PROJECT DETAILS
RTC Project No. 8131024

RTC Project Manager (PM)
Andrew V. Jayankura, P.E., PTOE, RSP1
(775) 332-2139
ajayankura@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: In House / Local Agencies / UNR-CATER

Construction Constractor: N/A

PROJECT DESCRIPTION
The Signal Timing 6 project is the start of the new three-year signal timing cycle. Signals completed under signal timing 5 will be re-evaluated, and re-timed to accommodate the changes in traffic demands. The goal of the project is to continue the re-timing of a 1/3 of the signals each year, and to expand signal timing plans to include weekends, holidays and special event plans if possible. The schedule of work for a typical corridor consists of the following:

• Collect traffic & signal data
• Input timings into model and evaluate existing signal timing
• Develop new timing and implement in the field
• Fine-tune timing, and conducting before-after studies.

LATEST NEWS
Next corridors for signal timing:

S. McCarran Boulevard (10 Signals) – Neil Road to Caughlin Ranch Parkway – new timing under fine-tuning.

W. McCarran Boulevard (11 Signals) – Plumb Lane to Kings Row – late August 2021.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: On going
Final Design: On going
Construction: Spring 2020 to Summer 2023

FINANCIAL INFORMATION
Total Project Estimate: $1,500,000
Funding Source: RTC Fuel Tax

 

Post updated on: July 29, 2021