PROJECT DETAILS
RTC Project No. 542038

RTC Project Manager (PM)
Andrew V. Jayankura, P.E., PTOE
(775) 332-2139
ajayankura@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  Stantec Consulting Services, Inc.

Construction Contractor:  Titan Electrical Contractors

PROJECT DESCRIPTION
Package 2 includes: new traffic signal at the intersection of Red Rock Rd and Silver Lake Rd and extending the westbound to southbound U.S. 395 on-ramp lane pocket for more capacity and storage.

LATEST NEWS
Construction has been postponed at the intersection of Red Rock and Silver Lake until Spring of 2020. Underground utilities have been completed. Waiting for warmer temperatures to complete slurry seal. The signal is expected to be operational in Spring 2020. Construction of the McCarran portion of the project is on hold until favorable weather conditions, start is expected in Spring 2020.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design:  Spring 2019 (Completed)
Construction:  Winter 2019/Spring 2020

FINANCIAL INFORMATION
Total Project Estimate:  $1,269,563.90 (as of December 2019)
Amount Approved:  $1,300,000
Funding Source: Regional Road Impact Fee (RRIF)

Post updated on: January 27, 2020