PROJECT DETAILS
RTC Project No. 0215006.01

RTC Project Manager (PM)
Blaine Petersen
(775) 335-1871
bpetersen@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Headway Transportation

Construction Contractor: To be determined

PROJECT DESCRIPTION
This project includes design and construction of two new traffic signals one at Mill Street and Telegraph Street and one at the intersection of Wilbur May Parkway and South Meadows Parkway.

LATEST NEWS
Project is currently in design phase and is scheduled for construction in Summer 2022.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: July 2021 to December 2021
Final Design: Summer 2022
Construction: Summer 2022

FINANCIAL INFORMATION
Total Project Estimate:
$ 1,200,000
Funding Source: RTC Fuel Tax


Post updated on: December 31, 2021

Traffic Signal Installations Project Map