PROJECT DETAILS
RTC Project No. 0247010

RTC Project Manager (PM)
Sara Going, P.E.
(775) 335-1897
sgoing@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Design Firm: Westwood Professional Services

Construction Contractor: To be determined

PROJECT DESCRIPTION
RTC’s Traffic Engineering Program provides traffic signal and vehicle capacity improvements region-wide. As part of this program, the Traffic Signal Modifications 22-01 project will modify the following existing intersections to improve traffic flow and accommodate growth in vehicle traffic:

  • Los Altos Parkway & Galleria Parkway – Extend westbound to southbound left turn pocket
  • El Rancho Drive & G Street – Remove split traffic signal phasing
  • Clear Acre Lane & McCarran Boulevard – Remove split traffic signal phasing
  • Galletti Way & Battle Born Way – Install new signal controller cabinet and inductive loop vehicle detection

The project will also perform an Intersection Control Evaluation to determine the most appropriate form of intersection control at La Posada Drive and Cordoba Boulevard. This is an evaluation only, and no construction is planned at this intersection within the Traffic Signal Modifications 22-01 project.

LATEST NEWS
The consultant is completing final design of the project.

SCHEDULE
Planning: Complete
Environmental: Complete
Preliminary Design: Fall 2021
Final Design: Summer 2022
Construction: Summer 2023

FINANCIAL INFORMATION
Total Project Estimate:
$1,202,471
Funding Source: RTC Fuel Tax


Post updated on: May 4, 2023

Traffic Signal Modifications Project Map