PROJECT DETAILS
RTC Project No. 0532015
RTC Project Manager (PM)
Blaine Petersen
(775) 335-1871
bpetersen@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax
Design Firm: Kimley-Horn & Associates
Construction Contractor: To Be Determined
PROJECT DESCRIPTION
This project includes a new roundabout at the intersection of 4th Street and Woodland Avenue along with geometric changes to 4th Street at Mesa Park Road.
Extend southbound left turn at the intersection of South Virginia Street and Kietzke Lane
LATEST NEWS
Project is currently in preliminary design with 60% plans due May 30, 2021. 4th Street is an Nevada Department of Transportation (NDOT) maintained roadway.
SCHEDULE
Preliminary Design: Winter 2021
Final Design: Winter 2021
Construction: Spring/Summer 2022
FINANCIAL INFORMATION
Total Project Estimate: $2,700,800
Funding Source: Impact Fee