PROJECT DETAILS
RTC Project No. 0215006.01

RTC Project Manager (PM)
Blaine Petersen
(775) 335-1871
bpetersen@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Headway Transportation

Construction Contractor: To be determined

PROJECT DESCRIPTION
This project includes design and construction of two new traffic signals one at Mill Street and Telegraph Street and one at the intersection of Wilbur May Parkway and South Meadows Parkway.

LATEST NEWS
Project is currently in preliminary design.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: July 2021 to December 2021
Final Design: December 2021 to February 2022
Construction: September 2022 to November 2022

FINANCIAL INFORMATION
Total Project Estimate:
$ 1,300,000
Funding Source: RTC Fuel Tax

 

Post updated on: September 30, 2021