Traffic Signal Modifications 24-01

PROJECT DETAILS


RTC Project No. 0247012

RTC Project Manager (PM)


Sara Going, P.E.


(775) 335-1897


sgoing@rtcwashoe.com

RTC Engineering Department


(775) 348-0171

Design Firm: Kimley-Horn and Associates

Construction Contractor: To be determined

PROJECT DESCRIPTION


The project is part of RTC’s Traffic Engineering Program and includes analysis and improvements to spot locations regionwide:

(Reno) North McCarran Boulevard and 7th Street – Evaluate traffic, bus, and pedestrian circulation and safety improvements near the intersection of McCarran Boulevard and 7th Street.


(Reno) South Virginia Street and Center Street – Pedestrian safety improvements at the roundabout.


(Reno) Vassar Street and Harvard Way – Modify intersection pavement markings to improve northbound to westbound turning movements for RTC buses.


(Sparks) Rock Boulevard and C Street – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).


(Sparks) North McCarran Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).


(Sparks) Rock Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).


(Sparks) Proctor R. Hug High School Circulation Study – Review pedestrian and circulation issues surrounding the high school for short and long term improvements.


(Sparks) Outlets at Legends / Lincoln Way Circulation Study – Review traffic circulation and conflicts along Lincoln Way within the Outlets at Legends development.

LATEST NEWS


The project team has completed data collection and field review for the following sites:

  • North McCarran Boulevard and 7th Street, South Virginia Street and Center Street, Proctor R. Hug High School, and Outlets at Legends / Lincoln Way.

The team is currently completing engineering studies and finalizing improvement recommendations for each site prior to beginning design.

SCHEDULE


Planning: N/A


Environmental: N/A


Preliminary Design: Summer 2023


Final Design: Winter 2023


Construction: Summer 2024

FINANCIAL INFORMATION


Total Project Estimate:
 $1,750, 000


Funding Source: RTC Fuel Tax


Post updated on: August 28, 2023

Traffic Signal Modification 24-01 Project Map