PROJECT DETAILS
RTC Project No. 0245006

RTC Project Manager (PM)
Andrew V. Jayankura, P.E., PTOE, RSP1
(775)332-2139
ajayankura@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Headway Transportation, LLC

Construction Contractor: To be determined

PROJECT DESCRIPTION
This project to include various traffic geometries and signal improvements around the Truckee Meadows. The project includes (4) four tasks:

New traffic signal at the intersection of Moana Lane at Baker Lane.
Traffic Operation improvement at the intersection of Prater Way at Fourth Street in Sparks.
Minor Traffic Operation/Geometry improvement at the intersection of Sparks Boulevard at Mesa Meadows Drive.
An Intersection Control Evaluation at the US 395/Red Rock Boulevard Interchange.

LATEST NEWS
Project is under design and construction expected to begin in early Summer 2023.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Current to November 2022
Final Design: November 2022 to February 2022
Construction: Summer 2023

FINANCIAL INFORMATION
Total Project Estimate:
$1,200,000
Funding Source: RTC Fuel Tax


Post updated on: March 16, 2023