PROJECT DETAILS
RTC Project No. 542037

RTC Project Manager (PM)
Blaine Petersen, P.E., PTOE
(775) 335-1871
bpetersen@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Headway Transportation

Construction Contractor: Titan Electrical Contracting, Inc.

PROJECT DESCRIPTION
Package 1 includes: new traffic signal at the intersection of Evans Avenue and Enterprise Road.

Flashing Yellow Arrow at: Keystone Avenue and 7th Street, Lincoln Way and Marina Gateway Drive, McCarran Boulevard and Neil Road, Mill Street and Kirman Avenue.

Battery backup system at: Mae Anne Avenue at Coit Plaza, Oddie Boulevard and I-580 (both sides of freeway), Wells Avenue and I-80 (both sides of freeway), Wells Avenue and 6th Street.

LATEST NEWS
Underground construction is ongoing with improvements at Prater and I80. All undergroung work will be complete by end of March. Signal pole and associated signal equipment scheduled for April/May 2020.

 

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: Fall/Winter 2018
Construction: Spring 2020

FINANCIAL INFORMATION
Total Project Estimate: $1,200,000

Amount Approved: $3,000,000 (Package 1 and package 2)
Funding Source: Regional Road Impact Fees (RRIF)

 

Post updated on: March 27, 2020