PROJECT DETAILS
RTC Project No. 0512018
RTC Project Manager (PM)
Jayankura, Andrew
(775) 332-2139
AJayankura@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax
Design Firm: Stantec
Construction Contractor: To be determined
PROJECT DESCRIPTION
Project includes Traffic operational and equipment upgrades at the following two intersections: Clear Acre/North McCarran Boulevard, El Rancho/Victorian Avenue.
LATEST NEWS
Project construction contract has been awarded to SNC. Construction is anticipated to begin in Summer 2021, dependent on procurement of traffic signal equipment.
SCHEDULE
Preliminary Design:
Final Design: Winter 2020
Construction: Summer 2021
FINANCIAL INFORMATION
Total Project Estimate: $ 899,200
Funding Source: Impact Fee (RRIF)
Post updated on: March 31, 2021