanford Way
International Place: Glendale Avenue to Icehouse Avenue

Monday 8/16

Chip Seal
McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Linda Way: Coney Island Drive to Glendale Avenue

Tuesday 8/17

Chip Seal
McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard
Slurry Seal
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way

Wednesday 8/18

Slurry Seal
Second Street: Keystone Avenue to Virginia Street

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Second Street: Keystone Avenue to Virginia Street
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way

Thursday 8/19

Slurry Seal
Nugget Avenue: Pyramid Way to Victorian Plaza Circle
Sixth Street: Ralston Street to Virginia Street
Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Nugget Avenue: Pyramid Way to Victorian Plaza Circle
Sixth Street: Ralston Street to Virginia Street

Friday 8/20

Slurry Seal
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way

Slurry Seal (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Rosewood Clubhouse to Boynton Slough Bridge
Mira Loma Drive: Veterans Parkway to Veterans Parkway
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Second Street: Keystone Avenue to Virginia Street

Saturday 8/21

Slurry Seal
Sunshine Lane: Mill Street to Second Street
Plumas Street: Ridgeview Drive to Ridgeview Drive

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • Neil Road and Catalina Drive
  • Industrial Way & Greg Street
  • ElRancho Drive & Clinton Street
  • Virginia Street & Planetarium
  • Silverada Boulevard & Tybo Avenue
  • 9th Street & Sutro Street
  • 4th Street & Morrill Avenue

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures, lane shifts, and one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is in progress at the following locations:

  • North side of Lemmon Drive from North Virginia to US 395 southbound off-ramp (Night Work).
  • Rock Boulevard between Prater Way and Glendale Avenue (Night Work).

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
    • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.
  • Look for sidewalk closures and pedestrian detours within the work zone.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

 

August 6, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Sunday 8/8

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard

Striping (Night Work – 7:00PM – 7:00AM)

Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Golden Valley Drive: Spearhead Way to Seventh Ave
Vassar Street: Virginia Street to Kietzke Lane
Coney Island Drive: Marieta Way to Stanford Way
Southern Way: Greg Street to Freeport Boulevard

Monday 8/9

Micro-Milling

McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard

Striping (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard
Coney Island Drive: Marieta Way to Stanford Way
Southern Way: Greg Street to Freeport Boulevard

 

Tuesday 8/10

Micro-Milling

McCourry Boulevard: Northwood Boulevard to SR 431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Freeport Boulevard: 21st Street to Stanford Way

Striping (Night Work – 7:00PM – 7:00AM)

Redfield Parkway: Kietzke Lane to Virginia Street
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Wednesday 8/11

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Freeport Boulevard: 21st Street to Stanford Way

Striping (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard
Freeport Boulevard: 21st Street to Stanford Way

 

Thursday 8/12

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Crane Way: 18th Street to Bridge Deck
Icehouse Avenue: End to End
Wolverine Way: Glendale Avenue to Stanford Way
International Place: Glendale Avenue to Icehouse Avenue

Striping (Night Work – 7:00PM – 7:00AM)

Baring Boulevard: McCarran Boulevard to Vista Boulevard
Crane Way: 18th Street to Bridge Deck
Icehouse Avenue: End to End
Wolverine Way: Glendale Avenue to Stanford Way
International Place: Glendale Avenue to Icehouse Avenue

Friday 8/13

Slurry Seal (Night Work – 7:00PM – 7:00AM)

Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Steneri Way: Freeport Boulevard to Glendale Avenue

Striping (Night Work – 7:00PM – 7:00AM)

Freeport Boulevard: 21st Street to Stanford Way
Rock Boulevard: Hymer Avenue to Glendale Avenue
Stanford Way: Glendale Avenue to Railroad
Steneri Way: Freeport Boulevard to Glendale Avenue

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • Neil Road and Catalina Drive
  • Industrial & Greg Street
  • ElRancho Drive & Clinton Street
  • Virginia St. & Planetarium
  • Silverada Blvd & Tybo Ave

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures, lane shifts, and one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Work on north side of Lemmon Drive from North Virginia to US 395 southbound off ramp. This portion of the contract is night work.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
  • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

This week drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

This project is complete.

 

July 30, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/30

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Golden Valley Drive: Spearhead Way to Seventh Ave

Striping (Night Work – 7:00PM – 7:00AM)
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Saturday 7/31

Slurry Seal
Coney Island Drive: Marieta Way to Stanford Way
Southern Way: Greg Street to Freeport Boulevard

Monday 8/2 through Friday 8/6

No Work Scheduled

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • York Way & Pyramid Way
  • Neil Road and Catalina Drive
  • Industrial & Greg Street

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction continues on Golden Valley Road between North Virginia Street and Yorkshire Drive.

Travelers should expect isolated shoulder closures, lane shifts, and one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Begin work on north side of Lemmon Drive from North Virginia to US 395 southbound off ramp. This portion of the contract is night work.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
  • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.

 

LEMMON DRIVE SEGMENT 1 PROJECT – US 395 TO MILITARY ROAD
RTC Project Manager, Judy Tortelli, P.E. – (775) 335-1824

 Q&D continues work on the new retaining wall near Walgreens.

  • Drivers may see shoulder and lane closures on Lemmon Drive from Sky Vista Parkway/Buck Drive to just east of the Walgreens driveway during daytime working hours.
  • Access to Walgreens driveway and the access road from Lemmon Drive will be closed for approximately four months.  Please use Sky Vista Parkway to access Walgreens.

Look Ahead and Reduced Speed Limit – beginning the week of August 9

Drivers can expect to see additional traffic control including orange barrels on the outside lanes of Lemmon Drive from Sky Vista Parkway/Buck Drive to Military Road as crews prepare for roadway widening.

  • Lane and shoulder widths will be reduced.
  • Business access will be maintained.
  • The speed limit will be reduced to 35 MPH through the work zone.
  • Temporary roadway striping will be completed in one overnight shift to minimize daytime traffic impacts.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

This project is complete.

 

July 23, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/23

Slurry Seal
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Striping
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Saturday 7/24

Slurry Seal
Mae Anne Avenue: Robb Drive to Quail Run Road

Sunday 7/25

Striping (Night Work – 7:00PM – 7:00AM)
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Monday 7/26

Slurry Seal
Redfield Parkway: Kietzke Lane to Virginia Street

Striping (Night Work – 7:00PM – 7:00AM)
Redfield Parkway: Kietzke Lane to Virginia Street
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Tuesday 7/27

Slurry Seal
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Striping (Night Work – 7:00PM – 7:00AM)
Redfield Parkway: Kietzke Lane to Virginia Street
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Wednesday 7/28

Slurry Seal
Arrowcreek Parkway: Thomas Creek to Private Entrance

Striping (Night Work – 7:00PM – 7:00AM)
Arrowcreek Parkway: Thomas Creek to Private Entrance
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Thursday 7/29

Slurry Seal
Vassar Street: Virginia Street to Kietzke Lane
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Golden Valley Drive: Spearhead Way to Seventh Ave
 
Striping (Night Work – 7:00PM – 7:00AM)
Vassar Street: Virginia Street to Kietzke Lane
Redfield Parkway: Kietzke Lane to Virginia Street

Friday 7/30

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Golden Valley Drive: Spearhead Way to Seventh Ave

Striping (Night Work – 7:00PM – 7:00AM)
Seventh Avenue: Sun Valley Drive to Golden Valley Drive
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street

Saturday 7/31

Slurry Seal
Coney Island Drive: Marieta Way to Stanford Way
Southern Way: Greg Street to Freeport Boulevard

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • York Way & Pyramid Way
  • Neil Road and Catalina Drive

Work will include roadside construction of bus stop pads and sidewalk.   Temporary bus stops are available for bus riders during construction. Drivers should expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction will begin on Golden Valley Road between North Virginia Street and Yorkshire Drive beginning July 26, 2021.

Travelers should expect isolated shoulder closures, lane shifts, and one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction in progress along Rock Boulevard. This portion of the contract is night work.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
  • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

July 16, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/16

Slurry Seal
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Striping
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Saturday 7/17

Slurry Seal
Mae Anne Avenue: Robb Drive to Quail Run Road

Sunday 7/18

Striping (Night Work – 7:00PM – 7:00AM)
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

Monday 7/19

Pavement Crack Sealing
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
McCourry Boulevard: Northwood Boulevard to SR431
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal
Gentry Way: Virginia Street to Kietzke Lane
Grove Street: Wrondel Way to Kietzke Lane

Striping (Night Work – 7:00PM – 7:00AM)
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road
Gentry Way: Virginia Street to Kietzke Lane
Grove Street: Wrondel Way to Kietzke Lane

Tuesday 7/20

Slurry Seal
Airmotive Way: Villanova Street to Terminal Way
Harvard Way: Automotive Way to Market Street

Striping (Night Work – 7:00PM – 7:00AM)
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Airmotive Way: Villanova Street to Terminal Way
Harvard Way: Automotive Way to Market Street

Wednesday 7/21

Slurry Seal
Lymberry Street: Cadillac Place to Lakeside Drive
Yori Avenue: Moana Lane to Gentry Way

Striping (Night Work – 7:00PM – 7:00AM)
Mae Anne Avenue: Robb Drive to Quail Run Road
Lymberry Street: Cadillac Place to Lakeside Drive
Yori Avenue: Moana Lane to Gentry Way

Thursday 7/22

Slurry Seal
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Striping
Gentry Way: Virginia Street to Kietzke Lane
Grove Street: Wrondel Way to Kietzke Lane
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Friday 7/23

Slurry Seal
Redfield Parkway: Kietzke Lane to Virginia Street

Striping
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Susileen Drive: Marthiam Avenue to Meridian Lane

Saturday 7/24

Slurry Seal
Sunshine Lane: Mill Street to end

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • York Way & Pyramid Way
  • Neil Road and Catalina Drive

Work will include roadside construction of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

GOLDEN VALLEY ROAD REHABILITATION PROJECT – YORKSHIRE DRIVE TO NORTH VIRGINIA STREET
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction will begin on Golden Valley Road between North Virginia Street and Yorkshire Drive beginning July 19, 2021.

Travelers should expect shoulder closures, lane shifts, and isolated one-way flagging during this stage of construction.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction in progress along Rock Boulevard.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation work in progress.

  • Traffic control includes transition to temporary lanes along the south side of Kings Row.
  • On-street parking is closed on Kings Row – residents are encouraged to park in driveways or along side streets.
  • On-street parking is allowed during non-working hours (5 p.m. through 7 a.m.). Vehicles parked in the work zone during work hours will be towed.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

July 9, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/9

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Striping
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Saturday 7/10

No work is scheduled

Sunday 7/11

Striping (Night Work – 7:00PM – 7:00AM)
Red Rock Road: US 395 to Moya Boulevard

Monday 7/12

Slurry Seal
Mira Loma Drive: Longley Lane to McCarran Boulevard

Striping (Night Work – 7:00PM – 7:00AM)
Mira Loma Drive: Longley Lane to Veterans Parkway
Parr Boulevard: Virginia Street to US 395

Tuesday 7/13

Slurry Seal
Sutro Street: Kuenzli Street to McCarran Boulevard

Striping (Night Work – 7:00PM – 7:00AM)
Parr Boulevard: Virginia Street to US 395

Wednesday 7/14

Slurry Seal
Sutro Street: Kuenzli Street to McCarran Boulevard

Striping (Night Work – 7:00PM – 7:00AM)
Sutro Street: Kuenzli Street to McCarran Boulevard

Thursday 7/15

Slurry Seal
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Striping
Mira Loma Drive: Longley Lane to Veterans Parkway

Friday 7/16

Slurry Seal
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Striping
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Saturday 7/17

Slurry Seal
Mae Anne Avenue: Robb Drive to Quail Run Road

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada
  • North Virginia Street at Wellington Way
  • York Way & Pyramid Way
  • Neil Road and Catalina Drive

Work will include roadside construction of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is scheduled to begin July 11, 2021, along Rock Boulevard.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Roadway and sidewalk rehabilitation is in progress.

Traffic control includes transition to temporary lanes along the south side of Kings Row.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

July 2, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 7/2

Pavement Patching
Kuenzli Street: Wells Avenue to Second Street
Fourth Street: West Street to Galletti Way

Striping (Night Work – 7:00PM – 7:00AM)
White Lake Parkway: HWY 395 to Village Parkway

Saturday, Sunday, Monday 7/3 – 5

No work is scheduled

Tuesday 7/6

Pavement Patching
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Mae Anne Avenue: Robb Drive to Quail Run Road
Sharlands Avenue: Mae Anne Avenue to Robb Drive

Slurry Seal
Parr Boulevard: Virginia Street to US 395

Crack Seal
Mira Loma Drive: Longley Lane to Rosehill Court
Pembroke Drive: Bullock Road to Piping Rock Drive
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway
Arrowcreek Parkway: Thomas Creek to private entrance

Wednesday 7/7

Pavement Patching
Country Club Drive: Lakeshore Boulevard to Tahoe Boulevard
McCourry Boulevard: Northwood Boulevard SR 431

Slurry Seal
Parr Boulevard: Virginia Street to US 395

Crack Seal
Mira Loma Drive: Longley Lane to Rosehill Court
Pembroke Drive: Bullock Road to Piping Rock Drive
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway
Arrowcreek Parkway: Thomas Creek to private entrance

Striping (Night Work – 7:00PM – 7:00AM)
Parr Boulevard: Virginia Street to US 395

Thursday 7/8

Pavement Patching
Village Boulevard: Lakeshore Boulevard to Tahoe Boulevard

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Crack Seal
Mira Loma Drive: Longley Lane to Rosehill Court
Pembroke Drive: Bullock Road to Piping Rock Drive
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Damonte Ranch Parkway: Double R Boulevard to Steamboat Parkway
Arrowcreek Parkway: Thomas Creek to private entrance

Striping
Parr Boulevard: Virginia Street to US 395
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Friday 7/9

Slurry Seal
Seventh Avenue: Sun Valley Drive to Golden Valley Road

Striping
Seventh Avenue: Sun Valley Drive to Golden Valley Road

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada

Work will include roadside construction of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Construction is scheduled to begin July 11, 2021.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Isolated utility improvement work is in progress.

Traffic control includes isolated lane shifts and flagger controls within the project area.

Later in the week, traffic control will transition to temporary lanes along the south side of Kings Row.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

June 25, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Friday 6/25

Slurry Seal
Village Parkway: Cold Springs Drive to Village Center Drive

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

Saturday and Sunday 6/26 – 27

No work is scheduled

Monday 6/28

Slurry Seal
Village Parkway: Cold Springs Drive to Village Center Drive

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

Tuesday 6/29

Slurry Seal
White Lake Parkway: HWY 395 to Village Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

Wednesday 6/30

Pavement Patching
Sutro Street: Kuenzli Street to McCarran Boulevard

Slurry Seal
White Lake Parkway: HWY 395 to Village Parkway

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

Thursday 7/1

Pavement Patching
Sutro Street: Kuenzli Street to McCarran Boulevard

Slurry Seal
White Lake Parkway: HWY 395 to Village Parkway

Striping (Night Work – 7:00PM – 7:00AM)
White Lake Parkway: HWY 395 to Village Parkway

Friday 7/2

Pavement Patching
Kuenzli Street: Wells Avenue to Second Street
Fourth Street: West Street to Galletti Way

Striping (Night Work – 7:00PM – 7:00AM)
White Lake Parkway: HWY 395 to Village Parkway

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction is in progress at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 7th Avenue
  • Lupin Drive and 6th Avenue
  • North Virginia Street at CARE Chest of Sierra Nevada

Work will include roadside construction of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting was awarded the construction contract.  Construction is scheduled to begin July 6, 2021.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Isolated utility improvement work is in progress.

Traffic control includes isolated lane shifts and flagger controls within the project area.

Later in the week, traffic control will transition to temporary lanes along the south side of Kings Row.

 

RENO CONSOLIDATED 21-01 – LUND LANE, YUMA LANE, ARMSTRONG LANE
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Construction is complete and the roadways are open without restrictions.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Minor traffic control will be in place on Packer Way.  Business access is open.

Work is substantially complete.  Work on punch list items will take place over the next couple of weeks.

 

June 18, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Sunday 6/20

Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Grove Street: Wrondel Way to Kietzke Lane
Lymbery Street: Cadillac Place to Lakeside Drive
Gentry Way: Virginia Street to Kietzke Lane
Moana Lane: Plumas Street to Neil Road
Yori Way: Moana Lane to Gentry Way
Redfield Parkway: Kietzke Lane to Virginia Street
Plumas Street: Ridgeview Drive to 596’ S Ridgeview Drive
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

Monday 6/21

Pavement Patching
Liberty Street: Arlington Avenue to Ryland Street

Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Grove Street: Wrondel Way to Kietzke Lane
Lymbery Street: Cadillac Place to Lakeside Drive
Gentry Way: Virginia Street to Kietzke Lane
Moana Lane: Plumas Street to Neil Road
Yori Way: Moana Lane to Gentry Way
Redfield Parkway: Kietzke Lane to Virginia Street
Plumas Street: Ridgeview Drive to 596’ S Ridgeview Drive
Susileen Drive: Marthiam Avenue to Meridian Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way
Sky Mountain Drive: McCarran Boulevard to Summit Ridge Drive
Sharlands Avenue: Mae Anne Avenue to Robb Drive
Mae Anne Avenue: Robb Drive to Quail Run Road

Tuesday 6/22

Pavement Patching
First Street: Arlington Avenue to Sierra Street
Second Street: Keystone Avenue to Virginia Street

Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Bullock Road to Piping Rock Drive
Mira Loma Drive: Longley Lane to Rosehill Court
Damonte Ranch Parkway: I580 NB Exit Ramp to End of Pavement
Arrowcreek Parkway: Thomas Creek to Private Gate

Wednesday 6/23

Pavement Patching
Mira Loma Drive: Longley Lane to Rosehill Court
Airmotive Way: Villanova Street to Terminal Way
Harvard Way: Automotive Way to Market Street
Sunshine Lane: Mill Street to End Cul-De-Sac

Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Veterans Parkway: South Meadows Parkway to Pembroke Drive
Pembroke Drive: Bullock Road to Piping Rock Drive
Mira Loma Drive: Longley Lane to Rosehill Court
Damonte Ranch Parkway: I580 NB Exit Ramp to End of Pavement
Arrowcreek Parkway: Thomas Creek to Private Gate

Thursday 6/24

Slurry Seal
Village Parkway: Cold Springs Drive to Village Center Drive

Friday 6/25

Slurry Seal
Village Parkway: Cold Springs Drive to Village Center Drive

Striping (Night Work – 7:00PM – 7:00AM)
Village Parkway: Cold Springs Drive to Village Center Drive

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction of this project will begin Monday, June 14, 2021 at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 6th Avenue

Work will include roadside replacement of bus stop pads and sidewalk.   Expect isolated shoulder closures and lane shifts.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting was awarded the contract.  Construction is scheduled to begin July 6, 2021.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Ongoing construction work will include isolated utility improvements followed by complete reconstruction of sidewalk and roadway.

Traffic control will include isolated lane shifts and flagger controls within project area during utility work.

 

RENO CONSOLIDATED 21-01 – LUND LANE, YUMA LANE, ARMSTRONG LANE
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane (Yuma Lane to Sunsileen Drive) and Yuma Lane (Armstrong Lane to Hunter Lake Drive) construction in progress.

Roadway closure to through traffic starting April 12 through mid-June 2021, for roadway rehabilitation.  Follow detour around construction project.  Project is expected to be completed by end of June, 2021.

 

SPARKS CONSOLIDATED 21-01 – PACKER WAY AND WILD ISLAND COURT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Construction in progress.

Traffic Control will be in place on Packer Way.  Business access will be maintained; follow directional signage.

Paving will take place on Sunday, June 20, 2021.

 

June 10, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

WEEK 4

Sunday 6/13/2021
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard

Monday 6/14/2021
Pavement Patching
York Way: Rock Boulevard to McCarran Boulevard
Nugget Avenue: Victorian Plaza Circle (West) to Pyramid Highway
Stanford Way: Railroad Crossing to Glendale Avenue
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard

Tuesday 6/15/2021
Pavement Patching
Damonte Ranch Parkway: I580 NB Exit Ramp to End of Pavement
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
First Street: Arlington Avenue to Sierra Street
Fourth Street: West Street to Galletti
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street
Parr Boulevard: Virginia Street to US395
Second Street: Keystone Street to Virginia Street
Sixth Street: Ralston Street to Virginia Street
Sunshine Lane: Mill Street to Cul-De-Sac
Sutro Street: Second Street to McCarran Boulevard

Wednesday 6/16/2021
Pavement Patching
Redfield Parkway: Virginia Street to Kietzke Lane
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
First Street: Arlington Avenue to Sierra Street
Fourth Street: West Street to Galletti
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street
Parr Boulevard: Virginia Street to US395
Second Street: Keystone Street to Virginia Street
Sixth Street: Ralston Street to Virginia Street
Sunshine Lane: Mill Street to Cul-De-Sac
Sutro Street: Second Street to McCarran Boulevard

Thursday 6/17/2021
Pavement Patching
Moana Lane: Plumas Street to Neil Road
Lymbery Street: Cadillac Place to Lakeside Drive
Pavement Crack Sealing (Night Work – 7:00PM – 7:00AM)
First Street: Arlington Avenue to Sierra Street
Fourth Street: West Street to Galletti
Kuenzli Street: Wells Avenue to Second Street
Liberty Street: Arlington Avenue to Ryland Street
Parr Boulevard: Virginia Street to US395
Second Street: Keystone Street to Virginia Street
Sixth Street: Ralston Street to Virginia Street
Sunshine Lane: Mill Street to Cul-De-Sac
Sutro Street: Second Street to McCarran Boulevard

Friday 6/18/2021
Pavement Patching
Gentry Way: Virginia Street to Kietzke Lane
Grove Street: Wrondel Way to Kietzke Lane
Caughlin Parkway: McCarran Boulevard to Sierra Crest Way

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting April 12, 2021 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Traffic Control will be in place on Packer Way starting May 17, 2021. Business access will be maintained; follow directional signage.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From 7th Avenue to Highland Ranch Parkway:

  • Construction completed.
  • Road open with no restrictions.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract and construction will begin July 6, 2021.

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Construction of this project starts June 7, 2021 work will include isolated utility improvements followed by complete reconstruction of sidewalk and roadway.

  • Traffic control will include isolated lane shifts within project area during utility work.

 

BUS STOP IMPROVEMENT AND CONNECTIVITY PROGRAM (ICP) PHASE 2
RTC Project Manager, Sara Going, P.E. – (775) 335-1897

Construction of this project will begin Monday, June 14, 2021 at the following locations:

  • Moya Boulevard and Lear Boulevard
  • Stead Boulevard and Mt. Anderson Street
  • Lupin Drive and 8th Avenue
  • Lupin Drive and 6th Avenue

Work will include roadside replacement of bus stop pads and sidewalk.

  • Traffic control will include isolated shoulder closures and lane shifts.

 

June 3, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

WEEK 2

Thursday 6/3/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E.Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

Friday 6/4/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

WEEK 3

Monday 6/7/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker LanE
Pavement Patching
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp

Tuesday 6/8/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevar
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane
Pavement Patching
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Susileen Drive: Marthiam Avenue to Meridian Lane

Wednesday 6/9/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane
Pavement Patching
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
York Way: Rock Boulevard to McCarran Boulevard
Nugget Avenue: Victorian Plaza Circle (West) to Pyramid Highway
Stanford Way: Railroad Crossing to Glendale Avenue

Thursday 6/10/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane
Pavement Patching
Isidor Court: West Calle De La Plata to Circuit Court
La Posada Drive: Pyramid Highway to Omni Drive
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Wolverine Way: Glendale Avenue to Stanford Way
Coney Island Drive: Marietta Way to Stanford Way
Spice Island Drive: Greg Street to Franklin Way
Mira Loma Drive: Longley Lane to Veterans Parkway

Friday 6/11/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane
Pavement Patching
Baring Boulevard: McCarran Boulevard to Vista Boulevard
East Greenbrae Drive: Howard Drive to Prater Way
Prater Way: View Street to Pyramid Highway

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting April 12, 2021 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Traffic Control will be in place on Packer Way starting May 17, 2021. Business access will be maintained; follow directional signage.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From 7th Avenue to Highland Ranch Parkway:

  • Construction completed.
  • Road open with no restrictions.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract and construction will begin July 6, 2021.

 

 

KINGS ROW REHABILITATION PROJECT – KEYSTONE AVENUE TO WYOMING AVENUE
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

Construction of this project starts June 7, 2021 work will include isolated utility improvements followed by complete reconstruction of sidewalk and roadway.

  • Traffic control will include isolated lane shifts within project area during utility work.

 

 

 

 

May 27, 2021

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

WEEK 2

Monday 5/31/2021
NO WORK SCHEDULED

Tuesday 6/1/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

Wednesday 6/2/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

Thursday 6/3/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E.Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

Friday 6/4/2021
Pavement Crack Sealing
Cordoba Boulevard: La Posada Drive to Calle De Oro Parkway
La Posada Drive: Pyramid Highway to Omni Drive
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)
Kiley Parkway: Pyramid Highway to Windmill Farms Parkway
Baring Boulevard: McCarran Boulevard to Vista Boulevard
York Way: Rock Boulevard to McCarran Boulevard
E. Greenbrae Drive: Howard Drive to Prater Way
Susileen Drive: Marthiam Avenue to Meridian Lane
Vassar Street: Wells Avenue to Kietzke Lane
Mira Loma Drive: Longley Lane to Veterans Parkway
Moana Lane: Plumas Street to Baker Lane

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction projec 

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Traffic Control will be in place on Packer Way starting May 17, 2021. Business access will be maintained; follow directional signage.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:
From 7th Avenue to Highland Ranch Parkway:

  • Construction completed: minor items and miscellaneous work
  • Road open with no restrictions.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract and construction will begin July 6, 2021.

 

 

 

 

 

May 20, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

2021 RTC PREVENTIVE MAINTENANCE PROJECT
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

WEEK 1

Monday 5/24/2021
NO WORK SCHEDULED

Tuesday 5/25/2021
Pavement Crack Sealing
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Panther Drive: Virginia Street to Western Road

Wednesday 5/26/2021
Pavement Crack Sealing
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Panther Drive: Virginia Street to Western Road

Pavement Patching
Calle de Oro Parkway: Cordoba Boulevard (West) to Cordoba Boulevard (East)

Thursday 5/27/2021
Pavement Crack Sealing
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Panther Drive: Virginia Street to Western Road

Pavement Patching
Isidor Court: West Calle De La Plata to Circuit Court

Friday 5/28/2021
Pavement Crack Sealing
Village Parkway: Cold Springs Drive to Cody Court
White Lake Parkway: Village Parkway to US Highway 395 Off Ramp
Golden Valley Road: Spearhead Drive to Opal Station Drive
Seventh Avenue: Golden Valley Road to Sun Valley Boulevard
Red Rock Road: US 395 Off Ramp to Moya Boulevard
Panther Drive: Virginia Street to Western Road

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting April 12, 2021 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Traffic Control will be in place on Packer Way starting May 17, 2021. Business access will be maintained; follow directional signage.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Construction completed: minor items and miscellaneous work.
  • Sun Valley Boulevard OPEN (north/south).
  • Minor and Intermittent lane/shoulder closures at 7th Aveune intersection.

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract. Construction will begin May 30, 2021.

 

Virginia Street Bus RAPDIT Transit Extension Project
RTC Project Manager, Jeff Wilbrecht, P.E. – (775) 335-1872

North Virginia Street:

  • Sierra Street to 15th Street Southbound traffic is detoured at Sierra Street for maintenance and repair work at North Virignia Roundabout.

 

 

 

 

May 14, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Full roadway closure on Wild Island Court starting 4/12 through mid-May for roadway rehabilitation. Follow detour and business access signs for access to Outback Steakhouse and Cocoanut Bowl which are open for business. Work on Packer Way will begin mid-May.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Finishing construction and miscellaneous work
  • Sun Valley Boulevard OPEN (north/south)
  • Minor and Intermittent lane closures at 7th Avenue intersection

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting awarded contract and construction will begin May 30, 2021.

 

 

May 6, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive:

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Full roadway closure on Wild Island Court starting 4/12 through mid-May for roadway rehabilitation. Follow detour and business access signs for access to Outback Steakhouse and Cocoanut Bowl which are ope for business. Work on Packer Way will begin mid-May.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH  AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Finishing construction and miscellaneous work
  • Sun Valley Boulevard OPEN (north/south)
  • Intermittent lane closures at 7th Avenue intersection
  • Detours in place

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting is apparent low bidder, contract will be awarded April 23rd and construction will begin May 30, 2021.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Avenue and Mae Anne Avenue traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.

PROJECT IS SUBSTANTIALLY COMPLETE

 

April 29, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Full roadway closure on Wild Island Court starting 4/12 through mid-May for roadway rehabilitation. Follow detour and business access signs for access to Outback Steakhouse and Cocoanut Bowl which are ope for business. Work on Packer Way will begin mid-May.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Raising utilities, stripping and miscellaneous work
  • Sun Valley Blvd OPEN (north/south)
  • Intermittent lane closures at 7th Ave intersection
  • Detours in place

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting is apparent low bidder, contract will be awarded April 23rd and construction will begin May 30, 2021.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Aveue and Mae Anne Aveue traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.  The next phase of this project, restriping York at Pyramid will begin April 23rd.

 

April 22, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Lane to Sunsileen Drive & Yuma Lane – Armstrong Lane to Hunter Lake Drive

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SPARKS CONSOLIDATED 21-01
RTC Project Manager, Scott Gibson, P.E., – (775) 335-1874

Packer Way and Wild Island Court Reconstruction:

  • Full roadway closure on Wild Island Court starting 4/12 through mid-May for roadway rehabilitation. Follow detour and business access signs for access to Outback Steakhouse and Cocoanut Bowl which are ope for business. Work on Packer Way will begin mid-May.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Raising utilities, stripping and miscellaneous work
  • Sun Valley Boulevard OPEN (north/south)
  • Intermittent lane closures at 7th Aveue intersection
  • Detours in place

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting is apparent low bidder, contract will be awarded April 23rd and construction will begin May 30, 2021.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Aveue and Mae Anne Aveue traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.  The next phase of this project, restriping York at Pyramid will begin April 23rd.

 

April 16, 2021

Construction has been classified as an essential service by Governor Sisolak. Construction crews have implemented safety and social-distancing precautions.

 

RENO CONSOLIDATED 21-01
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Armstrong Lane – Yuma Ln to Sunsileen Dr & Yuma Ln – Armstrong Ln to Hunter Lake Dr.:

  • Full roadway closure starting 4/12 through mid-June for roadway rehabilitation. Follow detour around construction project.

 

SUN VALLEY BOULEVARD MULTI-MODAL IMPROVEMENTS – PHASE 1: 7TH AVENUE TO HIGHLAND RANCH PARKWAY
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Sun Valley Boulevard:

From Staci Way to Highland Ranch Parkway:

  • Construction completed: ADA Ramps, Curb & Gutter, Sidewalk and Drainage improvements.
  • Road open with no restrictions.

From Staci Way to 7th Avenue:

  • Paving operations and traffic signal activation
  • Sun Valley Blvd OPEN (north/south)
  • Intermittent lane closures at 7th Ave intersection
  • Detours in place

 

ITS PHASE 3 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Titan Electrical Contracting is apparent low bidder, contract will be awarded April 23rd and construction will begin May 30, 2021.

 

TE SPOT 9 – PACKAGE 1 PROJECT
RTC Project Manager, Blaine Petersen, P.E. – (775) 335-1871

Sharlands Ave. and Mae Anne Ave. traffic signal is now operational, please use caution when traveling through the area as drivers get familiar with the new traffic operations.  The next phase of this project, restriping York at Pyramid will begin April 23rd.

 

TE SPOT 9 – PACKAGE 2
RTC Project Manager, Andrew V. Jayankura, P.E., PTOE, RSP1 – (775) 332-2139

Intersection of Arlington & Mt Rose:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.

Intersection of Rock Blvd & Mill St.:

  • Construction in progress for a new traffic signal.
  • Lane and shoulder closures are expected throughout construction.