PROJECT DESCRIPTION
This project will make  the following safety and operational improvements:

Moana Lane and Baker Lane – new traffic signal
Prater Way at Fourth Street in Sparks – traffic signal upgrades.
Sparks Boulevard at Mesa Meadows Drive –  crosswalk and intersection improvements.
An Intersection Control Evaluation at the Red Rock Road/US 395/ North Virginia Street Interchange.

LATEST NEWS
Construction contract will be open for bidding in September 2023.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: August 2022 to November 2022
Final Design: November 2022 to Summer 2023
Construction: Summer 2023 – Spring 2024

FINANCIAL INFORMATION
Total Project Estimate:
$2,210,742
Funding Source: RTC Fuel Tax


Post updated on: August 25, 2023