PROJECT DETAILS
RTC Project No. 0512018

RTC Project Manager (PM)
Jayankura, Andrew
(775) 332-2139
AJayankura@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Stantec

Construction Contractor: Sierra Nevada Construction, Inc. (SNC)

PROJECT DESCRIPTION
Project includes Traffic operational and equipment upgrades at El Rancho Drive-Battle Born Way/Victorian Avenue.

LATEST NEWS
Final completion of the Project is on hold until Spring 2022 due to inclement weather.  The intersection will be open for normal operations starting October 22, 2021.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: Winter 2020
Construction: Summer 2021

FINANCIAL INFORMATION
Total Project Estimate:
924,200
Funding Source: Regional Road Impact Fee (RRIF)

 

Post updated on: November 30, 2021