PROJECT DETAILS
RTC Project No. 311002

RTC Project Manager (PM)
Jeff Wilbrecht, P.E.
(775) 335-1872
jwilbrecht@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Lumos and Associates

Construction Contractor:  to be determined

PROJECT DESCRIPTION
This project consists of studying and developing alternatives for the continuation of the Truckee River Shared Use Path within an approximately 2,400-foot-long segment in the southern portion of the Truckee River from John Champion Memorial Park to the east side of the US 395/IR580 overpass in Reno, Nevada.

LATEST NEWS
Preliminary design and environmental analysis are underway. Preparation of 408 Permit application items has begun.

SCHEDULE
Planning:  July 2016 to December 2017
Environmental: 2019
Preliminary Design: 2018 to 2019
Final Design: 2019 to 2020
Construction: Project construction will be coordinated with NDOT’s SBX Project

FINANCIAL INFORMATION
Total Project Estimate:  $1,200,000 to $1,600,000
Amount Approved:  $212,754
Funding Source: RTC Fuel Tax, RTC Sales Tax, Federal Transportation Alternatives (TA) Set Aside

Post updated on:  September 26, 2019