PROJECT DETAILS
RTC Project No. 0531013

RTC Project Manager (PM)
Andrew V. Jayankura, P.E., PTOE
(775) 332-2139
ajayankura@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Kimley-Horn & Associates

Construction Contractor: to be determined

PROJECT DESCRIPTION
Package 2 includes new traffic signal at the intersection of Rock Boulevard and Edison Way.
Traffic Signal Cabinet and equipment upgrades at various locations throughout Reno and Incline Village. Traffic Intersection Control Evaluation at the intersection of W 4th Street / Mesa Park Road.

LATEST NEWS
Project is now progressing to final 100% design. Project is expected to advertise for bids in May.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Through March 2020
Final Design: April 2020 (Anticipated)
Construction: Fall 2020. Spring 2021 for the traffic signal at Rock Blvd / Edison Way

FINANCIAL INFORMATION
Total Project Estimate:
$1,489,800 (as of October 2019)
Amount Approved: $1,600,000
Funding Source: Regional Road Impact Fees (RRIF)

 

Post updated on:  March 27, 2020