PROJECT DETAILS
RTC Project No. 512013

RTC Project Manager (PM)
Maria Paz Fernandez, P.E.
(775) 335-1861
mpazfernandez@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  Stantec Consulting, Inc.

Construction Contractor:  to be determined

PROJECT DESCRIPTION
This project consists of studying and developing alternatives for the Oddie/Wells Corridor based on the findings shown in the Corridor Study performed and approved in 2013 by the RTC. This is a Complete Streets project that includes safety improvements to several modes of transportation such as sidewalks, bike lanes, comfortable and accessible public transportation stops, frequent and safe crossing opportunities, median islands, accessible pedestrian signals, curb extensions, narrower travel lanes, and more.

LATEST NEWS
Data collection, and the Environmental and Preliminary Design phase are underway.  Geotechnical Investigation and Topographic Survey has been completed.

Visit http://oddiewellsproject.com/ for information about the project and to sign up for updates.

SCHEDULE
Planning:
Complete 2013
Environmental: N/A
Preliminary Design: Fall 2019
Final Design:  Spring 2020
Construction: Summer 2020

FINANCIAL INFORMATION
T
otal Project Estimate:
Amount Approved: $1,550,000.00 PE phase
Funding Source: RTC Fuel Tax

Currently the amount approved is for the Preliminary Engineering (PE) phase only.

Post updated on:  November 21, 2018