PROJECT DETAILS
RTC Project No. 0215006.01
RTC Project Manager (PM)
Andrew V. Jayankura, P.E., PTOE, RSP1
(775) 332-2139
ajayankura@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax
Design Firm: Headway Transportation
Construction Contractor: Titan Electrical Contracting
PROJECT DESCRIPTION
This project includes design and construction of two new traffic signals, one at Mill Street and Telegraph Street and one at the intersection of Wilbur May Parkway and South Meadows Parkway. Underground work in progress at Mill Street/Telegraph Street.
LATEST NEWS
The new traffic signal at the intersection of Wilbur May Parkway and South Meadows Parkway is anticipated to be completed and active by end of January 2023.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Summer 2021
Final Design: Summer 2022
Construction: November 2022
FINANCIAL INFORMATION
Total Project Estimate: $ 1,200,000
Funding Source: RTC Fuel Tax
Post updated on: March 16, 2023