PROJECT DETAILS
RTC Project No. 0532015

RTC Project Manager (PM)
Blaine Petersen
(775) 335-1871
bpetersen@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Kimley-Horn & Associates

Construction Contractor: Sierra Nevada Construction

PROJECT DESCRIPTION
This project includes:
Package A: new roundabout at intersection of 4th Street/Woodland Avenue and geometric changes to 4th Street at Mesa Park Road.
Package B: extension of the southbound left turn at the intersection of South Virginia Street and Kietzke Lane.

Please visit 4th Street and Woodland Avenue Roundabout  for more information on the TE Spot 10 – South roundabout project.

LATEST NEWS
Construction contract awarded to Sierra Nevada Construction.  Construction to begin September 2022  with undergrounding of overhead utilities.  Main roundabout construction to begin Spring 2023.

4th Street is a Nevada Department of Transportation (NDOT) maintained roadway.

SCHEDULE
Planning: Complete
Environmental: N/A
Preliminary Design: Winter 2021
Final Design: February 2022
Construction: Summer 2023

FINANCIAL INFORMATION
Total Project Estimate:
$ 4,350,000
Funding Source: Regional Road Impact Fee (RRIF)


Post updated on: September 29, 2022

Traffic Engineering Spot 10 – SOUTH Project Map