PROJECT DETAILS
RTC Project No. 222027

RTC Project Manager (PM)
Judy Tortelli, P.E., PTOE
(775) 335-1824
jtortelli@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  CFA

Construction Contractor: to be determined

PROJECT DESCRIPTION
Rehabilitation and/or reconstruction the following streets:
• 15th Street from C Street to Prater Way
• Franklin Way from the Union Pacific Rail Road crossing to East Greg Street
• Sidewalk on the east side of El Rancho Drive from G Street to Oddie Boulevard

Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk, curb and replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing handicapped ramps, reconstruction of driveways, and other incidentals necessary for the rehabilitation and/or reconstruction of the street segments within the Project limits

LATEST NEWS
CFA is scheduled to submit 90% design plans for agency review on February 22, 2019.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: CFA submitted 50% design plans 1/4/2019
Final Design:  February 2019 to May 2019
Construction:  Anticipated May 2019 to August 2019

FINANCIAL INFORMATION
Total Project Estimate: $1.4 Million
Amount Approved:  $392,981
Funding Source: RTC Fuel Tax

Currently, the project is approved for design and engineering during construction services only.

Post updated on: March 21, 2019