PROJECT DETAILS
RTC Project No. 531013

RTC Project Manager (PM)
Andrew V. Jayankura, P.E., PTOE
(775) 332-2139
ajayankura@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  Kimley-Horn & Associates

Construction Contractor:  to be determined

PROJECT DESCRIPTION
Package 2 includes new traffic signal at the intersection of Rock Boulevard and Edison Way.  Traffic Signal Cabinet and equipment upgrades at various locations throughout Reno and Incline Village.  Traffic Intersection Control Evaluation at the intersection of W 4th Street / Mesa Park Road.

LATEST NEWS
The design and engineering during construction contract was awarded to Kimley-Horn and Associates. Preliminary design and investigation underway.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: through March 2020
Final Design:  April 2020 (Anticipated)
Construction:  Summer/Fall 2020

FINANCIAL INFORMATION
Total Project Estimate:  $1,489,800 (as of October 2019)
Amount Approved:  $1,600,000
Funding Source: Regional Road Impact Fee (RRIF)

Post updated on: October 30, 2019