PROJECT DETAILS
RTC Project No. 0247012
RTC Project Manager (PM)
Sara Going, P.E.
(775) 335-1897
sgoing@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: Kimley-Horn and Associates
Construction Contractor: To be determined
PROJECT DESCRIPTION
The project is part of RTC’s Traffic Engineering Program and includes analysis and improvements to spot locations regionwide:
(Reno) North McCarran Boulevard and 7th Street – Evaluate traffic, bus, and pedestrian circulation and safety
improvements near the intersection of McCarran Boulevard and 7th Street.
(Reno) South Virginia Street and Center Street – Pedestrian safety improvements at the roundabout.
(Reno) Vassar Street and Harvard Way – Modify intersection pavement markings to improve northbound to
westbound turning movements for RTC buses.
(Sparks) Rock Boulevard and C Street – Replace traffic signal controller cabinet and install new uninterrupted
power source (UPS).
(Sparks) North McCarran Boulevard and York Way – Replace traffic signal controller cabinet and install new
uninterrupted power source (UPS).
(Sparks) Rock Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted
power source (UPS).
(Sparks) Proctor R. Hug High School Circulation Study – Review pedestrian and circulation issues
surrounding the high school for short and long term improvements.
(Sparks) Outlets at Legends / Lincoln Way Circulation Study – Review traffic circulation and conflicts along
Lincoln Way within the Outlets at Legends development.
LATEST NEWS
The project team has completed data collection and field review for the following sites:
- North McCarran Boulevard and 7th Street, South Virginia Street and Center Street, Proctor R. Hug High School, and Outlets at
Legends / Lincoln Way.
The team is currently completing engineering studies and finalizing improvement recommendations for
each site prior to beginning design.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Summer 2023
Final Design: Winter 2023
Construction: Summer 2024
FINANCIAL INFORMATION
Total Project Estimate: $1,750, 000
Funding Source: RTC Fuel Tax
Post updated on: August 28, 2023
Traffic Signal Modification 24-01 Project Map