PROJECT DETAILS
RTC Project No. 311002

RTC Project Manager (PM)
Jeff Wilbrecht, P.E.
(775) 335-1872
jwilbrecht@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  to be determined

Construction Contractor:  to be determined

PROJECT DESCRIPTION
This project consists of studying and developing alternatives for the continuation of the Truckee River Shared Use Path within an approximately 2,400-foot-long segment in the southern portion of the Truckee River from John Champion Memorial Park to the east side of the US 395/IR580 overpass in Reno, Nevada.

It is anticipated design and NEPA determination will occur through 2018 with construction occurring Summer of 2019.

LATEST NEWS
Solicitation and review of RFP documents for design consultant services currently under way.

SCHEDULE
Planning:  July 2016 to December 2017
Environmental: 2018
Preliminary Design: 2018 to 2019
Final Design:  2019
Construction:  2019 to 2020

FINANCIAL INFORMATION
Total Project Estimate:  $1,200,000 to $1,600,000
Amount Approved:  $212,754
Funding Source:  RTC Sales Tax, Federal Transportation Alternatives (TA) Set Aside

Post updated on:  November 21, 2018