Striping modification at Pyramid Way and York Way. Installation of new traffic signal at Sharlands Avenue and Mae Anne Avenue. Investigation of improvements for southbound Vista Boulevard and Baring Boulevard. Installation of Battery Backup Systems (BBS) along Sun Valley Boulevard. Seven signalized intersections.

LATEST NEWS
Titan Electrical has been awarded the contract and construction will begin Fall/Winter 2020.

SCHEDULE
Preliminary Design: Winter 2020
Final Design: Spring 2020
Construction: Fall 2020

FINANCIAL INFORMATION
Total Project Estimate:
$ 2,000,000
Funding Source: Regional Road Impact Fee (RRIF)

 